J. Christopher Stuhmer, Inc. v. Centaur Sculpture Galleries, Ltd.

871 P.2d 327, 110 Nev. 270, 1994 Nev. LEXIS 32
CourtNevada Supreme Court
DecidedMarch 30, 1994
Docket24323
StatusPublished
Cited by4 cases

This text of 871 P.2d 327 (J. Christopher Stuhmer, Inc. v. Centaur Sculpture Galleries, Ltd.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. Christopher Stuhmer, Inc. v. Centaur Sculpture Galleries, Ltd., 871 P.2d 327, 110 Nev. 270, 1994 Nev. LEXIS 32 (Neb. 1994).

Opinion

*271 OPINION

Per Curiam:

Appellant J. Christopher Stuhmer, Inc. (Stuhmer Inc.) entered into a written contract with Centaur Galleries, Ltd., Inc. (Centaur) for the construction of a retail art gallery in the Horton Plaza in San Diego, California. The parties agreed that Pacific Coast Builders (PCB) would do the construction work, while Stuhmer Inc. would supervise the project. When Centaur failed to pay in full, Stuhmer Inc. filed suit seeking $51,687.89 for money due under the contract or alternatively, under the theory of quantum meruit. The district court found that Stuhmer Inc. had contracted with Centaur’s California corporation and had assigned all its rights under the contract to PCB, and accordingly denied Stuhmer Inc.’s request for damages. We reverse and remand to the district court with instructions to enter judgment for Stuhmer Inc. against Centaur’s Nevada corporation in the amount of $51,587.89.

FACTS

Stuhmer Inc. built the Centaur Sculpture Galleries retail store in The Fashion Show Mall in Las Vegas. After the completion of this gallery Richard Perry (Perry) of Centaur contacted Stuhmer Inc., requesting that Stuhmer Inc. construct the new Centaur gallery in San Diego based on the same design used in the Las Vegas construction. Because Stuhmer Inc. was not licensed as a contractor in California the parties agreed that PCB, a California company owned by Stuhmer’s brother, would perform the construction work, while Stuhmer Inc. would supervise the project. Stuhmer and his brother (Steve Stuhmer) verbally agreed that PCB would get a $20,000.00 flat fee for its services plus 50% of the profit on the project.

On October 18, 1988, Stuhmer Inc. and Centaur entered into a written construction contract for the amount of $268,140.90. Centaur’s address was listed as 3200 Las Vegas Boulevard, Las Vegas, Nevada 89109, throughout the contract, and Perry’s signature appeared in the block entitled “owner.” The project began.

Centaur made a payment to Stuhmer Inc. of $80,442.00 when the contract was signed, and subsequently Stuhmer Inc. invoiced Centaur Galleries in Las Vegas on a number of occasions and was paid the additional sum of $152,724.09. Stuhmer Inc. paid PCB and answered questions from Perry regarding the project. Stuhmer visited the San Diego job site during the design process, *272 prior to construction commencing, and when the construction was about 75% completed. PCB had its own crew on the job during construction and also hired other subcontractors and tradesmen to work on the project. PCB submitted all of its subcontractor and tradesmen bills to Stuhmer Inc., who directly paid these laborers.

After the construction was completed in February of 1989, Perry continued to communicate directly with Stuhmer Inc. in Las Vegas regarding items that he claimed needed to be completed, and regarding construction extras that Stuhmer Inc. provided at a cost of $10,113.89. Additionally, Centaur’s attorneys communicated with Stuhmer Inc. in writing regarding The project.

On November 2, 1990, Stuhmer filed suit against Centaur-Nevada seeking $51,687.89 in damages for money due under the contract, or for the reasonable value of services and materials provided under the theory of quantum meruit. 1 Pursuant to a bench trial, the district court found that Stuhmer Inc. had entered into the contract with Centaur’s California corporation (Centaur-California) rather than Centaur’s Nevada corporation (Centaur-Nevada), and that Stuhmer Inc. had assigned its interest in the contract to PCB. The district court therefore concluded that Stuhmer Inc. lacked standing to claim contract damages, and entered judgment in favor of Centaur-Nevada and Centaur-California, denying Stuhmer Inc.’s request for damages. This appeal followed.

DISCUSSION

Whether the district court erroneously found that the contract was between Stuhmer Inc. and Centaur-California.

Centaur-California has closed its San Diego gallery and its corporate operations, and is apparently without any assets. Centaur, in an attempt to escape paying a judgment, asserts that *273 Centaur-California rather than Centaur-Nevada contracted with Stuhmer Inc.

It is undisputed that the wording of the contract did not indicate whether Centaur was a Nevada corporation or a California corporation. However, the block entitled “owner” and signed by Perry on behalf of Centaur lists a Las Vegas address that is the principal place of business of Centaur-Nevada.

In reaching the conclusion that Stuhmer Inc. contracted with Centaur-California, the district court found that the term “owner” in the contract referred to the tenant in the lease of the premises in San Diego, which was Centaur-California. These lease agreements were plaintiff's Exhibits 9, 10, and 11, which were never offered or admitted into evidence and accordingly, the district court erred in relying on them.

The district court further found that the fact that all payments to Stuhmer Inc. were made from a separate bank account maintained by Centaur-California supported its conclusion. 2 Though there is evidence supporting this factual finding, the district court erred in failing to consider Stuhmer’s unrefuted testimony regarding the circumstances surrounding the contract.

The best approach for courts to use in interpreting a contract that is ambiguous is to “delve beyond the express terms of a written contract” and “examine the circumstances surrounding the parties’ agreement in order to determine the true mutual intentions of the parties.” Hilton Hotels v. Butch Lewis Productions, 107 Nev. 226, 231, 808 P.2d 919, 921 (1991). This includes not only the circumstances surrounding the execution of the contract, but also subsequent acts and declarations of the parties. Transwestern Leasing v. Corrao Construction Co., 98 Nev. 445, 447, 652 P.2d 1181, 1183 (1982).

Stuhmer’s unrefuted testimony regarding the circumstances of the agreement clearly shows that Stuhmer Inc. contracted with Centaur-Nevada. 3 Stuhmer testified that it was his understanding that he was contracting with the same entity that he had previously dealt with when building the Centaur Sculpture Galleries in Las Vegas, and that the first time he heard of Centaur-California was after the subject litigation was filed. See Water Rights v. North Colorado Water Conservancy District, 677 P.2d 320, 327 (Colo. 1984) (“It is also well-established that the parties’ construction of a contract before a dispute arises is a particularly persuasive aid in determining the true meaning of the agreement.”). The correspondence to Stuhmer Inc. not only from *274

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
871 P.2d 327, 110 Nev. 270, 1994 Nev. LEXIS 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-christopher-stuhmer-inc-v-centaur-sculpture-galleries-ltd-nev-1994.