Santa Fe Engineers, Inc. v. H. Lawrence Garrett, Iii, Secretary of the Navy

991 F.2d 1579, 38 Cont. Cas. Fed. 76,506, 1993 U.S. App. LEXIS 9500, 1993 WL 129181
CourtCourt of Appeals for the Federal Circuit
DecidedApril 27, 1993
Docket92-1361
StatusPublished
Cited by11 cases

This text of 991 F.2d 1579 (Santa Fe Engineers, Inc. v. H. Lawrence Garrett, Iii, Secretary of the Navy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Santa Fe Engineers, Inc. v. H. Lawrence Garrett, Iii, Secretary of the Navy, 991 F.2d 1579, 38 Cont. Cas. Fed. 76,506, 1993 U.S. App. LEXIS 9500, 1993 WL 129181 (Fed. Cir. 1993).

Opinion

*1580 COWEN, Senior Circuit Judge.

The appellant (Santa Fe or Contractor) entered into a contract with the Navy for the construction of a facility for the retrieval of spent space shuttle rocket booster tubes at Port Hueneme, California. After completion of the contract, Santa Fe filed a claim for an equitable adjustment in an amount exceeding $50,000 with the contracting officer. Upon denial of the claim, the contractor appealed to the Armed Services Board of Contract Appeals (ASBCA), which held a hearing on the merits.

After the hearing had been completed, this court issued its decisions in United States v. Grumman Aerospace Corp., 927 F.2d 575 (Fed.Cir.1991), and Dawco Construction, Inc. v. United States, 930 F.2d 872 (Fed.Cir.1991). The Board determined that these decisions raised a question regarding the Board’s jurisdiction over the appeal. Therefore, instead of deciding the case on the merits, the Board issued an order requiring Santa Fe to show cause why the appeal should not be dismissed. Both parties were directed to comment on the effect of the two decisions on the Board’s jurisdiction. After considering the parties’ responses, the Board dismissed the appeal for lack of subject matter jurisdiction, without prejudice to Santa Fe’s sub-mittal of a properly certified claim to the contracting officer, ASBCA No. 36292, 92-2 BCA (CCH) 1124795 (1992).

The Board held: (1) The claim submitted by the contractor to the contracting officer did not meet the requirements of a claim under the Contract Disputes Act (CDA), 41 U.S.C. § 605 (1988), as implemented by the Defense Acquisition Regulation, DAR 7-103.12, and as interpreted by Dawco; and (2) the contractor’s vice president, who signed the certification, was not an appropriate certifying individual under the contract and the same regulation, as interpreted by Grumman.

For the reasons to be set forth, we affirm the Board’s decision that Santa Fe’s submissions did not constitute a claim under the CDA. Therefore, we need not decide whether Santa Fe’s vice president was qualified to certify the claim.

BACKGROUND

Although Santa Fe challenges the conclusions which the Board drew from its factual findings, there is little or no dispute as to the underlying, material facts. The claim which culminated in this appeal had its origin in the discovery by Santa Fe on June 14, 1984, of unsuitable soil conditions in the area where a ramp was to be constructed. The Navy issued a stop work notice for the ramp and sent Santa Fe a proposed change order (PCO 46), in which the Navy requested that Santa Fe submit a proposal for solving the unsuitable soil conditions in the ramp area. Santa Fe’s first proposal for PCO 46 was a ballpark estimate, which was rejected and resulted in the Navy’s cancellation of PCO 46 on August 7, 1984. On the same date, the Navy issued PCO 47, which proposed a deletion of the ramp.

On November 21, 1984, Santa Fe submitted a cost proposal in the amount of $265,-942, based on the stop work notice and the related ramp problems. The proposal included a time extension request of 72 days. The letter stated that a certification of the proposal would be forthcoming. The Board found that the parties were not in dispute over the proposal at that time.

On December 11, 1984, a meeting was held among Mr. Stephen Riley, Santa Fe’s vice president, and the Navy representatives to negotiate the changes relating to the deletion of the ramp. A bilateral agreement was reached by the parties granting the government credit in the amount of $14,115. The results of the meeting with respect to Santa Fe’s cost proposal of November 21, 1984, were confirmed in a letter from the Navy to Santa Fe dated January 2, 1985, which read in part:

A meeting was held on 11 Dec 84 with your Stephen Riley to discuss the ramp deletion change.... It was determined that more information and justification was needed before the government could properly evaluate your proposed costs.

*1581 The letter detailed the nature of the information which the Navy requested. The Board found that the parties were not in dispute over the cost proposal at that time.

Santa Fe responded to the Navy’s letter of January 10, by its letter of February 6, 1985, stating that the Navy officials:

[Mjay well totally misunderstand the effect of stopping work, requesting proposals and canceling work and misguiding future directives. We therefore, find it necessary to consider our cost proposal in response to your PCO-46 a claim and shall certify it as such.

The letter was signed by Santa Fe’s vice president and included a certification in compliance with the CDA. Santa Fe did not request a decision of the contracting officer at that time. On February 6, 1985, the same day that Santa Fe certified its cost proposal as a claim, Santa Fe wrote the Navy stating that Santa Fe would be providing additional data “to help the owner better understand the proposal.”

By letter of April 16, 1985, Santa Fe wrote the Navy in part as follows: “You have requested previously additional costs associated with changes and delays at the Wharf Construction area. Your letter of January 2, 1985, acknowledged our claim but requested additional information.” The letter enclosed certain data but did not request a decision of the contracting officer. Instead, Santa Fe requested that a meeting be held to continue negotiations. The letter also reduced Santa Fe’s claim for time extensions from 72 to 57 calendar days.

Another meeting was held on September 24, 1985, following which Santa Fe provided the Navy with additional material in support of its proposal of November 21, 1984.

A year later on December 2, 1986, Santa Fe wrote the government stating in part: “Our claim to you for this time, as well as the direct costs, has been in to you and certified for some time. If you care to have another meeting on this matter prior to my requesting a final decision, please let me know within (10) days.” The Navy replied by letter of March 17, 1987, stating that it had found insufficient justification for a time extension associated with the ramp deletion and advised Santa Fe that if it disagreed, it should proceed in accordance with the Disputes clause of the contract.

Santa Fe replied on May 28,1987, stating in part as follows: “Due to the length of time this claim has been before your office and in light of our previous certification, we at this time request the issuance of a written final decision from the Contracting Officer concerning this claim.” Although more than two years had elapsed since February 6, 1985, when Santa Fe certified its proposal as a claim, Santa Fe did not attach a claim certification to its letter, and did not otherwise execute a new claim certification.

On September 29, 1988, the contracting officer issued his decision, denying Santa Fe’s claim for direct costs in part and its claim for delayed costs in total.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bannum, Inc. v. United States
40 Cont. Cas. Fed. 76,807 (Federal Claims, 1995)
Alvarado Construction, Inc. v. United States
39 Cont. Cas. Fed. 76,708 (Federal Claims, 1994)
Boeing Co. v. United States
39 Cont. Cas. Fed. 76,663 (Federal Claims, 1994)
Kirkham Constructors, Inc. v. United States
39 Cont. Cas. Fed. 76,597 (Federal Claims, 1993)
Roy v. Brown
5 Vet. App. 554 (Veterans Claims, 1993)
Blake Construction Co. v. United States
38 Cont. Cas. Fed. 76,537 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
991 F.2d 1579, 38 Cont. Cas. Fed. 76,506, 1993 U.S. App. LEXIS 9500, 1993 WL 129181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/santa-fe-engineers-inc-v-h-lawrence-garrett-iii-secretary-of-the-navy-cafc-1993.