Phillips Construction Co., Inc. v. The United States

394 F.2d 834, 184 Ct. Cl. 249, 1968 U.S. Ct. Cl. LEXIS 117
CourtUnited States Court of Claims
DecidedMay 10, 1968
Docket334-63
StatusPublished
Cited by21 cases

This text of 394 F.2d 834 (Phillips Construction Co., Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips Construction Co., Inc. v. The United States, 394 F.2d 834, 184 Ct. Cl. 249, 1968 U.S. Ct. Cl. LEXIS 117 (cc 1968).

Opinion

OPINION

PER CURIAM:

This case was referred to Trial Commissioner Lloyd Fletcher with directions to make findings of fact and recommendation for conclusions of law pursuant to the order of reference and Rule 57(a). The commissioner has done so in an opinion and report filed on March 21, 1967, wherein the facts necessary to the opinion are stated therein. Exceptions to the commissioner’s opinion, findings, and recommended conclusion of law were filed by the defendant and the case has been submitted to the court on oral argument of counsel and the briefs of the parties. Since the court agrees with the commissioner’s findings, opinion, and recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is, therefore, enti-tied to recover and judgment is entered for plaintiff in the sum of $89,000.

OPINION OF COMMISSIONER

FLETCHER, Commissioner:

The Armed Services Board of Contract Appeals held extensive hearings on this Capehart Housing Contract dispute. Based upon substantial evidence, the Board decided that this plaintiff-contractor had suffered a changed condition for which it was entitled to an equitable adjustment. The inability of the parties to agree amicably on the amount of the adjustment resulted in further hearings. Thereafter, the Board issued a second decision on quantum holding that the amount of plaintiff’s equitable adjustment should be $89,000.

Content with the Board’s decision on the merits but dissatisfied with its determination of the amount of adjustment, the plaintiff now asks this court to “proceed, realistically, to determine the amount of plaintiff’s damages resulting from the changed condition.” Its assignment of errors, therefore, has been confined to an attack on those findings of the Board relating to the amount to which plaintiff is equitably entitled.

Striking for the jugular vein, the Government now contends that its Board erred as a matter of laiv in its first decision by finding that a changed condition was encountered. Therefore, says the Government, plaintiff is not entitled to an equitable adjustment at all, much less to $89,000. Not one to place all its eggs in one basket, however, the Government adds that, assuming the existence of a changed condition, the Board’s second decision as to the proper amount of an equitable adjustment is fully supported by the evidence before it.

For the reasons stated below, I am of the opinion that, contrary to the Government’s present position, the Board’s first decision that plaintiff encountered a “changed condition” was a finding of fact rather than the resolution of a question of law. Accordingly, if that finding is supported by substan *836 tial evidence (which I believe it to be) it is final and conclusive and, therefore, plaintiff is entitled to an equitable adjustment for the changed condition. I am of the further opinion that the subsequent evidence presented to the Board as to the proper amount of such equitable adjustment will not support a figure in excess of that recommended by the Board in its second decision on quantum. I, therefore, believe that judgment for the plaintiff should be entered here in the sum of $89,000.

The Board made findings of fact which are amply supported by the evidence before it and which may be summarized as follows. As the low bidder for a typical Capehart housing project, plaintiff was awarded a contract under date of October 2, 1957, calling for the construction within 480 days 1 of 800 family housing units adjacent to the Myrtle Beach Air Force Base on the South Carolina coast. As amended, the final contract price was $12,202,842 to be paid from private funds under the usual Capehart financial arrangements with a banking institution. 2 Plaintiff substantially completed its construction work in November 1959, and the Board member who heard the ensuing dispute concluded from photographic evidence that the resulting project was one of the most attractive he had ever seen. It was a complete community composed of many houses with carports. It was well-landscaped and included several miles of paved streets and sidewalks, together with sanitary and storm drainage and utilities.

Plaintiff’s completion of the project was not easily come by. Some of the heaviest rainfall in the history of this area seriously impeded plaintiff’s construction work, and the Board found that the “quagmire” conditions existing on the site for prolonged periods during construction caused plaintiff to suffer “a considerable loss.” Plaintiff has never disputed that it assumed the risks incident to abnormal rainfall as such. But it claimed that its difficulties were greatly compounded by what it considered to be the inadequacy of the Government-designed drainage system for the project. As the Board put it in its first decision:

While recognizing water would be on the site, the chief complaint of the appellant in this case is that drainage arrangements were insufficient to disperse it. The result was that large areas became flooded where saturation of the ground continued for prolonged periods of time.
There was no dispute that the appellant accomplished work in a quagmire. Whether it was a hog-wallow or a ’Gator-hole, it is certain that workmen wore boots to wade through the mud.
During the hearing, appellant’s exhibit No. 4 was used frequently by both parties. It was a drawing of the site and showed the flood areas in red. The red part constituted approximately half of the site and affected all three mortgage areas. The two large flood areas were separated by a slightly elevated ridge in the center of the site. Natural ditches, which the appellant developed into open swales in accordance with the drawings, were approximately in the middle of the large flood areas.
The areas marked in red were flooded many times and the ground was slow to dry out after each flood. A Government witness testified that the water impounded would stay there until the cows drink it or the sun dries it up.

After noting that the soil in the area involved was such that, when saturated with water, it had to be either aerated or replaced, the Board turned its atten *837 tion to the adequacy of the storm drainage system provided in the Government’s drawings. The general scheme was to flow water down street gutters into catch basins, thence via underground pipes into on-site swales, and thence into an off-site swale connected with an outfall ditch emptying into the Atlantic Ocean.

The worst situation that faced plaintiff, said the Board, was the clogged condition of the outfall ditch. It was the key to the proper functioning of the drainage system, and when it failed to carry away the excess water, the result was prolonged ponding and flooding back on the construction site. Plaintiff was not able itself to correct this situation because the outfall ditch was located on contiguous private land not owned by the Government. However, on plaintiff’s complaints, the Government undertook to rectify the condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Betance Enterprises, Inc.
Armed Services Board of Contract Appeals, 2023
Stanley Miller Constr. Co. v. State
2010 Ohio 1488 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Net Construction, Inc. v. C & C Rehab & Construction, Inc.
256 F. Supp. 2d 350 (E.D. Pennsylvania, 2003)
Hendry Corp. v. Metropolitan Dade County
648 So. 2d 140 (District Court of Appeal of Florida, 1995)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Donald B. Murphy Contractors, Inc. v. State
696 P.2d 1270 (Court of Appeals of Washington, 1985)
Mojave Enterprises v. United States
31 Cont. Cas. Fed. 71,507 (Court of Claims, 1983)
McCormick-Selph v. United States
588 F.2d 808 (Court of Claims, 1978)
METRO. SEWERAGE COMM. v. RW Const., Inc.
255 N.W.2d 293 (Wisconsin Supreme Court, 1977)
Teitelbaum v. United States
458 F.2d 72 (Court of Claims, 1972)
Phillips Construction Co., Inc. v. The United States
440 F.2d 429 (Court of Claims, 1971)
Red Circle Corporation v. The United States
398 F.2d 836 (Court of Claims, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
394 F.2d 834, 184 Ct. Cl. 249, 1968 U.S. Ct. Cl. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-construction-co-inc-v-the-united-states-cc-1968.