Insulation Contracting Supply Inc. v. S3h, Inc.

CourtNevada Supreme Court
DecidedSeptember 29, 2015
Docket62856
StatusUnpublished

This text of Insulation Contracting Supply Inc. v. S3h, Inc. (Insulation Contracting Supply Inc. v. S3h, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Insulation Contracting Supply Inc. v. S3h, Inc., (Neb. 2015).

Opinion

We are asked to determine whether (1) ICS waived its claims against Sal, (2) NRS 624.626 entitles ICS to damages beyond the district court's award, (3) ICS proved damages beyond the district court's award, (4) the district court awarded ICS damages for costs that 5311 already paid, (5) ICS's mechanic's lien and unjust enrichment claims fail as a matter of law, and (6) the district court erred in awarding either party attorney fees. We reverse in part and remand the issue of attorney fees because the district court did not adequately explain its bases for those awards. We affirm in all other respects. ICS Did Not Waive Its Claims Against 5311 S3H contends ICS waived all material claims by signing an unconditional waiver and accepting payment for that waiver. The district court held ICS's unconditional waiver ineffective because S3H only tendered $440,546.64 to ICS, and the full amount agreed upon for ICS's waiver was $601,001. In light of the district court's findings, it properly declined to enforce that waiver. First, S3H argues unconditional waivers are enforceable even without payment. NRS 108.2457(5)(d) sets forth a statutorily mandated form for unconditional waivers, and that form requires the following language. "[t]his document is enforceable against you if you sign it, even if you have not been paid. If you have not been paid, use a conditional release form." However, NRS 108.2457(2)(b) declares all lien waivers unenforceable unless "[t]he lien claimant receive[s] payment for the lien." Conflict between statutory provisions can make unambiguous language ambiguous. Orion Portfolio Servs. 2, LLC v. Cnty. of Clark, 126 Nev. 397, 402, 245 P.3d 527, 531 (2010). If such an ambiguity arises, the court must look to the Legislature's intent. Id. at 403, 245 P.3d 531. Additionally,

SUPREME COURT OF NEVADA 2 (0) 1.947A "this court considers the statute's multiple legislative provisions as a whole." Leven v. Frey, 123 Nev. 399, 405, 168 P.3d 712, 716 (2007). NRS 108.2457(2)(b) governs here, so lien waivers cannot be enforced unless the waiving party is paid in full. The legislative history shows the statutory forms contained at NRS 108.2457(5)(d) were merely meant to standardize waiver forms, not alter any rights or obligations contained elsewhere in the statute. Conversely, NRS 108.2457(1) and (2) made important, substantive changes to Nevada law, such that waiving lien claims became substantially more difficult. See In re Fontainebleau Las Vegas Holdings, LLC, 128 Nev., Adv. Op. 53, 289 P.3d 1199, 1213-14 (2012); Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 124 Nev. 1102, 1115 n.39, 197 P.3d 1032, 1041 n.39 (2008). The conflicting provisions are easily resolved by reading NRS 108.2457(5)(d)'s disclosure as a warning about the worst possible outcome for a lien claimant, rather than a statement of law. This is a natural reading of the provisions, and it is consistent with NRS 108.2457's legislative history and structure. S3H also contends that the district court erred in allowing evidence that undermined the unconditional waiver. We disagree. Nevada applies the parol evidence rule to waivers. Tallman v. First Nat'l Bank of Nev., 66 Nev. 248, 257, 208 P.2d 302, 306 (1949). It also applies traditional exceptions to the parol evidence rule, like fraud and mistake. Russ v. General Motors Corp., 111 Nev. 1431, 1438-39, 906 P.2d 718, 723 (1995). Here, the district court found that S3H made a mistake that led the parties to agree $601,001 would settle all claims, not $440,546.64 as listed on the unconditional waiver form. Therefore, the district court did not abuse its discretion in allowing extrinsic evidence of a mistake to contradict the terms of the unconditional waiver. See M.C. Multi-Family

SUPREME COURT OF NEVADA 3 (0) 1947A e Dev., L.L.C. v. Crestdale Assocs., Ltd., 124 Nev. 901, 913, 193 P.3d 536, 544 (2008). Finally, 5311 argues that it paid in full for ICS's waiver by paying $440,546.64. The district court disagreed, as it concluded by necessary implication that 5311 owed ICS $601,001 for its unconditional waiver.' The district court did not err. Settlement agreements require a meeting of the minds. May v. Anderson, 121 Nev. 668, 672, 119 P.3d 1254, 1257 (2005). Whether a meeting of the minds occurred is a factual finding reviewed for substantial evidence. Lawry v. Devine, 82 Nev. 65, 67, 410 P.2d 761, 762 (1966). "Substantial evidence is evidence that a reasonable mind might accept as adequate to support a conclusion." Whitemaine v. Aniskovich, 124 Nev. 302, 308, 183 P.3d 137, 141 (2008). Although evidence about the parties' settlement expectations is conflicting, substantial evidence supports the district court's conclusion that the parties agreed to a $601,001 settlement. Sal agrees that the parties initially believed the final payment to ICS would be $601,001. However, S3E1 characterizes the agreement as Sal paying (1) approved change orders, plus (2) withheld retention, plus (3) $229,440 for ICS's $1.2 million claim. S3H claims, and the district court found, that a math error led S311 to incorrectly believe the total amount was $601,001. Therefore,

"The district court found that the parties agreed to a payment of $601,001 to settle ICS's claims. However, ICS signed an unconditional waiver stating that S3H paid ICS $440,546.64 to waive all material claims. The district court necessarily found that S311 agreed to pay $601,001 because it found that "S311 did not comply with agreed terms of the settlement," even though it also concluded that 5311 paid ICS $440,546.64.

SUPREME COURT OF NEVADA 4 (0) 1947A e S3H's position is entirely consistent with the proposition that, at one point, the parties reached a global settlement agreement for $601,001. Documentary evidence also supports the district court's finding that the parties initially agreed to a total payment of $601,001. An email from an S311 employee shows the "[n]egotiated final payment for both jobs" is $601,001.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russ v. General Motors Corp.
906 P.2d 718 (Nevada Supreme Court, 1995)
Lawry v. Devine
410 P.2d 761 (Nevada Supreme Court, 1966)
Central Bit Supply, Inc. v. Waldrop Drilling & Pump, Inc.
717 P.2d 35 (Nevada Supreme Court, 1986)
Weddell v. H2O, INC.
271 P.3d 743 (Nevada Supreme Court, 2012)
Wyeth v. Rowatt
244 P.3d 765 (Nevada Supreme Court, 2010)
Shuette v. Beazer Homes Holdings Corp.
124 P.3d 530 (Nevada Supreme Court, 2005)
Whitemaine v. Aniskovich
183 P.3d 137 (Nevada Supreme Court, 2008)
Leven v. Frey
168 P.3d 712 (Nevada Supreme Court, 2007)
May v. Anderson
119 P.3d 1254 (Nevada Supreme Court, 2005)
Barney v. Mt. Rose Heating & Air Conditioning
192 P.3d 730 (Nevada Supreme Court, 2008)
Edwards v. Emperor's Garden Restaurant
130 P.3d 1280 (Nevada Supreme Court, 2006)
Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.
197 P.3d 1032 (Nevada Supreme Court, 2008)
Tallman v. First National Bank
208 P.2d 302 (Nevada Supreme Court, 1949)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Wilmington Trust FSB v. A1 Concrete Cutting & Demolition, LLC
289 P.3d 1199 (Nevada Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Insulation Contracting Supply Inc. v. S3h, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/insulation-contracting-supply-inc-v-s3h-inc-nev-2015.