HELIX ELEC. OF NEV., LLC v. APCO CONSTR., INC. C/W 80508

2022 NV 13
CourtNevada Supreme Court
DecidedMarch 24, 2022
Docket80508
StatusPublished

This text of 2022 NV 13 (HELIX ELEC. OF NEV., LLC v. APCO CONSTR., INC. C/W 80508) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HELIX ELEC. OF NEV., LLC v. APCO CONSTR., INC. C/W 80508, 2022 NV 13 (Neb. 2022).

Opinion

138 Nev., Advance Opinion 13 IN THE SUPREME COURT OF THE STATE OF NEVADA

HELIX ELECTRIC OF NEVADA, LLC, No. 77320 Appellant/Cross-Respondent, vs. APCO CONSTRUCTION, INC., A NEVADA CORPORATION, Respondent/Cross-Appellant.

HELIX ELECTRIC OF NEVADA, LLC, No. 80508 Appellant/Cross-Respondent, vs. APCO CONSTRUCTION, INC., A • •c NEVADA CORPORATION, MAR 2 4 2022 Respondent/Cross-Appellant. ELI CLERK ay IEF DEPUTY CLERK

Consolidated appeals and cross appeals from a district court judgment, certified as final pursuant to NRCP 54, and an award of attorney fees in a construction contract action. Eighth Judicial District Court, Clark County; Mark R. Denton, Judge. Affirmed.

Peel Brimley LLP and Eric B. Zimbelman and Richard L. Peel, Henderson, for Appellant/Cross-Respondent.

Fennemore Craig, P.C., and Christopher H. Byrd, Las Vegas; Fennemore Craig, P.C., and John Randall Jefferies, Phoenix, Arizona; Marquis Aurbach Coifing and Cody S. Mounteer, Las Vegas, for Respondent/Cross-Appellant.

SUPREME COURT OF NEVADA

(0) I 947A .)1004 t 2 - OÝ2,V5 BEFORE THE SUPREME COURT, PARRAGUIRRE, C.J., STIGLICH and SILVER, JJ.

OPINION By the Court, SILVER, J.: Pay-if-paid provisions enable a contractor to pay the subcontractor only if the contractor first receives payment from the project developer or owner. We clarified in APCO Construction, Inc. v. Zitting Brothers Construction, Inc., 136 Nev. 569, 569, 473 P.3d 1021, 1024 (2020), that pay-if-paid provisions, while not void per se, are unenforceable if they run contrary to the rights and requirements established under NRS 624.624-.630. Here, the district court correctly concluded that a subcontract provision conditioning the payment of funds retained from earlier progress payments on the contractor first being paid was unenforceable. As the court further concluded, however, the unenforceability of the pay-if-paid condition did not also invalidate the remaining conditions precedent for obtaining the retention payment. We also agree with the district court that, as the subcontract was assigned after the original contractor terminated its contract with the developer, the subcontractor cannot obtain the unpaid retention from the original contractor. Finally, for the same reason, the contractor is not entitled to attorney fees under the subcontract for defending this action. We therefore affirm. FACTS AND PROCEDURAL HISTORY Gemstone Development West, Inc., sought to construct condominiums (the project) and hired respondent/cross-appellant APCO Constniction, Inc., as its general contractor. APCO, in turn, subcontracted with appellant/cross-respondent Helix Electric of Nevada, LLC, at Gemstones direction. While working under APCO, Helix billed

2 $5,131,207.11 and was paid $4,626,186.11. The difference, $505,021, was withheld in retention. Under section 3.8 of the subcontract, the retention would be released only upon the occurrence of several conditions, including Gemstone paying APCO, Helix completing its work on the project, Gemstone accepting that work, and Helix delivering close-out documents and claim releases to APCO. Before the project's completion, the relationship between APCO and Gemstone deteriorated. Due to Gemstone's failures to issue certain progress payments to APCO, APCO issued stop work notices for the project multiple times. In so doing, APCO notified the subcontractors that while all work on the project was suspended due to its stop work notice, the parties were hoping to resolve the issues and, as the prime contract had not at that point been terminated, its subcontractors remained contractually bound to their subcontracts with APCO. Gemstone, in turn, claimed APCO was in breach of their agreement and threatened to terminate the prime contract if the breaches were not cured. Gemstone notified the subcontractors of the imminent termination of APCO and that it had already located a replacement general contractor so as to not delay the project. Soon thereafter, APCO notified the subcontractors that it intended to terminate the prime contract, explaining that when the general contractor terminates its contract, the subcontractors could also terminate their subcontracts. Ultimately, APCO left the project at the end of August, with both parties claiming that they had terminated the prime contract."

'Gemstone and APCO disputed which of them terminated the prime contract, but ultimately, it was determined by the district court that APCO validly terminated the contract.

3 Gemstone thereafter notified the subcontractors that it had terminated the prime contract and that Camco Pacific Construction Company would act as construction manager in place of APCO. Helix did not terminate its subcontract with APCO but worked on the project under Carrico from August to September 2008. Although Helix did not sign the subcontract Cameo proposed, it billed Camco for its remaining fees, including the retention earned while Helix worked under APCO, as instructed by Gemstone. By December 15, 2008, however, the project lenders had withdrawn funding and work on the project was terminated. Camco paid Helix only a fraction of the amount it billed, which payment did not cover its retention. APCO, Camco, and numerous subcontractors, including Helix, recorded mechanics liens against the property, and the district court consolidated the multiple cases for purposes of discovery and trial. Pertinent here, the district court granted partial summary judgment in favor of Helix and other subcontractors, preventing APCO and Camco from asserting any defenses based on pay-if-paid agreements. The court relied on NRS 624.624 and Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc., 124 Nev. 1102, 197 P.3d 1032 (2008), which generally make pay-if-paid agreements unenforceable and also require higher-tiered contractors to pay their lower-tiered subcontractors within the time periods set forth in NRS 624.624(1). At trial, the district court found that the subcontracts had been assigned to Gemstone under the prime contract because Gemstone purported to terminate the prime contract and told the subcontractors that their contracts would be assumed by Cameo; Carrico began directing the project and receiving billings from the subcontractors, including for

(CO 1947A a1Mbo 4 retention; and Helix worked directly with Gemstone and Camco, not APCO, after APCO left the project. The district court dismissed Helix's claims for retention against APCO because section 3.8s preconditions for retention were not satisfied while APCO was the contractor, a fact that Helix admitted. Specifically, the district court faulted Helix for failing to show completion of the entire project and Gemstones acceptance, Gemstones final payment to APCO, and delivery of the close out documents and claim releases. APCO requested attorney fees pursuant to section 18.5 of the subcontract, but the court awarded APCO attorney fees pursuant to NRCP 68, for less than APCO's requested amount. Helix appeals, challenging the denial of its claims for retention against APCO and the award of attorney fees under NRCP 68, and APCO cross-appeals, challenging the reduction of its requested attorney fees. DISCUSSION Construction contracts commonly allow the owner or developer of a project to withhold a percentage of funds from progress payments to the contractor pending completion of the work. See Pittsburg Unified Sch. Dist. v. S.J. Amoroso Constr. Co., 181 Cal. Rptr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allianz Insurance v. Gagnon
860 P.2d 720 (Nevada Supreme Court, 1993)
Cover v. Chicago Eye Shield Co.
136 F.2d 374 (Seventh Circuit, 1943)
Lauren Kyle Holdings, Inc. v. Heath-Peterson Constr. Corp.
864 So. 2d 55 (District Court of Appeal of Florida, 2003)
Saavedra-Sandoval v. Wal-Mart Stores, Inc.
245 P.3d 1198 (Nevada Supreme Court, 2010)
May v. Anderson
119 P.3d 1254 (Nevada Supreme Court, 2005)
Lehrer McGovern Bovis, Inc. v. Bullock Insulation, Inc.
197 P.3d 1032 (Nevada Supreme Court, 2008)
Albios v. Horizon Communities, Inc.
132 P.3d 1022 (Nevada Supreme Court, 2006)
Pittsburg Unified School District v. S.J. Amoroso Construction Co.
232 Cal. App. 4th 808 (California Court of Appeal, 2014)
I. Cox Construction Co. v. CH2 Investments, LLC
296 P.3d 1202 (Nevada Supreme Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
2022 NV 13, Counsel Stack Legal Research, https://law.counselstack.com/opinion/helix-elec-of-nev-llc-v-apco-constr-inc-cw-80508-nev-2022.