Essex Electro Engineers, Inc. v. The United States

960 F.2d 1576, 37 Cont. Cas. Fed. 76,304, 92 Daily Journal DAR 6042, 1992 U.S. App. LEXIS 7162, 1992 WL 76022
CourtCourt of Appeals for the Federal Circuit
DecidedApril 17, 1992
Docket91-5096
StatusPublished
Cited by26 cases

This text of 960 F.2d 1576 (Essex Electro Engineers, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Essex Electro Engineers, Inc. v. The United States, 960 F.2d 1576, 37 Cont. Cas. Fed. 76,304, 92 Daily Journal DAR 6042, 1992 U.S. App. LEXIS 7162, 1992 WL 76022 (Fed. Cir. 1992).

Opinion

MICHEL, Circuit Judge.

Essex Electro Engineers, Inc. appeals the summary judgment of the United States Claims Court denying Essex’s claim for interest under the Contract Disputes Act (CDA). Essex Electro Engineers, Inc. v. United States, 22 Cl.Ct. 757 (1991). The Claims Court held that Essex’s submissions were not CDA claims entitling Essex to interest because there was no dispute at the time they were made. However, we hold that the submissions are not claims because they did not seek a sum certain as a matter of right as required by the Federal Acquisition Regulation (FAR) which implements the CDA. Nevertheless, because the Claims Court correctly concluded that the government was entitled to judgment as a matter of law, we affirm.

I. BACKGROUND

Essex contracted with the Naval Regional Contracting Center to overhaul and reconfigure 122 mobile electric power plants. Three change orders were issued during performance of the contract. The principal amounts due to Essex under the three change orders have been paid as a result of an administrative settlement. Essex now seeks interest on those amounts from the date it made submissions purporting to be claims under the CDA.

A. The 100 Percent Replacement Parts Change Order

The first change order required that certain parts be subject to a 100 percent replacement requirement. In response to a letter from the Administrative Contracting Officer (ACO) requesting a cost proposal *1578 for such a change, Essex submitted a cost proposal on February 14, 1986. On October 7, 1986, without ruling on Essex’s proposal, the ACO unilaterally executed the change order which provided that “[a]n equitable firm-fixed price for this change order shall be negotiated with an appropriate Supplemental Agreement.”

On April 13, 1987, Essex submitted a revised cost proposal which reduced the amount proposed earlier and noted that

prices are based upon purchase orders and cost estimates. The engineering and labor hours are estimates based on our experience in reviewing the work to be performed and estimating what the direct labor and engineering time and cost will be.

Although the letter contained a certification in the form required by section 6 of the CDA, it did not request a final decision by the ACO.

In February 1988, the parties “defini-tized” the change order by executing an amendment to the contract. The “firm-fixed price” for the change order that was agreed to was less than that offered by Essex in its revised proposal. Upon Essex’s submission of an invoice for the amount due under the amendment to the contract, the government made payment on March 14, 1988.

On May 25, 1989, Essex sent a letter to the ACO which purported to be a “claim for interest due on the payment made on the certified claim arising from the referenced Change Order. We request your final decision on this claim within sixty days in accordance with the [CDA].” Essex based this claim for interest on its April 13, 1987 submission of a revised cost proposal and requested interest for the period commencing with that date.

Without determining whether the April 13, 1987 submission was a CDA claim, which would entitle Essex to interest, the ACO allowed a limited amount of interest. Elaborating on the interest provision of the CDA, the FAR allows “interest on a contractor’s claim on the amount found due and unpaid from (a) the date the contracting officer receives the claim ... or (b) the date payment otherwise would be due, if that is later....” 48 C.F.R. § 33.208 (1991). Because payment ordinarily would be due 20 days after receipt of an invoice, and because shipment preceded the invoice, the ACO calculated interest for each shipment for the period beginning 20 days after acceptance of the shipment until final payment. To arrive at the final interest amount due, the ACO also credited progress payments to the principal payments as they came due. The final interest amount found to be due, however, has not been paid by the government. 1

B. The Support Equipment Change Order

The same basic sequence of events occurred with respect to the second change order. On April 23,1986, the ACO issued a unilateral modification to the contract. This change order required that the contractor furnish material, parts, labor and services for the incorporation of “winterization kits” into each of the mobile power plants. It also required that Essex submit a price proposal within 30 days. The record is unclear as to whether a submission was made immediately following the change order; however, on April 15, 1987, Essex submitted a “revision to our estimated cost proposal submitted ... 19 June 1986.” Once again, the letter stated that prices were based upon

purchase orders and cost estimates. The engineering and labor hours are estimates based on our experience in reviewing the work to be performed and estimating what the direct labor and engineering time and cost will be.

This letter held itself out to be a “claim” and was certified. It was never decided by the ACO. However, after an audit and several days of price negotiation, the parties executed an amendment on March 2, 1989. Upon Essex’s submission of an invoice to the government for the amount due under the amendment to the contract, *1579 it received payment on March 16 or 17, 1989.

On May 2, 1989, Essex sent a letter to the ACO which held itself out to be a claim for interest under the CDA on the settlement sum. Essex based this claim for interest on its revised cost proposal dated April 15, 1987. Once again, without ruling on whether the April 15, 1987 letter constituted a claim, the ACO allowed a limited amount of interest calculated from 20 days after shipment. This interest has not been paid.

C. The “Over and Above” Work Change Order

On September 24, 1986, the ACO issued another unilateral modification to the contract. This change order allowed the contractor to “propose additional repairs and reconfigurations to the mobile power units beyond those contemplated by the original contract.” Essex, 22 Cl.Ct. at 762. Under this amendment, Essex submitted inspection reports which included proposals for “over and above” work on each unit. Each proposal indicated what the additional costs for repairs would be and requested government approval to proceed with the additional work. For all “over and above” work proposed by the contractor that was authorized by the government, the price was later definitized.

The inspection reports prior to the March 27, 1987 report were not themselves labeled as “claims”; however, in a letter dated January 26, 1987, Essex referred to all of the prior inspection reports as claims. The March 27, 1987 report, and all subsequent reports, were characterized on their face as “claims.” However, none of the reports demanded a decision by the ACO as all were mere proposals for additional work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Islands Mechanical Contractor, Inc.
Armed Services Board of Contract Appeals, 2017
Sharp Electronics Corporation v. Army
707 F.3d 1367 (Federal Circuit, 2013)
J.P. Donovan Construction, Inc. v. Mabus
469 F. App'x 903 (Federal Circuit, 2012)
Executive Court Reporters, Inc. v. United States
29 Fed. Cl. 769 (Federal Claims, 1998)
Munitions Carriers Conference, Inc. v. United States
932 F. Supp. 334 (District of Columbia, 1996)
Davies Precision Machining, Inc. v. United States
35 Fed. Cl. 651 (Federal Claims, 1996)
Cincinnati Electronics Corp. v. United States
39 Cont. Cas. Fed. 76,724 (Federal Claims, 1994)
Detroit International Bridge Co. v. United States
39 Cont. Cas. Fed. 76,711 (Federal Claims, 1994)
Boeing Co. v. United States
39 Cont. Cas. Fed. 76,663 (Federal Claims, 1994)
Aerolease Long Beach v. United States
31 Fed. Cl. 342 (Federal Claims, 1994)
Kirkham Constructors, Inc. v. United States
39 Cont. Cas. Fed. 76,597 (Federal Claims, 1993)
L. Addison & Associates, Inc. v. United States
27 Fed. Cl. 181 (Federal Claims, 1992)
CYR Construction Co. v. United States
27 Fed. Cl. 153 (Federal Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
960 F.2d 1576, 37 Cont. Cas. Fed. 76,304, 92 Daily Journal DAR 6042, 1992 U.S. App. LEXIS 7162, 1992 WL 76022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/essex-electro-engineers-inc-v-the-united-states-cafc-1992.