Holland Construction Corporation v. Bozzuto Contracting Company

CourtDistrict Court, D. Maryland
DecidedJuly 28, 2020
Docket8:17-cv-00937
StatusUnknown

This text of Holland Construction Corporation v. Bozzuto Contracting Company (Holland Construction Corporation v. Bozzuto Contracting Company) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holland Construction Corporation v. Bozzuto Contracting Company, (D. Md. 2020).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

HOLLAND CONSTRUCTION * CORPORATION * Plaintiff/Counter-Defendant * v. Civil Action No. 8:17-cv-00937-PX * BOZZUTO CONTRACTING COMPANY, et al. *

Defendants/Counter-Plaintiffs * ***

MEMORANDUM OPINION Pending in this construction dispute is a motion for partial summary judgment filed by contractor Bozzuto Contracting Company and its surety, Liberty Mutual Insurance Company (together “Bozzuto”) (ECF No. 67); a cross-motion for partial summary judgment filed by subcontractor Holland Construction Corporation (“Holland”) (ECF No. 69); a motion in limine filed by Holland to exclude expert testimony and opinions by Kenneth Kosteva (ECF No. 68); and a motion for certification of a question of law to the Maryland Court of Appeals filed by Holland (ECF No. 70). The matter has been fully briefed, and no hearing is necessary. See Loc. R. 105.6. For the reasons below, Bozzuto’s motion for partial summary judgment is GRANTED IN PART and DENIED IN PART; Holland’s cross-motion for partial summary judgment is DENIED; Holland’s motion in limine to exclude expert testimony is DENIED; and Holland’s motion for certification is DENIED. I. Background This case arises from a construction project at The Rotunda (the project), a mixed-use property in Baltimore, Maryland, featuring a shopping mall, restaurants, office space, and luxury apartments. ECF No. 67-26 at 2. Defendant Bozzuto Contracting Company was selected as the general contractor for this ambitious renovation. ECF 67-4. Bozzuto Contracting secured a payment bond from Defendant Liberty Mutual Insurance Company to guarantee payment to its subcontractors and material suppliers. ECF 67-1 at 5.

In January 2014, Bozzuto executed a subcontract with Holland Construction Corporation (“Holland”) to perform masonry work on the project. ECF 67-2 at 2. At the time of execution, the subcontract was valued at $3,857,000, which later grew to $4,923.309.21 after Bozzuto submitted several change orders. Id. at 3; ECF No. 67-3 ¶ 4. To date, Bozzuto has paid Holland $4,406,476.31. Id. The subcontract includes detailed architectural and structural drawings and project specifications. ECF No. 67-2 at 3 (Art. 2(a)). Under the subcontract terms, Holland agreed to perform its work in “strict accordance” with these documents, “without delay,” and to the “full satisfaction” of Bozzuto, as well as a third-party architect and the owner of the Rotunda. Id. at 2

(Art. 1(b)). Holland also agreed to be bound to the terms of the primary contract between Bozzuto and the owner, and to assume the “risks and responsibilities” that Bozzuto had assumed to the owner. Id. at 4 (Art. 5(a)). Under the prime contract terms, Holland agreed that if disputes arise, it would nonetheless “proceed diligently” with its work pending “final resolution” of the dispute. Id.; ECF No. 67-4 at 46 (Art. 4.3.4 of the General Conditions of the Contract for Construction). Holland completed the bulk of its masonry work by the end of 2015. ECF No. 67-3 ¶ 5. On November 30, 2015, Holland submitted a payment application for $205,161.74, in which it represented that it had completed over 99% of its masonry work (“Payment Application”). ECF No. 67-5 at 2. Also, as required under the subcontract and as part of the Payment Application, Holland submitted an “Acknowledgment of Payment and Settlement Due.” ECF No. 67-2 at 3 (Art. 3(c)); ECF 67-5 at 13. Pursuant to the Payment Application, Holland expressly “waive[d] any rights in the nature of lien, claims, or bond claims, which [Holland] may have for labor performed and/or materials furnished to date and agree[d] that [the requested] payment . . . is in

full settlement of any amount due . . . to date.” Id. The written waiver included a blank space for Holland to list any exceptions to such waiver. The space was left blank. Id. Although Holland represented in the Payment Application that it had completed its work, a number of items remained. ECF No. 69-2 at 3-4; ECF No. 67-12. In March 2016, Bozzuto sent Holland a list of outstanding items for completion based on the architect’s field reports. ECF Nos. 67-7 & 67-8. As Holland made progress on some of these items, it sent to Bozzuto a list of proposed change orders. ECF No. 67-3 ¶ 8. However, the requested change orders included some work that had been completed before the Payment Application. Id. In August 2016, Holland submitted to Bozzuto an updated list of change order requests in a document entitled “change request log.” Id. ¶ 9; ECF No. 67-9. Based on this log, Holland

sought payment for 66 claims, 47 of which are disputed in this litigation and of those, 28 relate work or materials provided before the Payment Application. ECF No. 67-3 ¶ 9; ECF No. 67-9; ECF No. 67-10. On December 1, 2016, Bozzuto shared the architect’s punch-list, which attributed hundreds of defective and incomplete items to Holland. ECF No. 67-3 ¶ 11; ECF No. 67-12. Holland returned to the site and, from January to February 2017, worked on correcting the items. ECF No. 69-2 at 3-4; ECF No. 69-3 ¶ 3. In March 2017, Holland notified Bozzuto that it had completed those punch-list items which, according to Holland, were within the scope of its masonry work, and documented in a spreadsheet its response to each punch-list item. ECF No. Id.; ECF No. 69-4. Hundreds of punch-list items remained outstanding. Id. Bozzuto objected to Holland not addressing the outstanding items. ECF No. 74-1 ¶¶ 7-9. Holland nonetheless demobilized and left the project. Id.; ECF No. 67-3 ¶ 12. Holland filed this action a month later, on April 11, 2017. ECF No. 1.

Bozzuto next sent Holland a “Notice to Cure Default” on May 16, 2017, which alerted Holland to the areas of deficient performance that Bozzuto viewed as constituting Holland’s material breach of the subcontract. ECF No. 67-13. As authorized under the subcontract, Bozzuto gave Holland three days to cure the default. Id. Holland’s president responded three days later in writing, stating that the punch list was complete and that remaining items were not Holland’s responsibility. ECF No. 69-5. Bozzuto next filed a counterclaim against Holland for breach of contract arising from Holland’s alleged incomplete and deficient work. ECF No. 10. Holland never returned to the site, and Bozzuto officially terminated the contract in December 2018. ECF No. 67-14. Relevant to Bozzuto’s counterclaim is Holland’s brick tie installation at the project. ECF

No. 67-8 at 2; ECF No. 67-12; ECF No. 67-15 at 2; ECF No. 67-17 at 3. Brick ties are structural supports installed between the interior and exterior walls of a building. ECF No. 67-1 at 14; ECF No. 67-18. Brick ties span the wall cavity by connecting the outer wall to the inner wall. Id. This is done by anchoring the brick tie in the inner wall and then embedding the brick tie in the mortar of the outer wall. Id. Improperly installed brick can cause “reduction in lateral load resistance,” and in turn may result in “distress or failure of the masonry facade.” ECF No. 67-26 at 7. For this reason, the subcontract required Holland to follow the manufacturer’s instructions when installing the brick ties and to embed them at least two inches into the external wall’s mortar. Id. at 6; ECF No. 67-21 at 2-3; ECF No. 67-22 at 2-3. Concerned with the quality of Holland’s brick-tie work throughout the project, Bozzuto hired Kenneth Kosteva, a civil engineer and associate principal at Wiss, Janey, Elstner Associates, Inc., to conduct a limited assessment of the brick-tie installation and, if appropriate, provide a remedial recommendation and an expert opinion on the sufficiency of Holland’s work.

ECF No. 67-26 at 2. Over six days, Kosteva opened the Rotunda walls in 31 places in order to take a representative sample of Holland’s brick-tie work. Id. at 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Jane Roe v. Jane Doe John Doe
28 F.3d 404 (Fourth Circuit, 1994)
Emmett v. Johnson
532 F.3d 291 (Fourth Circuit, 2008)
Beall v. Beall
434 A.2d 1015 (Court of Appeals of Maryland, 1981)
Harford County v. Town of Bel Air
704 A.2d 421 (Court of Appeals of Maryland, 1998)
Owens-Illinois, Inc. v. Cook
872 A.2d 969 (Court of Appeals of Maryland, 2005)
Perper v. FAYED, T/A FAYCO ELECTRIC SERVICE
234 A.2d 144 (Court of Appeals of Maryland, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
Holland Construction Corporation v. Bozzuto Contracting Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holland-construction-corporation-v-bozzuto-contracting-company-mdd-2020.