Transamerica Insurance Corporation, Inc., for and on Behalf of Stroup Sheet Metal Works v. The United States

973 F.2d 1572, 38 Cont. Cas. Fed. 76,374, 93 Daily Journal DAR 1281, 1992 U.S. App. LEXIS 20875, 1992 WL 213073
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 4, 1992
Docket92-5044
StatusPublished
Cited by146 cases

This text of 973 F.2d 1572 (Transamerica Insurance Corporation, Inc., for and on Behalf of Stroup Sheet Metal Works v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transamerica Insurance Corporation, Inc., for and on Behalf of Stroup Sheet Metal Works v. The United States, 973 F.2d 1572, 38 Cont. Cas. Fed. 76,374, 93 Daily Journal DAR 1281, 1992 U.S. App. LEXIS 20875, 1992 WL 213073 (Fed. Cir. 1992).

Opinion

BENNETT, Senior Circuit Judge.

DECISION

Transamerica Insurance Corporation appeals from a bench ruling of the United States Claims Court which granted the United States’ motion to dismiss Trans-america’s complaint for lack of subject matter jurisdiction. The Claims Court found that the contractor’s submissions did not *1574 constitute a claim under the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 601, because they did not request a final decision from the contracting officer. In the alternative, the Claims Court held that the contractor’s claim certification was fatally flawed because it was unduly qualified. This court reverses and remands.

BACKGROUND

On September 15, 1987, the United States Army Corps of Engineers (Government) entered a contract with contractor Bodenhamer Building Corporation (BBC) for the construction of Bowley Elementary School at Fort Bragg, North Carolina, for the contract price of $3,804,000. On October 6, 1987, Bodenhamer entered into a subcontract with Stroup Sheet Metal Works for specified roofing work under the contract. Transamerica Insurance Corp., acting as surety, issued payment and performance bonding for the Bowley project.

Construction under the roofing subcontract began in late summer 1988 at which time Stroup discovered a disparity between the actual requirements of the subcontract and the roof plan on which it had based its bid and so informed BBC. In an August 2, 1988 letter, BBC notified the Area Engineer at Fort Bragg of the specification discrepancy, informing him that the roof plan was incorrectly scaled and that in actuality there was “approximately two times the square footage shown on the roof plan.” BBC further notified the Government that this discrepancy would require additional material, labor and time, with delays affecting the completion date, and that as of 3 p.m. on August 2, Stroup’s roofing operation had been stopped until direction could be received on how to proceed.

Responding to BBC in a letter dated August 3, 1988, the contracting officer’s authorized representative stated that: (1) as the contractor, BBC was responsible for and should have reviewed the drawings and that “approval by the contracting officer shall not relieve the contractor from responsibility for any errors or omissions in such drawings;” (2) the contractor should have notified the contracting officer of these discrepancies earlier; (3) drawings which purport to be done to scale are not necessarily binding; (4) “the Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby;” and (5) BBC was requested to submit a written corrective plan of action by August 10, 1988.

On August 9, 1988, BBC drafted two letters, one to its subcontractor Stroup and one to the contracting officer. The Stroup letter notified the subcontractor of the Government’s denial of responsibility, instructed Stroup to continue to work on the project pending resolution of the claim, and offered to be the “conduit” for an equitable adjustment claim which Stroup could make to the contracting officer. The letter to the contracting officer stated BBC's position that the problem in the specifications arose due to errors in the contract drawings and thus that “this problem is a design error which is the responsibility of the Government and not the Contractor.” BBC further stated, “[w]e can offer no written corrective plan of action inasmuch as we have done nothing wrong which needs to be corrected. ... We recognize your letter as a directive ... which constitutes a constructive change to the Contract. Accordingly, we hereby notify you that we are proceeding as directed by you and reserving all rights granted us under the Contract for an equitable adjustment in the Contract for all additional costs incurred, both direct and indirect, as a result of this design deficiency.”

In an August 26, 1988 letter, Stroup submitted to BBC a request for equitable adjustment of the subcontract, maintaining that the alleged defect in the roofing specifications increased the cost of performance by $241,919. As part of the equitable adjustment request, Stroup included a request for an extension of time for the duration of construction due to the expanded scope of work of 135 days and included a certification signed by Stroup’s president. In a September 1, 1988 letter, BBC submitted Stroup’s claim and request for eq *1575 uitable adjustment to the contracting officer and included a certification executed by BBC’s president.

On or about September 6, 1988, BBC notified the Government of its intention to abandon its contractual obligations and on September 8, 1988, the Government terminated the BBC contract for default. On September 15, 1988, Stroup learned that BBC’s contract was in default and that the surety Transamerica would be taking over the project through completion contractor Sebeo. Thereafter, Transamerica entered a ratification agreement with Stroup for the completion of Stroup’s contractual obligations on the project. On November 7, 1988, Transamerica and the Government entered into a surety takeover agreement under which Transamerica agreed to take over and complete performance of the BBC contract. The agreement provided that the “surety shall have the right to pursue and settle all existing and future claims that arise under this contract.”

On November 25, 1988, Stroup wrote the Chief of the Claims Section of the U.S. Army Corps of Engineers, urging him to make an expeditious decision on the pending equitable adjustment claim which had been submitted on September 1. On February 21, 1989, Stroup talked by telephone with both the Government and the former general contractor in an effort to get a final decision on its claim. After the conversation, on March 8, 1989, Stroup submitted to Transamerica and to the Government a revised cost summary on Form 1411 with a revised claim for equitable adjustment. On March 15, 1989, the contracting officer requested submission of supplemental information, including all cost and pricing data as well as a recertification of the claim by the surety. The contracting officer also required that Transamerica adopt Stroup’s claim as its own “since Stroup does not enjoy privity of contract with the Government” and that if the request for more time was “intended to assert a right to a contract time extension, Stroup and/or Transamerica should submit full justification for the requested time extension.”

. On March 28, 1989, the contracting officer issued a preliminary decision denying the request for equitable adjustment. The decision stated:

The claim is presented as a request for equitable adjustment and the basis of it is not clearly stated.... I acknowledge that the graphic scale provided was erroneous and reliance upon dimensions scaled from that undimensioned schematic plan would have resulted in quantities of the various elements of the roofing system which were substantially less than the quantities actually required to be performed_ Under the circumstances of these bid documents, any reliance upon the Roof Plan for quantities of required work was imprudent and such reliance is at the risk of the bidder. Based on the above, it is my present intent to deny your claim; however, this is not my final decision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platinum Services, Inc.
Armed Services Board of Contract Appeals, 2024
American Technical Services, Inc
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Kamaludin Slyman CSC
Armed Services Board of Contract Appeals, 2020
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Vanquish Worldwide, LLC v. United States
134 Fed. Cl. 72 (Federal Claims, 2017)
Bruhn Newtech, Inc. v. United States
129 Fed. Cl. 656 (Federal Claims, 2016)
Federal Contracting, Inc. v. United States
128 Fed. Cl. 788 (Federal Claims, 2016)
MicroTechnologies, LLC
Armed Services Board of Contract Appeals, 2016
Securiforce International America, LLC v. United States
125 Fed. Cl. 749 (Federal Claims, 2016)
Meridian Engineering Company v. United States
122 Fed. Cl. 381 (Federal Claims, 2015)
Jacqueline R. Sims, LLC v. United States
600 F. App'x 760 (Federal Circuit, 2015)
Bizhan Niazi Logistic Services Company
Armed Services Board of Contract Appeals, 2014
Certified Construction Company of Kentucky, LLC
Armed Services Board of Contract Appeals, 2014
Kellogg Brown & Root Services, Inc. v. United States
115 Fed. Cl. 168 (Federal Claims, 2014)
K-Con Building Systems, Inc. v. the United States 0
114 Fed. Cl. 595 (Federal Claims, 2014)
Diversified Maintenance Systems, Inc. v. United States
110 Fed. Cl. 612 (Federal Claims, 2013)
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
973 F.2d 1572, 38 Cont. Cas. Fed. 76,374, 93 Daily Journal DAR 1281, 1992 U.S. App. LEXIS 20875, 1992 WL 213073, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transamerica-insurance-corporation-inc-for-and-on-behalf-of-stroup-sheet-cafc-1992.