Dayside Inc. v. First Judicial District Court Ex Rel. Carson City

75 P.3d 384, 119 Nev. 404, 119 Nev. Adv. Rep. 48, 2003 Nev. LEXIS 54
CourtNevada Supreme Court
DecidedAugust 29, 2003
Docket40580
StatusPublished
Cited by16 cases

This text of 75 P.3d 384 (Dayside Inc. v. First Judicial District Court Ex Rel. Carson City) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dayside Inc. v. First Judicial District Court Ex Rel. Carson City, 75 P.3d 384, 119 Nev. 404, 119 Nev. Adv. Rep. 48, 2003 Nev. LEXIS 54 (Neb. 2003).

Opinion

OPINION 1

Per Curiam:

This original petition for a writ of mandamus or certiorari challenges a district court order that granted the real party in interest partial summary judgment on petitioner’s mechanic’s lien foreclosure claim for relief and dismissed the accompanying lien. The district court ruled that a construction contract executed by petitioner and the real party in interest contained an enforceable mechanic’s lien waiver provision. Petitioner now seeks a writ of mandamus or certiorari directing the district court to reverse the partial summary judgment and restore the mechanic’s lien.

We conclude that contractual lien waiver provisions do not violate public policy, that the waiver present in this case was sup *406 ported by the contract’s terms, and that the voluntariness of petitioner’s waiver is beyond our review. Therefore, we deny the petition, as the district court did not abuse its discretion in entering partial summary judgment and dismissing the lien.

FACTS

In May 1999, petitioner Dayside Inc. and real party in interest Parkway Manor Inc. executed a pre-printed form contract requiring Dayside to construct an apartment building on Parkway’s real property. Parkway agreed to pay Dayside a total of $9,165,226 in monthly installments, and Dayside agreed, among other things, that it would

not file a mechanic’s or materialman’s lien or maintain any claim against [Parkway’s] real estate or improvements ... on account of any work done, labor performed or materials furnished under this Contract ....

The parties crossed out language imposing the lien waiver on subcontractors, and then wrote that Dayside’s waiver of lien rights was valid “to the extent such waiver is in accordance with Nevada law.”

According to Dayside, after “Parkway refused to pay Dayside large sums of money owed,” Dayside recorded a mechanic’s lien and later joined a subcontractor in litigation already underway against Parkway. Dayside apparently pleaded various contract and tort claims for relief against Parkway, including one seeking to foreclose the mechanic’s lien.

In June 2002, the district court granted Parkway partial summary judgment, ruling that the contract’s lien-waiver provision was clear and not contrary to Nevada law. The district court then ordered Dayside’s mechanic’s lien dismissed. In December 2002, Dayside filed in this court the instant petition for a writ of mandamus or certiorari, challenging the partial summary judgment and dismissal.

DISCUSSION

A writ of mandamus is available to compel the performance of an act that the law requires as a duty resulting from an office, trust or station, 2 or to remedy a manifest abuse of discretion. 3 A writ of certiorari, on the other hand, serves to remedy jurisdictional excesses committed by an inferior tribunal, board, or officer, exer *407 cising judicial functions. 4 Writs of mandamus and certiorari are extraordinary remedies generally unavailable if the petitioner has a plain, speedy and adequate legal remedy, such as an appeal from a final judgment. 5 Here, Dayside could challenge the partial summary judgment and the dismissal of its mechanic’s lien following the entry of a final judgment that resolves all of the parties’ claims for relief. 6 But even when an appeal is an adequate remedy, this court may nevertheless exercise its discretion to consider issuing a writ of mandamus or certiorari if an important issue of law needs clarification, and public policy will be served by this court’s invocation of its original jurisdiction. 7

Dayside argues that this court should consider the instant writ petition because whether a contractor may waive its mechanic’s lien rights is an issue of first impression in Nevada. Dayside elaborates that the issue “involves an important public policy of this state, specifically, the protection of materialmen and laborers.” Because this petition raises an issue of first impression involving the public policy of this state, we shall exercise our discretion to consider the petition.

Dayside does not complain that the district court lacked jurisdiction to dismiss its lien by partial summary judgment. Thus, we review the dismissal for a manifest abuse of discretion. 8

The district court dismissed Dayside’s lien based on the lien-waiver provision contained in its construction contract with Parkway. Dayside argues that any provision in a contract waiving a contractor’s mechanic’s lien rights is void as against public policy. It is well settled in other states, though, that “a clear and unambiguous provision in a contract whereby a contractor waives his rights to a mechanic’s lien or agrees not to file a lien is valid and binding and will preclude the contractor from asserting a right to *408 a lien.’ ’ 9 Some state legislatures have declared a lien waiver to be against public policy. 10 But other state legislatures have expressly permitted waivers. 11 Nevada’s legislative enactments are silent on the subject. 12 Absent a prohibitive legislative proclamation, a waiver of mechanic’s lien rights is not contrary to public policy. 13

Dayside further argues that the waiver here is unenforceable because there was a failure of consideration when Parkway failed to make the final payments. But even if Parkway breached the contract in regard to payment for work performed, that has no effect on the lien-waiver provision because “a mechanic’s lien, once waived, cannot be revived by the owner’s failure to abide by other independent covenants in the contract.” 14 A waiver provision merely limits the avenues available to a contractor to collect for expended materials or labor in the event the owner fails to pay. 15 Thus, an owner’s inadequate payment is an event anticipated by the parties to the contract, rather than a failure of consideration. 16

*409 Additionally, Dayside seems to contend that there was no consideration to support the waiver in the first place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
75 P.3d 384, 119 Nev. 404, 119 Nev. Adv. Rep. 48, 2003 Nev. LEXIS 54, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dayside-inc-v-first-judicial-district-court-ex-rel-carson-city-nev-2003.