Youngdale & Sons Construction Co. v. United States

38 Cont. Cas. Fed. 76,467, 27 Fed. Cl. 516, 1993 U.S. Claims LEXIS 275, 1993 WL 9081
CourtUnited States Court of Federal Claims
DecidedJanuary 15, 1993
DocketNo. 553-88C
StatusPublished
Cited by52 cases

This text of 38 Cont. Cas. Fed. 76,467 (Youngdale & Sons Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Youngdale & Sons Construction Co. v. United States, 38 Cont. Cas. Fed. 76,467, 27 Fed. Cl. 516, 1993 U.S. Claims LEXIS 275, 1993 WL 9081 (uscfc 1993).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

This is a Contract Disputes Act (CDA) case in which the plaintiff, Youngdale & Sons Construction Co., Inc. (Youngdale),1 seeks to recover damages in excess of $1.6 million, plus interest, from the defendant, the United States, acting through the Department of the Army, Corps of Engineers (Corps). In its complaint, plaintiff avers, inter alia, that during construction of the subject project, Visiting Officers’ Quarters at Vandenberg Air Force Base, it encountered two differing site conditions, i.e., excess ground water and subterranean rock formations. Plaintiff further avers that pursuant to the differing site conditions clause of subject contract, and given apposite case law, it is entitled not only to recover the additional costs incurred due to said conditions, but it is also entitled to [518]*518utilize the total-cost method in proving derivative damages.2

The defendant, on the other hand, belatedly concedes to the pre-award existence of the excess ground water condition, but emphatically denies the existence of different site conditions regarding the rock. In addition to the foregoing, the defendant strongly contends that the plaintiff is not entitled to utilize the total-cost method in proving its damages; but rather, it is only entitled on this record to utilize the direct or specific cost method. For the reasons hereinafter expressed, the court finds, after a full and thorough review of the record, that the plaintiff is entitled to recover certain additional costs plus interest stemming from the excess water differing site condition only. With respect to the alleged rock differing site condition, we find that plaintiff is not entitled to any recovery thereunder, because it failed to prove by the requisite quantum that said condition constitutes a differing site condition. Moreover, we find that any damages to which plaintiff is entitled in view of the excess water differing site condition must be calculated pursuant to the direct cost method, and not the total-cost method, inasmuch as the plaintiff has failed to establish the necessary elements required under that method of calculating damages. Lastly, given that the plaintiff is entitled to recover damages with respect to the excess water differing site condition, we accordingly find that the defendant is not entitled to liquidated damages under the terms of the contract.

Jurisdiction is premised on 41 U.S.C. § 609(a)3 of the CDA.

FACTS

On December 27, 1982, the defendant issued its invitation for bids (No. DACA-05-83-B-0040) on contract No. DACA-09-83-C-0053, for the construction of two two-story apartments and one two-unit single story apartment at Vandenberg Air Force Base. The estimated cost of the project noted by defendant was approximately $3,030,000 to complete. Id. Plaintiff and 11 other bidders4 submitted their bids on January 26, 1983, for the Vandenberg project. Youngdale’s bid of $2,693,800 was found to be considerably lower than that of the government’s estimate, as well as that of the 11 other bidders; therefore, the government awarded the contract to Young-dale on or about February 24, 1983 (PX 5).

In furtherance of the award, on March 15, 1983, Youngdale received a Notice to Proceed dated March 8, 1983, from the government. The contract required that Youngdale complete the project by June 7, 1984, i.e., within 450 calendar days, blow-[519]*519ever, this date was later revised by the government to June 13, 1984. In any event, on March 17, 1983, upon inspection5 of the site, Youngdale personnel encountered 8 to 18 inches of ground water within 2 to 3 minutes of digging several potholes throughout the site. In addition, the soil removed from these holes was of a pancake-batter consistency. Upon discovering this condition, Youngdale immediately informed the government personnel at a preconstruction meeting of the saturated soil condition. The government indicated, in response, that all jobs on the base were experiencing similar problems. Notwithstanding, Youngdale sent Serial Letter No. 7 to the government on March 23, 1983, memorializing and advising it that Young-dale considered the saturated soil conditions to be materially different from those indicated in the contract documents and, therefore, it would reserve all rights with respect to any adjustments in time and price relating to what it deemed to be a compensable differing site condition. The government responded on April 5, 1983, with Serial Letter 005 denying that the conditions encountered were “inconsistent with those shown on the contract drawings and specifications.” Moreover, on April 11, 1983, the government stated in another letter that “the saturated soil condition is normal at this time of year and therefore should have reasonably been anticipated [by the contractor]; hence, no pecuniary or time adjustments are deemed necessary.”

However, despite the defendant’s firm position, supra, Garcia Paving, one of Youngdale's subcontractors, was unable to clear and grub the site at the outset of the project because its equipment immediately became mired in the muddy soil and had to be removed from the site. In view thereof, Youngdale sent another letter on April 15, 1983, informing the government that it was unable to commence earthwork activities and that it needed clear direction as to how it should best proceed given the existing differing site condition. In addition, Youngdale forwarded to the government a report from Sobhani Engineers, a private engineering firm hired by Youngdale, to examine the soil conditions at subject site. The government, in turn, strongly responded on April 27, 1983, that the contract correctly reflected the site conditions and that Youngdale should proceed as planned. Moreover, that letter also contained a Cure Notice, for inadequate progress, indicating that Youngdale was in noncomplianee with the contract because it had failed to prosecute its work diligently. Following thereon, the government sent a superseding Cure Notice on May 2, 1983, to plaintiff threatening termination for “failure to begin substantial performance of the contract.” Therefore, as required by the government’s Cure Notices, and in spite of the apparent adverse conditions at the site, Youngdale and its subcontractors attempted, once again, to clear and grub the site; however, they were again unsuccessful.

As a result of the foregoing, and in light of the government’s pertinacious position as to the excess water condition at the site, Youngdale videotaped said site conditions on May 6,1983, to buttress its position with respect to the disputed water differing site condition. The video depicted the mired equipment and the several potholes dug by Youngdale that immediately became filled with water within minutes of being dug. Tr. 146-156. Notwithstanding these conditions, Youngdale again required its subcontractor, Garcia Paving, to return to the job site and to continue working. Although the equipment continued to become mired in the mud, Garcia was able to make marginal progress through the earthwork for the building pads for Buildings “A” and “B.” The parking and roadway areas, however, were completely saturated and were continuously pumping out water; thus, Garcia was unable to perform any significant work in these areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Optimum Services, Inc.
Armed Services Board of Contract Appeals, 2016
Flatiron-Lane v. Case Atlantic Co.
121 F. Supp. 3d 515 (M.D. North Carolina, 2015)
Bay County, Florida v. United States
117 Fed. Cl. 131 (Federal Claims, 2014)
Delhur Industries, Inc. v. United States
95 Fed. Cl. 446 (Federal Claims, 2010)
Cent. Allied Ents., Inc. v. Adjutant General's Dept.
2010 Ohio 3229 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. State
2010 Ohio 1488 (Ohio Court of Claims, 2010)
Stanley Miller Constr. Co. v. Ohio School Facilities Comm.
2010 Ohio 1528 (Ohio Court of Claims, 2010)
Richard E. Lambert, Ltd. v. City of Tucson Department of Procurement
221 P.3d 375 (Court of Appeals of Arizona, 2009)
Mactec, Inc. v. Bechtel Jacobs Company, LLC
346 F. App'x 59 (Sixth Circuit, 2009)
KOGA ENGINEERING & CONSTRUCTION, INC. v. State
203 P.3d 676 (Hawaii Intermediate Court of Appeals, 2009)
Cumberland Casualty & Surety Co. v. United States
82 Fed. Cl. 500 (Federal Claims, 2008)
Universal Construction, Inc. v. United States
71 Fed. Cl. 179 (Federal Claims, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,467, 27 Fed. Cl. 516, 1993 U.S. Claims LEXIS 275, 1993 WL 9081, Counsel Stack Legal Research, https://law.counselstack.com/opinion/youngdale-sons-construction-co-v-united-states-uscfc-1993.