Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.

197 P.3d 1032, 124 Nev. 1102
CourtNevada Supreme Court
DecidedOctober 30, 2008
Docket45618, 45860, 45898
StatusPublished
Cited by53 cases

This text of 197 P.3d 1032 (Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 197 P.3d 1032, 124 Nev. 1102 (Neb. 2008).

Opinion

*1105 OPINION

By the Court,

Gibbons, C. J.:

We previously issued an opinion in these matters on June 12, 2008. In that opinion, we reversed the judgment on the breach of contract claim regarding the retrofit issue and remanded for a new trial, affirmed the district court’s judgment enforcing the lien, vacated the district court’s award of attorney fees, and reversed the award of sanctions. Appellants’ and respondents’ petitions for rehearing followed.

We will consider rehearing when we have overlooked or misapprehended material facts or questions of law or when we have overlooked, misapplied, or failed to consider legal authority directly controlling a dispositive issue in the appeal. 2 Having considered the petitions and answers thereto in light of this standard, we conclude that rehearing is not warranted, and therefore, we deny the petitions for rehearing. Nevertheless, as petitioners have pointed out, a portion of our June 12, 2008, opinion could be misconstrued as being contrary to this court’s precedent. Accordingly, although we deny rehearing, we withdraw our June 12, 2008, opinion and issue this opinion in its place.

In this opinion, we reach the same conclusions as in our prior opinion, but we clarify our reasoning for reversing the district court’s judgment on the breach of contract claim regarding the retrofit issue and for remanding that matter to the district court for a new trial.

In the district court, respondent Bullock Insulation, Inc. (Bullock Insulation), filed complaints against appellants Lehrer McGovern Bovis, Inc. (Bovis), and Venetian Casino Resort, LLC (Venetian Resort), 3 for, among other claims, breach of contract and to foreclose on a mechanic’s lien. The parties disputed, among other things, whether, by the terms of the subcontract between Bullock Insulation and Bovis, Bovis was required to pay Bullock Insulation to retrofit walls with fire retardant materials. After considering the jury’s answers to special interrogatories and its general verdict, the district court entered judgment in favor of Bullock Insulation. The district court later entered an order granting Bullock Insulation’s motion for attorney fees and sanctioning Bovis for bad-faith litigation practices. These appeals followed.

In these appeals, we consider the primary issue of whether a new trial is required when the district court creates special interrogatories upon issues of fact and the jury’s answers to those in *1106 terrogatories are inconsistent, such that an ultimate judgment cannot be entered without contradicting a portion of the answers and the general verdict. While this court has held that parties have a duty to object to inconsistent jury verdicts before the jury is discharged, we conclude that this general rule is not absolute because, under NRCP 49(b), the district court is obligated not to enter a judgment when the answers to interrogatories are inconsistent with each other and one or more answers are also inconsistent with the general verdict. In this case, we conclude that a new trial is warranted regarding the breach of contract claim related to the retrofit issue, even though the parties failed to object to the verdicts as inconsistent prior to discharge of the jury, because the ultimate judgment cannot be reconciled by an interpretation of the special verdicts and the general verdict in their totality. Therefore, because NRCP 49(b) mandates that a judgment shall not be entered when such inconsistencies exist, we conclude that the district court abused its discretion when it entered the inconsistent judgment.

We also consider the enforceability of a mechanic’s lien waiver provision entered into before the Legislature amended NRS Chapter 108 to require specific forms for lien waivers, and whether a pay-if-paid provision entered into before the Legislature amended NRS Chapter 624 to include provisions for prompt payment is unenforceable as a matter of public policy. Additionally, we consider whether the district court abused its discretion when it sanctioned Bovis for maintaining its defense in bad faith.

We conclude that the district court properly determined that the lien waiver and pay-if-paid provisions were unenforceable based upon Nevada’s public policy favoring the statutory right to a mechanic’s lien. Additionally, the district court abused its discretion when it sanctioned Bovis for bad-faith litigation practices.

Accordingly, we reverse the judgment on the jury verdict as it concerns the breach of contract claims related to the retrofit issue, based on the inconsistent answers to the special interrogatories, and remand this matter to the district court for further proceedings consistent with this opinion. We affirm the remaining portion of the district court’s judgment regarding the lien waiver provision, the pay-if-paid provision, and the principal owed, plus interest. Finally, in light of our decision that a new trial is warranted on the breach of contract claim concerning the retrofit work, we necessarily vacate the portion of the district court’s order awarding attorney fees and reverse the portion of its order awarding sanctions.

*1107 FACTS AND PROCEDURAL HISTORY

Las Vegas Sands, Inc., the predecessor of Venetian Resort, entered into a Construction Management Agreement (the agreement) with Bovis under which Bovis agreed to manage remaining construction of the Venetian Casino Resort and Hotel (the project). Under the agreement, Bovis was obligated to hire subcontractors and provide the work, labor, services, materials, supplies, and equipment necessary to complete the project.

Bovis later subcontracted with Bullock Insulation for firestopping work on the project. Firestopping involves installing fire retardant material around openings in walls to prevent smoke and fire from spreading between rooms. Under the subcontract, Bullock Insulation was to install “firestop putty pads” around certain of the project’s electrical boxes, but the parties dispute whether, by the terms of the subcontract, Bullock Insulation was required to install the putty pads around the electrical boxes in the rooms’ separation walls.

The subcontract incorporated the general conditions of the agreement, which contained a lien waiver clause, whereby Bullock Insulation promised “not [to] suffer or permit any lien or other encumbrance to be filed” against the project. The lien waiver clause is located in the agreement after other provisions discussing final payment terms and the conditions precedent for final payment. The lien waiver is not dependent upon Bullock Insulation’s receipt of any payment for labor or materials. Also preceding the lien waiver provision of the agreement is a pay-if-paid provision, under which, by way of incorporation into the subcontract, Bullock Insulation’s right to payment for its work was contingent upon Venetian Resort’s payments to Bovis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HELIX ELEC. OF NEV., LLC v. APCO CONSTR., INC. C/W 80508
2022 NV 13 (Nevada Supreme Court, 2022)
MOTOR COACH INDUS., INC. VS. KHIABANI
2021 NV 42 (Nevada Supreme Court, 2021)
Lopez Vs. Progressive N. Insurance Co.
Nevada Supreme Court, 2021
In Re: Matter Of King
Nevada Supreme Court, 2020
APCO CONSTR., INC. VS. ZITTING BROS. CONSTR., INC.
2020 NV 64 (Nevada Supreme Court, 2020)
PARDEE HOMES OF NEVADA VS. WOLFRAM
2019 NV 22 (Nevada Supreme Court, 2019)
Pardee Homes of Nev. v. Wolfram
444 P.3d 423 (Nevada Supreme Court, 2019)
Phung v. Doan
Nevada Supreme Court, 2018
Emerson (Preston) v. State
Nevada Supreme Court, 2018
Transglobal Assets, Inc. v. Conte
Nevada Supreme Court, 2017
KLABACKA VS. NELSON C/W 66772
2017 NV 24 (Nevada Supreme Court, 2017)
CASHMAN EQUIPMENT CO. VS. WEST EDNA ASSOC. C/W 65819/66452
2016 NV 69 (Nevada Supreme Court, 2016)
In re Guardianship & Estate of Echevarria
2016 NV 45 (Nevada Supreme Court, 2016)
IN RE: GUARDIANSHIP OF ECHEVARRIA
2016 NV 45 (Nevada Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
197 P.3d 1032, 124 Nev. 1102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lehrer-mcgovern-bovis-inc-v-bullock-insulation-inc-nev-2008.