K-Con Building Systems, Inc. v. United States

115 Fed. Cl. 558, 2014 U.S. Claims LEXIS 135, 2014 WL 1348155
United States Court of Federal Claims·Decided April 7, 2014·No. 1:05-cv-00981·Published·Cited by 3 cases

Opinion

OPINION AND ORDER

SWEENEY, Judge

Plaintiff K-Con Building Systems, Inc. filed three suits in this court concerning its contracts with the United States Coast Guard (“Coast Guard”) for the design and construction of prefabricated metal buildings in Elizabeth City, North Carolina, St. Peters-burg, Florida, and Port Huron, Michigan. After the court issued summary judgment rulings in each case and held trial in the Elizabeth City case, the parties engaged in settlement discussions. Those discussions revealed several issues that required resolution prior to any settlement. Accordingly, the parties have filed the relevant motions in all three cases.

In this case, which concerns the building in St. Petersburg, plaintiff moves for partial summary judgment on the issue of liquidated damages, and defendant cross-moves for summary judgment on all of plaintiffs remaining claims. For the reasons set forth below, the court denies both motions.

*560 I. BACKGROUND

In April 2001, the United States General Services Administration (“GSA”) awarded plaintiff a Federal Supply Schedule contract for Prefabricated Structures and Outdoor Smoking Shelters. 1 Subsequently, in the summer of 2003, the Coast Guard solicited a proposal from plaintiff for the design and construction of a prefabricated structure to serve as a supply warehouse in St. Peters-burg. The Coast Guard divided the warehouse project into three components: a base item and two options items. The base item consisted of the design and construction of the warehouse, and included all site work, utilities, and parking. The option items concerned the construction of additional facilities within the warehouse. The Coast Guard awarded the contract to plaintiff on September 5, 2003, but due to funding issues, only the base item was awarded. Along with other standard clauses, the contract contained clauses pertaining to changes, differing site conditions, suspension of work, and liquidated damages. Of particular interest in this case is the liquidated damages clause that provided for liquidated damages in the amount of $564 for each day that plaintiff failed to complete the building beyond the contractually specified completion date, which, on the date of contract award, was July 26, 2004.

A. Contract Performance

1. Design Submissions

The contract award triggered deadlines related to construction bonds, project schedules, project meetings, the commencement of work, and the initial design submission. On October 15, 2003, after approving plaintiffs bonds, the Coast Guard permitted plaintiff to begin work at the job site. Shortly thereafter, on November 4, 2003, the Coast Guard conducted a delayed postaward kickoff meeting with plaintiff. During the meeting, the participants discussed a variety of issues related to the design documents that plaintiff would provide to the Coast Guard. In addition, plaintiff informed the Coast Guard that its geotechnical firm had begun its site investigation, and that it had hired both an architect and a firm to produce the site work and civil work designs.

Pursuant to the contract specifications, plaintiff was required to present to the Coast Guard a schedule that reflected plaintiffs submission of the design in three phases (a “50% design,” a “100% design,” and a “final design”). In the schedule it submitted to the Coast Guard on November 7, 2003, plaintiff indicated that it had begun working, to an unspecified extent, on the 50% design on October 16, 2003 — the day it likely received the Coast Guard’s notice to proceed — and planned to submit it to the Coast Guai’d around November 14, 2003. In that same schedule, plaintiff indicated that it anticipated beginning construction on December 29, 2003, erecting the building beginning on March 22, 2004, and completing the project around May 27, 2004 — two months before the contract completion date.

Plaintiff did not meet its self-imposed November 14, 2003 deadline for submitting the 50% design to the Coast Guard. Instead, it appears that plaintiff submitted the 50% design shortly after December 10, 2003. In a January 6, 2004 letter, the Coast Guard noted several issues with the design that required plaintiffs attention before it could conduct its official review. These issues included electronic files that did not comply with computer-aided-design requirements, incomplete drawing sets, systems missing from the drawings, and missing calculations for the foundation design. To address the Coast Guard’s comments, plaintiff was required to have its designer redesign the foundation, which entailed making new calculations and amending its drawings.

Plaintiff resubmitted a complete 50% design on February 2, 2004, and its foundation *561 calculations on February 3, 2004. The Coast Guard approved the design three days later. Plaintiff then submitted its 100% design on February 25, 2004. In a cover letter to its review comments, the Coast Guard noted that it “consider[ed] the design, especially the Structural design, incomplete” and requested that plaintiff make corrections.

2. Construction Begins

Pursuant to the contract specifications, plaintiff could not begin construction until the Coast Guard approved the final design. That approval occurred some time before April 6, 2004, when plaintiff and the Coast Guard conducted a preconstruction conference. Plaintiff ultimately began mobilizing for construction on May 1, 2004, with actual construction beginning during the week of May 10, 2004.

Upon the commencement of construction, plaintiff began work on the building’s foundation. According to an as-built schedule included with defendant’s expert’s report, plaintiff performed its initial work on the foundation from May 13 to May 24, 2004; poured the footings from May 24 to June 1, 2004; poured the walls from June 1 to June 11, 2004; and completed the foundation from June 11 to June 26, 2004. 2 The progression of work reflected in this as-built schedule was a departure from what plaintiff had initially planned when it began construction. As early as May 13, 2004, plaintiff had anticipated completing the foundation by June 1, 2004, the date that it had scheduled an order for concrete to arrive on the job site. 3

During a June 15, 2004 progress meeting, plaintiff and the Coast Guard discussed several issues related to constructing the foundation, pouring the slab, and erecting the building. 4 One issue discussed was plaintiffs late start on construction. Because of this late start, the Coast Guard considered most remaining items on the project schedule as being on the critical path of performance. Then, with respect to the foundation and slab, the Coast Guard expressed its concern that plaintiff was “not following proper construction practices at the jobsite especially regarding the building slab and foundation,” noting that its “[¡Inspector had to reject two concrete trucks last Friday (6/11/04) as they sat around the jobsite over two hours because [plaintiff] was not ready to use the concrete in the trucks.”

Free access — add to your briefcase to read the full text and ask questions with AI

K-Con Building Systems, Inc. v. United States, 115 Fed. Cl. 558, 2014 U.S. Claims LEXIS 135, 2014 WL 1348155 (uscfc 2014).

115 Fed. Cl. 558 (K-Con Building Systems, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related