Great Lakes Dredge & Dock Co. v. United States

96 F. Supp. 923, 119 Ct. Cl. 504, 1951 U.S. Ct. Cl. LEXIS 47
United States Court of Claims·Decided May 1, 1951·No. 45658·Published·Cited by 26 cases

Opinion

WHITAKER, Judge.

In our former opinion, 116 Ct.Cl. 679, 90 F.Supp. 963, 965, we held that plaintiff was “entitled to recover such amount as this court may finally determine is proper as an equitable adjustment on account of the latent conditions encountered which differed from those which plaintiff had a right to expect.” We said, however, that “plaintiff is limited to a recovery based upon the finding of the head of the department on October 30, 1937, that the latent conditions encountered which entitle plaintiff to an equitable adjustment were those conditions resulting from the fact that it had encountered ‘ground water under hydrostatic pressure * * * to a degree not contemplated by the specifications and in such concentration as to constitute a change in latent conditions within the meaning of article 4 of the contract.’ ”

When this condition was encountered, it became the duty of the contracting officer under article 4 of the contract to “make such changes in the drawings and (or) specifications as he may find necessary”; whereupon, plaintiff was entitled to “any increase or decrease of cost and (or) difference in time resulting from such changes.” However, when these conditions were encountered the contracting officer determined that they were no different from what plaintiff had reason to expect and he, therefore, refused to change the drawings and specifications or to make the equitable adjustment required. It was not until October 30, 1937, that the head of the department reversed the contracting officer and held that latent conditions had been encountered within the meaning of article 4 of the contract. This, however, was just about a month before the work was completed and, therefore, long after the time that any change could be made’in the plans or specifications, if indeed any change in the plans and specifications could have been made that would have met the changed conditions encountered.

Article 4, however, clearly contemplates that if latent conditions are encountered materially differing from those specified, in that event plaintiff is entitled to an equitable adjustment based upon the increase in cost resulting therefrom. Article 4 provides that “any increase or decrease of cost and (or) difference in time resulting from such changes” to meet the latent conditions “shall be adjusted as provided in article 3 of this contract.” Article 3 of the contract provides for the making of changes in the contract other than those required by the encountering of changed conditions and says that “if such changes cause an increase or decrease in the amount due under this contract, or in the time required for its performance, an equitable adjustment shall be made and the contract shall be modified in writing accordingly.”

The equitable adjustment referred to in article 4 of course means that adjustment which is equitable to take care of the increased cost resulting from the unexpected conditions encountered. The question presented to the contracting officer, and now to the court, is what were plaintiff’s increased costs and, therefore, what was the equitable adjustment to which it was entitled.

Neither the contracting officer nor the head of the department ever determined what plaintiff’s increased costs were, but they did determine what in their judgment was an equitable adjustment. It will be seen, however, that what they determined was an equitable adjustment was not based on plaintiff’s actual increased costs resulting from the encountering of these changed conditions, as the contract contemplated. It was based upon a computation of what they supposed plaintiff’s increased costs would have been had it adopted the system of using - additional well points instead of the system it - did adopt, on the theory that the use of these additional well points would have permitted plaintiff to do its work on dry land and would have, therefore, avoided much of plaintiff’s actual increased costs. The making of an equitable adjustment on this theory,- however, was not a compliance with the provisions of the contract, which *925 provided that “any increase or decrease of cost and (or) difference in time resulting from such changes shall be adjusted as provided in article 3 of this contract,” that is to say, equitably adjusted. The equitable adjustment contemplated by the article, however, was an equitable adjustment based on actual increased cost, and not on what plaintiff’s increased costs might have been had some procedure different from that adopted and approved been used to take care of the unexpected conditions.

Under the specifications, in article 2-01 (b), it was provided: “Leakage within the cofferdam area shall be controlled by a system of well points, drains, sumps, and pumps, as approved by the contracting officer.” [Italics ours.]

Also in article 3-05 of the specifications it was provided: “ * * * Lowering of ground water under foundations shall be accomplished by means of a well-point system, or by such other means as are approved by the contracting officer * * *. Comprehensive plans for all unwatering operations shall be submitted by the contractor for approval of the contracting officer prior to installation.”

Plaintiff originally intended to use well points to take care of surplus water, but it was found that the use of these well points punctured the overlying stratum which had held in check subterranean water, and when this stratum was punctured this subterranean water shot up into the cofferdam and flooded it. When this developed the contracting officer approved the abandonment of the use of well points in certain areas by change orders 12 and 13, and the substitution therefor of sumps and pumps. Then later, with the knowledge of the contracting officer, the plaintiff completely abandoned the use of well points and substituted therefor the use of sumps - and pumps.

The method of dewatering was subject to the approval of the contracting officer, and, he, at least tacitly, approved the use of sumps and pumps instead of well points. It was, therefore, wholly unwarranted for him and for the head of the department to have made an equitable adjustment based upon what they supposed plaintiff’s increased costs would have been had well points been used, instead of what its increased costs actually were, using the dewatering methods actually used and approved by the contracting officer partly expressly and partly tacitly.

Free access — add to your briefcase to read the full text and ask questions with AI

Great Lakes Dredge & Dock Co. v. United States, 96 F. Supp. 923, 119 Ct. Cl. 504, 1951 U.S. Ct. Cl. LEXIS 47 (cc 1951).

96 F. Supp. 923 (Great Lakes Dredge & Dock Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Parker Excavating, Inc. v. City & County of Denver
2012 COA 180 (Colorado Court of Appeals, 2012)
Net Construction, Inc. v. C & C Rehab & Construction, Inc.
256 F. Supp. 2d 350 (E.D. Pennsylvania, 2003)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
American Line Builders, Inc. v. United States
38 Cont. Cas. Fed. 76,406 (Court of Claims, 1992)
Amp-Rite Electric Co. v. Wheaton Sanitary District
580 N.E.2d 622 (Appellate Court of Illinois, 1991)
Glasgow, Inc. v. Commonwealth
529 A.2d 576 (Commonwealth Court of Pennsylvania, 1987)
John F. Harkins Co. v. SCH. DIST. OF PHIL.
460 A.2d 260 (Superior Court of Pennsylvania, 1983)
McDevitt & Street Co. v. Dept. of Gen. Serv.
377 So. 2d 191 (District Court of Appeal of Florida, 1979)
METRO. SEWERAGE COMM. v. RW Const., Inc.
255 N.W.2d 293 (Wisconsin Supreme Court, 1977)
Phillips Construction Co., Inc. v. The United States
394 F.2d 834 (Court of Claims, 1968)