K-Con Building Systems, Inc. v. United States

114 Fed. Cl. 722, 2014 U.S. Claims LEXIS 223, 2014 WL 785167
CourtUnited States Court of Federal Claims
DecidedFebruary 26, 2014
Docket1:05-cv-00914
StatusPublished
Cited by2 cases

This text of 114 Fed. Cl. 722 (K-Con Building Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K-Con Building Systems, Inc. v. United States, 114 Fed. Cl. 722, 2014 U.S. Claims LEXIS 223, 2014 WL 785167 (uscfc 2014).

Opinion

OPINION AND ORDER

SWEENEY, Judge

Plaintiff K-Con Building Systems, Inc. filed three suits in this court concerning its contracts with the United States Coast Guard (“Coast Guard”) for the design and construction of prefabricated metal buildings in Elizabeth City, North Carolina, St. Peters-burg, Florida, and Port Huron, Michigan. After the court issued summary judgment rulings in each case and held trial in this case, the parties engaged in settlement discussions. Those discussions revealed several issues that required resolution prior to any settlement. Accordingly, the parties have filed the relevant motions in all three eases.

In this ease, which concerns the building in Elizabeth City, plaintiff seeks to invalidate the Coast Guard’s termination of its contract for default. Plaintiff also seeks to amend its complaint to allege an affirmative claim for an equitable adjustment. For the reasons set forth below, the court invalidates the Coast Guard’s default termination, dismisses those claims premised on the default termination for lack of jurisdiction, concludes that it possesses jurisdiction to entertain both parties’ liquidated damages claims, and grants plaintiffs motion to amend its complaint.

I. BACKGROUND

In April 2001, the United States General Services Administration (“GSA”) awarded plaintiff a Federal Supply Schedule contract for Prefabricated Structures and Outdoor Smoking Shelters. 1 Subsequently, in September 2003, the Coast Guard solicited proposals for the design and construction of a prefabricated building to house a component repair shop at the Coast Guard Support Center in Elizabeth City. Plaintiff responded to the solicitation and, on September 23, 2003, the Coast Guard placed an order under plaintiffs GSA contract for the solicited building. The initial value of the order was $513,520 and the initial completion date was June 17, 2004.

*725 A. Contract Performance

As set forth in the contract, the Coast Guard contemplated that plaintiff would design the building based on the contract specifications, submit the design to the Coast Guard in two phases (a “100% design” and a “final design”), and then, upon the Coast Guard’s approval of the final design, begin construction. The design and construction of the building were to be completed no more than 262 days after contract award.

One aspect of the work to be performed by plaintiff was the design and installation of heating, ventilation, and air conditioning (“HVAC”) systems “to accommodate all building operations.” Among the HVAC work required was the provision of air conditioning in the building’s test labs, including a room to house existing, identified hydraulic test equipment (“hydraulic test lab”). In addition, plaintiff was required to disconnect an existing chiller from hydraulic test equipment situated in another building, relocate the chiller and the equipment to the new building, reconnect the chiller to the equipment, and run new distribution piping.

Work on the project did not begin within the time anticipated in the contract. The Coast Guard postponed the postaward kickoff meeting, which should have occurred between fourteen and twenty-eight days after contract award, to December 4, 2003. In addition, plaintiff encountered delays in the delivery of the building due to worldwide steel shortages. Plaintiff also required additional time in which to coordinate the connection of government-owned equipment, some of which was different from the equipment listed in the contract specifications. Plaintiff asserted that this latter problem delayed its mechanical and electrical designs. In an April 15, 2004 bilateral contract modification, the contract completion date was extended by 126 days to October 21, 2004.

On May 6, 2004, one of the contracting officers involved with the contract, 2 Marion E. Hundley, sent plaintiff a cure letter warning that plaintiffs “failure to submit a proper progress schedule and failure to perform any work on site was endangering the performance of [the] contract.” Plaintiff responded to the cure letter on May 16, 2004, describing its progress in various aspects of the project. It explained that it was “refining [its] construction schedule with supplies and subcontractors and would submit the schedule on May 20, 2004.” It further indicated that it had “completed the layout of the building” and was “coordinating” with the Coast Guard regarding the “the location of existing utilities.” In addition, plaintiff asserted that it “planned to start site work and installation of the building pad on May 18, 2004,” and that, “once the foundation design was revised and approved,” it was prepared to install the foundation. Finally, it stated that it was “inspecting the existing equipment to be relocated ... and ... holding on site discussions with the base personnel to evaluate the impact of the planned move.”

One month later, in a June 18, 2004 letter, Ms. Hundley advised plaintiff that its “mechanical design submittal had significant comments that had to be addressed prior to a re-submittal of the document.” Despite this design issue, the Coast Guard permitted plaintiff to proceed with construction after accepting plaintiffs structural foundation drawings on July 6, 2004. Plaintiff began to erect the building’s steel structure on July 30, 2004.

At around the same time, plaintiff sent its 100% design package to the Coast Guard. On July 23, 2004, a second contracting officer, Victoria W. Worrell, forwarded the Coast Guard’s comments on the package to plaintiff. She indicated that once plaintiff had incorporated the Coast Guard’s comments and submitted its final design, it could “proceed with all work other than that related to the HVAC system,” and that once the design requirements of the HVAC system were resolved, the mechanical drawings could be incorporated into the final design.

More than one month later, the parties agreed to a contract modification, effective September 9, 2004, increasing the contract price to $551,155.35 to compensate plaintiff for its installation of sound attenuation blan *726 kets above three of the rooms in the building. But, as of September 10, 2004, the issues with the hydraulic test lab’s HVAC system had not been resolved.

On September 20, 2004, plaintiff sent a progress schedule to the Coast Guard indicating a completion date of December 8, 2004, forty-three days beyond the then-contract completion date of October 26, 2004. Ms. Hundley noted the discrepancy in a September 22, 2004 forbearance letter. Subsequently, in a November 10, 2004 bilateral contract modification, the completion date was extended, for the final time, to November 9, 2004, due to a supplier’s shipping delay. Given that plaintiff had previously anticipated completing the building on December 8, 2004, it remained unable to meet the contract completion date. Nevertheless, despite noting plaintiffs “failure to make progress and ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
114 Fed. Cl. 722, 2014 U.S. Claims LEXIS 223, 2014 WL 785167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-con-building-systems-inc-v-united-states-uscfc-2014.