James M. Ellett Construction Company, Inc. v. United States

93 F.3d 1537, 41 Cont. Cas. Fed. 76,997, 1996 U.S. App. LEXIS 21938, 1996 WL 479523
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 26, 1996
Docket94-5161
StatusPublished
Cited by235 cases

This text of 93 F.3d 1537 (James M. Ellett Construction Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
James M. Ellett Construction Company, Inc. v. United States, 93 F.3d 1537, 41 Cont. Cas. Fed. 76,997, 1996 U.S. App. LEXIS 21938, 1996 WL 479523 (Fed. Cir. 1996).

Opinion

MAYER, Circuit Judge.

James M. Ellett Construction Company, Inc. appeals the judgment of the United States Court of Federal Claims, No. 90-641 C (July 29,1994), dismissing its suit challenging a contracting officer’s final decision for want of subject matter jurisdiction because Ellett had not submitted a “claim” that complied with the requirements of the Contract Disputes Act. Subsequent to the court’s dismissal, this court clarified the definition of a claim, overruling the cases upon which the trial court had relied in dismissing Ellett’s complaint. Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed.Cir.1995) (in banc). Because Ellett submitted both a “claim” as that term is explained in Reflectone, and a termination settlement proposal that ripened into a claim which the contracting officer settled by determination, there was jurisdiction. Therefore, we reverse and remand for further proceedings.

*920 Background

In July 1988, the Forest Service of the United States Department of Agriculture (agency) awarded Ellett a contract to construct a 2.7 mile logging road in the Siskiyou National Forest, Oregon. The contract contained the April 1984 version of the Federal Acquisition Regulation (FAR) clause authorizing the government to terminate the contract for its convenience, 48 C.F.R. § 52.249-2 (Alternate I), which states, in pertinent part:

(d) After termination, the Contractor shall submit a final termination settlement proposal to the Contracting Officer in the form and with the certification prescribed by the Contracting Officer____
(e) Subject to paragraph (d) above, the Contractor and the Contracting Officer may agree upon the whole or any part of the amount to be paid because of the termination. ...
(f) If the Contractor and the Contracting Officer fail to agree on the whole amount to be paid the Contractor because of the termination of work, the Contracting Officer shall pay the Contractor the amounts determined as follows, but without duplication of any amounts agreed upon under paragraph (e)____
(i) The Contractor shall have the right of appeal, under the Disputes clause, from any determination made by the Contracting Officer under paragraph (d) [or]
(f)____If the Contracting Officer has made a determination of the amount due under paragraph (d) [or] (f) ..., the Government shall pay the Contractor (1) the amount determined by the Contracting Officer ... if no timely appeal has been taken, or (2) the amount finally determined on appeal.

On July 28, 1988, the agency issued Ellett a partial notice to proceed, which authorized the construction of just 4,000 feet of the road, because of pending legislation to limit entry into the area. The agency then terminated the remainder of the contract for convenience on September 30,1988.

By letter dated November 17, 1988, the stated purpose of which was “to file formal notice of claim pursuant to the Contract Disputes Act of 1978 [ (CDA) ],” Ellett sought to recover $545,157.19 from the agency. Specifically, the company claimed: (1) a $136,964.81 equitable adjustment for government-ordered changes; (2) $32,036.50 for “unforeseen and unexpected security costs” that were “not disclosed in the prospectus”; and (3) $376,155.88 in lost profits. Although not submitted on the forms the FAR requires for settlement proposals, see 48 C.F.R. § 49.206-1(e) (1995) (“Settlement proposals must be on the forms prescribed in 49.602____”), Ellett says this letter, like a termination settlement proposal, was intended to recover all money due under the contract. The contracting officer responded by letter of December 2, 1988, that FAR Part 49 governs “the settlement of termination proposals and requests for contract modification.” The letter said Ellett needed to submit a settlement proposal on Standard Forms (SF) 1436 (Settlement Proposal (Total Cost Basis)) and 1439 (Schedule of Accounting Information), which were enclosed.

On March 3, 1989, Ellett submitted a settlement proposal on the required forms, requesting a net payment of $494,826. It admits that the amount sought in this request was largely duplicative of its November 17, 1988 submission, although different in some respects because of the requirements of the forms and unspecified intervening events. The parties then began to negotiate a mutually agreeable settlement.

In a January 12, 1990 letter to the contracting officer, Ellett observed that it had been “nearly 14 months” since the November 17,1988 CDA “claim” and one year since the settlement proposal. Consequently, it said that unless the “outstanding claim” were resolved satisfactorily within thirty days, it would file suit in the United States Court of Federal Claims. 1 The agency responded with a settlement offer of $120,649, which Ellett rejected in a March 31, 1990 letter, *921 which also said that unless the agency agreed to a settlement of $250,000 within two weeks, it would file suit.

The government rejected the $250,000 settlement offer, and the contracting officer prepared a document styled “Contracting Officer’s Findings and Determination,” dated June 25, 1990. There he evaluated the termination settlement proposal and concluded that Ellett was entitled to termination costs of $416,144.01, less progress payments the agency had already made, for a net of $22,-779.01.

On July 13,1990, Ellett filed a complaint in the Court of Federal Claims, seeking $451,-084 plus interest, costs, and attorneys fees. The government moved to dismiss for lack of subject matter jurisdiction because the November 17, 1988 letter did not qualify as a valid claim under the CDA, and even if it were a valid claim, it was not properly certified. The court agreed that the letter was not properly certified and dismissed the suit. James M. Ellett Constr. Co. v. United States, No. 90-641 C (Cl.Ct. Feb. 6, 1991). We reversed. James M. Ellett Constr. Co. v. United States, No. 91-5071, 1992 WL 82447 (Fed.Cir. Apr. 24, 1992).

On remand, the government renewed its motion to dismiss, arguing that Ellett had not yet submitted a claim to the contracting officer for purposes of the CDA. In granting the motion, the court said Ellett had to establish that “(1) [it] asserted in writing and with sufficient specificity a right to additional compensation, (2) the government disputed that right, and (3) [it] communicated [its] desire for a contracting officer decision.” Slip op. at 10 (citing Heyl & Patterson, Inc. v. O’Keefe, 986 F.2d 480 (Fed.Cir.1993); Transamerica Ins. Corp. v. United States, 973 F.2d 1572 (Fed.Cir.1992)). It also relied on

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platinum Services, Inc.
Armed Services Board of Contract Appeals, 2024
LR General Solutions, LLC
Armed Services Board of Contract Appeals, 2023
Mountain Movers/Ainsworth-Benning, LLC
Armed Services Board of Contract Appeals, 2020
Parsons Government Services, Inc.
Armed Services Board of Contract Appeals, 2020
Ford Lumber & Building Supply, Inc.
Armed Services Board of Contract Appeals, 2019
Asi Constructors, Inc. v. United States
129 Fed. Cl. 707 (Federal Claims, 2016)
Zafer Taahhut Insaat Ve Ticaret, A.S. v. United States
129 Fed. Cl. 454 (Federal Claims, 2016)
Bruhn Newtech, Inc. v. United States
129 Fed. Cl. 656 (Federal Claims, 2016)
Boarhog LLC v. United States
129 Fed. Cl. 130 (Federal Claims, 2016)
Refaei v. United States
129 Fed. Cl. 1 (Federal Claims, 2016)
Claude Mayo Construction Company, Inc. v. United States
128 Fed. Cl. 616 (Federal Claims, 2016)
Federal Contracting, Inc. v. United States
128 Fed. Cl. 788 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
93 F.3d 1537, 41 Cont. Cas. Fed. 76,997, 1996 U.S. App. LEXIS 21938, 1996 WL 479523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/james-m-ellett-construction-company-inc-v-united-states-cafc-1996.