Alliant Techsystems, Inc., Global Environmental Solutions Business Division v. United States, Defendant-Cross

178 F.3d 1260, 1999 U.S. App. LEXIS 10979, 1999 WL 339023
CourtCourt of Appeals for the Federal Circuit
DecidedMay 28, 1999
Docket98-5016, 98-5044
StatusPublished
Cited by143 cases

This text of 178 F.3d 1260 (Alliant Techsystems, Inc., Global Environmental Solutions Business Division v. United States, Defendant-Cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alliant Techsystems, Inc., Global Environmental Solutions Business Division v. United States, Defendant-Cross, 178 F.3d 1260, 1999 U.S. App. LEXIS 10979, 1999 WL 339023 (Fed. Cir. 1999).

Opinions

Opinion for the court filed by Circuit Judge BRYSON. Concurring opinion filed by Circuit Judge PLAGER.

BRYSON, Circuit Judge.

The contract at issue in this government contract case contains an option clause. When the government sought to exercise that option, the contractor objected that the attempt was legally ineffective. After the contracting officer rejected the contractor’s position and directed it to perform the option, the contractor filed an action in the Court of Federal Claims seeking a declaration that it was not obligated to perform because the government had not validly invoked the option clause. The Court of Federal Claims held that the contractor was required to perform, but at a delivery rate lower than that ordered by the contracting officer. When the contractor refused to perform even at the rate directed by the court, the government terminated the contract for default.

We reject the government’s threshold argument that the Court of Federal Claims lacked jurisdiction over the contractor’s request for declaratory relief. On the merits, we hold that, although the option clause was not effectively exercised, the disputes clause of the contract required the contractor to perform in accordance with the decision of the Court of Federal Claims pending resolution of the action. Because the performance period required by the trial court’s decision has expired, our holding that the contractor has no obligations under the option clause does not affect the contractor’s obligations under the disputes clause. We therefore reverse the order of the Court of Federal Claims upholding the validity of the option exercise, but we affirm the court’s order that Alliant was contractually obligated to perform the option quantity at a rate of 1550 bombs per month, although we do so based on the disputes clause rather than the option clause.

I

In October 1995, Global Environmental Solutions, Inc., a division of Alliant Tech-systems, Inc., (Alliant) entered into a contract with the United States Army to demilitarize 24,497 bombs. The contract included an “Evaluated Option for Increased Quantity,” which allowed the Army to increase the number of bombs to be demilitarized by up to 100 percent of the base number in the contract. The option provision specified the time period during which the option could be exercised, the time at which option performance was to begin, and the monthly rate at which the option quantity was to be delivered. The contract also incorporated by reference the standard “disputes clause,” which is set forth at 48 C.F.R. § 52.233-1 and provides as follows:

[1264]*1264Disputes
(a) This contract is subject to the Contract Disputes Act of 1978 as amended (41 U.S.C. 601-613).
. . . . .
(i) The contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under the contract, and comply with any decision of the Contracting Officer.

During the summer of 1997, the contracting officer advised Alliant that he planned to exercise the evaluated option in full by increasing the number of bombs to be demilitarized by 100 percent. Alliant objected, arguing that the time for exercising the option had expired. Nonetheless, on August 4, 1997, the contracting officer issued a unilateral modification of the contract purporting to exercise the option.

In a letter to the contracting officer dated September 11, 1997, Alliant argued that the contracting officer’s attempt to exercise the option was ineffective. Alli-ant took the position'that it was not bound to perform because (1) the attempted exercise of the option was untimely and (2) the contracting officer had specified a delivery rate that was not set forth in the option clause. On September 17, 1997, the contracting officer rejected Alliant’s arguments by letter and insisted that Alli-ant demilitarize the additional bombs at the specified rate. The contracting officer disagreed with Alliant’s interpretation of the delivery rate and the time period for exercising the option. Pursuant to the contracting officer’s schedule, the first delivery of demilitarized bombs under the option clause was due on October 31, 1997.

On the day of the contracting officer’s letter, Alliant filed a complaint in the Court of Federal Claims seeking a declaration that it was not required to perform the option. Alliant also sought an injunction barring the government from enforcing the option clause or from terminating the contract for default for failure to perform the option. The trial court ruled that it did not have jurisdiction to enter an injunction, but that it had jurisdiction to issue a declaratory judgment. On October 31, 1997, the court addressed the merits of Alliant’s request for declaratory relief.

In its order, the Court of Federal Claims declared that Alliant was required to perform the option, but at a rate lower than that ordered by the contracting officer. Alliant has appealed from the aspect of the court’s order holding that the option was effectively exercised. The government has appealed from the court’s ruling that it had jurisdiction to grant declaratory relief and that the delivery rate specified by the contracting officer was too high.

II

The Tucker Act defines, the jurisdiction of the Court of Federal Claims with respect to disputes arising under the Contract Disputes Act (CDA) as follows:

The Court of Federal Claims shall have jurisdiction to render judgment upon any claim by or against, or dispute with, a contractor arising under section 10(a)(1) of the Contract Disputes Act of 1978, including a dispute concerning termination of a contract, rights in tangible or intangible property, compliance with cost accounting standards, and other nonmonetary disputes on which a decision of the contracting officer has been issued under section 6 of that Act.

28 U.S.C. § 1491(a)(2). The parties agree that the CDA grants jurisdiction to the Court of Federal Claims and the agency boards over a contractor’s request for relief only when the appeal or action is based on a qualifying claim filed by the contractor and a final decision by the contracting officer. See generally Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed.Cir.1995) (in banc). In the portion of its brief directed to jurisdiction, the government argues that the Court of Federal Claims lacked jurisdiction over the complaint in this case because the complaint was not preceded [1265]*1265by either a qualifying claim by Alliant or a final decision by the contracting officer. Alliant responds that the correspondence between the parties is properly characterized as constituting a claim and a final decision.

A

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryan Ashush JV
Armed Services Board of Contract Appeals, 2025
Samho Enterprise
Armed Services Board of Contract Appeals, 2025
Mindseeker, Inc.
Armed Services Board of Contract Appeals, 2024
Konecranes Nuclear Equipment & Services, LLC
Armed Services Board of Contract Appeals, 2024
North Wind Construction Services, LLC
Armed Services Board of Contract Appeals, 2024
PAE Applied Technologies LLC
Armed Services Board of Contract Appeals, 2023
J&J Maintenance, Inc., d/b/a J&J Worldwide Services
Armed Services Board of Contract Appeals, 2023
Fluor Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2022
Systems Application & Tech v. United States
26 F.4th 163 (Fourth Circuit, 2022)
M. Nicolas Enterprises, Llc.
Federal Claims, 2021
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2021
Northrop Grumman Corporation
Armed Services Board of Contract Appeals, 2021

Cite This Page — Counsel Stack

Bluebook (online)
178 F.3d 1260, 1999 U.S. App. LEXIS 10979, 1999 WL 339023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alliant-techsystems-inc-global-environmental-solutions-business-division-cafc-1999.