Port City Construction Co. v. Adams & Douglass, Inc.

273 A.2d 121, 260 Md. 585, 1971 Md. LEXIS 1261
CourtCourt of Appeals of Maryland
DecidedFebruary 3, 1971
Docket[No. 231, September Term, 1970.]
StatusPublished
Cited by8 cases

This text of 273 A.2d 121 (Port City Construction Co. v. Adams & Douglass, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Port City Construction Co. v. Adams & Douglass, Inc., 273 A.2d 121, 260 Md. 585, 1971 Md. LEXIS 1261 (Md. 1971).

Opinion

Hammond, C. J.,

delivered the opinion of the Court.

The parties had at one another below over a mechanics’ lien filed in the Circuit Court for Prince George’s County by the appellee, a subcontractor. The appellant, the gen *587 eral contractor, bonded the lien claim and filed a petition to strike the lien grounded on the claim that in the written construction subcontract between them the appellee expressly waived the right to file a lien. The appellee answered the petition asserting:

“That the language of Paragraph 16 of the agreement referred to in the Petition as Exhibit ‘A’ is not intended to constitute a waiver of the right of respondent to file a mechanic’s lien in this case, and such a waiver is against public policy.”

Appellee also filed a “counterclaim” against appellant for $13,544.00, the amount claimed to be due and unpaid for work performed (and the amount claimed in the lien proceeding). Judge Bowie held that the right to file a lien had not been waived and dismissed the petition, and that “the counterclaim substantially duplicates the lien claim and that the counterclaim should therefore be stricken.” We reverse both orders.

It is clear that there is no public policy against the waiver of the right to file a mechanics’ lien (including a waiver to a prime contractor by a subcontractor) and that the law of Maryland contemplates with approval that there will be waivers.

The legislature supplemented the existing lien law in 1845 — Ch. 287, § 5, of the Laws of that year, now Code, Art. 63, § 3 — to provide “[t]hat no person having a lien * * * shall be considered as waiving such lien by granting a credit or receiving notes or other securities, unless the same be received as payment, or the said lien be expressly waived * * *. Thereafter, in various cases the Court of Appeals found and gave effect to an express waiver of the lien. See Willison v. Douglas, 66 Md. 99; Pinning v. Skipper, 71 Md. 347; Goldman v. Brinton, 90 Md. 259; and compare Maryland Brick Co. v. Spilman, 76 Md. 337, and Dickerson Lumber Co. v. Herson, 230 Md. 487, 492. See also “The Maryland Mechanics’ Lien Law — Its Scope and Effect,” 28 Md. L. Rev. 225, under *588 the subtitle “Waiver” at 233-235; the Annotation: “Mechanic’s Lien — Provision Against, 76 A.L.R.2d 1087, 1110; and 53 Am.Jur.2d Mechanics’ Liens §§ 290 and 334.

The real contention is as to the effect of the waiver sentence in the subcontract between appellant and appellee. The subcontract recites that appellant has entered into a prime contract with the named owner for construction work at a named site and that appellee “shall perform the work, namely in the following portions of the Prime Contract: All clearing, site preparation, demolition, excavating, grading, off site borrow,” (and so forth, in detail) for which appellant would pay $82,500. Other paragraphs supplied directions and agreements as to the work and the course and manner of payments, including Provision II (b), an agreement that:

“No progress payment or other payment hereunder shall become due and payable to Subcontractor unless (if Contractor shall so request) Subcontractor shall furnish (A) a sworn itemized statement of his costs to the end of the period covered by his requisitions, supported by bills and vouchers, (B) a copy of the payrolls covering all labor furnished in the execution of the work to the end of the period covered by his requisitions, together with a sworn certificate that such payrolls are correct and that the wages therein shown have been paid, (C) receipted bills showing payment for all materials and equipment and subcontracts utilized or performed in the execution of the work to the end of the period covered by his requisitions, or, in lieu thereof, duly executed releases of Owner, Contractor and Contractor’s payment bond, if any, and or waivers of lien from each of the materialmen, equipment suppliers and subcontractors of Subcontractor covering such materials, equipment and subcontracts, and (D) Subcontractor’s duly executed releases of Owner, Con *589 tractor and Contractor’s payment bond, if any, and or a waiver of lien by Subcontractor with respect to all of the work performed to the end of the period covered by his requisitions.”

Paragraph VII of the subcontract provided: “This Subcontract is subject to and includes the terms and conditions set forth on the other side of this page.”

The “terms and conditions” were spelled out in eighteen numbered paragraphs, some subdivided, covering a variety of matters, such as (1) permitting payment to the subcontractor without impairing certain rights of the contractor, (2) prohibiting the employment of workers objectionable to the contractor, (3) the risk of the work, and the risk of the performance of the work and the remedy of the contractor in regard thereto, (4) items the contractor considered to have induced him to enter into the contract, (10) the subcontractor’s responsibility for hinderance, delay or damage resulting from the manner in which he executes the work, (11) requiring the subcontractor, upon request, to furnish surety bonds to insure performance, (12) requiring the subcontractor to pay certain taxes, (13) prohibiting the delegation of the work, (15) obliging diligent prosecution of the work, and (16) the crucial paragraph, which deals with liens and the procedures to be employed to protect the contractor and the owner from liens. Paragraph 16 reads as follows:

“In the event that at any time any items of indebtedness incurred by Subcontractor in the performance of the work are unpaid, whether due or to become due, Contractor is authorized to make such payment directly to those to whom such indebtedness is payable, out of any moneys payable to Subcontractor. Subcontractor hereby expressly waives the right to file any lien or claim against the property of the Owner or Contractor or Contractor’s payment bond, if any, or against money due Contractor under the Prime Contract. If at any time there shall be any lien *590 or other claim for moneys due or to become due for which, if established, Contractor might be liable, and which would be chargeable to Subcontractor, Contractor shall have the right to bond said lien or otherwise discharge the indebtedness and/or to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify Contractor against such lien or other claim with interest, together with the expense incident to discharging such lien or other claim, including any premiums charged for a bond and any attorney’s fees and disbursements, all of which Subcontractor agrees to pay. Should Contractor give Subcontractor notice of any unpaid claim against the latter in connection with the work, Subcontractor shall be estopped from disputing liability for any such claim unless within three (3) days after such notice he indicates to Contractor in writing by registered mail that there is some sum different from that demanded owing or that there are no sums owing.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cearfoss Construction Corp. v. MMSG Ltd. Partnership
904 F. Supp. 450 (D. Maryland, 1995)
Barry Properties v. Fick Bros. Roofing Co.
353 A.2d 222 (Court of Appeals of Maryland, 1976)
Gerard C. Wallace Co. v. Simpson Land Co.
298 A.2d 881 (Court of Appeals of Maryland, 1973)
Grinnell Co. v. City of Crisfield
287 A.2d 486 (Court of Appeals of Maryland, 1972)
Brunecz v. DiLeo
283 A.2d 606 (Court of Appeals of Maryland, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
273 A.2d 121, 260 Md. 585, 1971 Md. LEXIS 1261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/port-city-construction-co-v-adams-douglass-inc-md-1971.