Dawco Construction, Inc. v. The United States

930 F.2d 872, 37 Cont. Cas. Fed. 76,056, 1991 U.S. App. LEXIS 5359, 1991 WL 44865
CourtCourt of Appeals for the Federal Circuit
DecidedApril 3, 1991
Docket90-5074
StatusPublished
Cited by149 cases

This text of 930 F.2d 872 (Dawco Construction, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dawco Construction, Inc. v. The United States, 930 F.2d 872, 37 Cont. Cas. Fed. 76,056, 1991 U.S. App. LEXIS 5359, 1991 WL 44865 (Fed. Cir. 1991).

Opinion

MICHEL, Circuit Judge.

The United States appeals the judgment of the United States Claims Court awarding Dawco Construction, Inc. (“Dawco”) $529,935, plus interest, as an equitable adjustment for differing site conditions encountered in performance of the landscape portion of a housing refurbishment contract. Dawco Construction, Inc. v. United States, No. 450-86C (Cl.Ct. Nov. 17 & 22, 1989, 18 Cl.Ct. 682 and Feb. 5, 1990). Defendant-appellant also appeals the Claims Court ruling that it had jurisdiction to entertain the contractor’s claim, contending that Dawco did not “submit” a claim to the contracting officer, as required under the Contract Disputes Act. 41 U.S.C. § 605 (1988).

Although the Claims Court correctly ruled that it could hear Dawco’s claim, it erroneously adopted the “jury verdict method” to measure the quantum of damages due the contractor. Accordingly, we affirm-in-part, upholding its ruling on jurisdiction, reverse-in-part, overturning the judgment awarding damages, and remand for a proper determination of damages.

BACKGROUND

A. The Contract Dispute

Dawco was awarded a contract to refurbish the Cabrillo-Larksdale Naval housing project near San Diego, California, in August 1983. As part of the contract, Dawco was also required to landscape the grounds around six individual housing areas, a total of 903,000 square feet. Dawco, in turn, subcontracted this portion of the work to J.C. Landscape (“JCL”) for $460,000.

After the contract award, the Navy determined that the grading required by the contract specifications would not produce acceptable drainage and in a September 26, 1983 letter, directed Dawco to suspend all landscaping work until further notice and to continue only refurbishing the buildings. The Navy then developed a new drainage plan calling for installation of an underground drainage system in four of the six areas. The drainage system redesign was detailed in a Change Order Request, and was accompanied by a request for a cost proposal. The Navy, however, rejected Dawco’s proposed costs, presented in a May 21, 1984 letter from JCL to the Navy, and decided instead to landscape only the two of the six areas that did not need underground drainage lines.

On May 29, 1984, the Navy formally issued a change to the contract, designated “PCO 20,” “[d]elet[ing] entirely” all landscaping work on four areas and directing Dawco to complete, in accord with the original contract specifications, the landscaping site work on the other two areas. In addition, the two areas were enlarged by 35,900 square feet. The change resulted in a net reduction of 397,540 square feet, or at least 44 percent, of the original 903,000 square foot area to be landscaped.

After resuming the landscaping work over the two areas, JCL encountered the differing site conditions that are the subject of this appeal. JCL contended that the areas were not maintained during the eight-month suspension in work, causing *875 the site to “deteriorare] significantly.” Dawco Construction, Inc. v. United States, 18 Cl.Ct. 682, 685 (1989). The resulting new conditions consisted primarily of overgrowth and other obstructions on or within the topsoil, characterized by the Claims Court as “unexpected massive rambling dispersed subsurface running tree roots, rock, boulders, cobble, abandoned water lines not shown on the drawings, weed root masses, demolition debris, galvanized copper piping, asphalt, [and] concrete.” Id. at 695-96.

On October 9, 1985, Dawco’s counsel sent a letter to Richard G. Thurman, the Navy “contracts manager” and the representative of the Resident Officer In Charge of Construction (“Resident Officer”), explaining that Dawco “would like to start settlement discussions as soon as possible” concerning additional costs arising from the differing site conditions. Jt.App. at 110. Although there may have been an earlier undated proposal in the same amount, on November 22, 1985, the Navy received a proposal from Dawco seeking $825,063 as an equitable adjustment. According to Thurman’s letter of November 15, 1985, Dawco had, up to that time, “made no presentation” concerning Daw-co’s costs as the prime contractor, only JCL’s as subcontractor, on the landscaping work. Jt.App. at 111. Thurman stressed that the Navy “must have your [complete] proposal in hand in order to obtain funding and proceed to negotiation.” Id. The November 22 proposal, however, was, according to Thurman, also limited to JCL’s proposed costs.

Two months later, on January 9, 1986, Dawco’s counsel outlined the history of its “claim” and “requested] a Contracting Officers [sic] Final Decision on [its] claim of $325,063.00, which was submitted to the Government on or about November 15, 1985.” Jt.App. at 115. Attached to the letter was a certification signed by Dawco’s president, James H. Benson, and a list of apparently estimated costs.

On February 27, 1986, however, Thurman sent Dawco a letter stating that the Resident Officer was:

unwilling and procedurally unable to negotiate a settlement of the PCO #20 landscape issue for any additive amount.
We will forward the issue for a contracting officer’s final decision as soon as possible. Unless you submit a new proposal, we will forward your undated proposal for $325,063.... Please submit a certification in accordance with the “Disputes” clause of the contract’s General Provisions.

Cl.Ct.Trial Exhibit No. 234 (emphasis added).

On April 9, 1986, Thurman wrote Dawco and acknowledged receipt of an April 2, 1986 letter from Dawco. 1 In this letter, Thurman recited the Navy’s reasons for construing Dawco’s earlier letters as not constituting proper submission of a certified claim. According to Thurman, Daw-co’s assertion that it submitted a claim in May 1984 was “not possible” because the Navy did not direct Dawco to proceed on the contract before May 29, 1984 — the date the PCO was issued. In addition, the May 1985 letter, Thurman explained, was insufficient because it consisted only of . JCL’s proposal and did not include “a listing of [Dawco’s] own costs and credits.” Jt.App. at 121. Since only the April 2, 1986 letter was sufficient, according to the Navy, to constitute a proper claim, Thurman wrote that the 60-day claim resolution requirement of the Contract Disputes Act was triggered by receipt of the April 2, 1986 letter.

Nevertheless, because of Dawco’s failure to “identify the difference between the cost to perform the landscape work as contracted for and the cost to perform the work with the deletions and differing site conditions,” the contracting officer declined to issue a decision on the equitable adjustment due Dawco. Govt.Br. at 10.

On July 21, 1986, well after the 60-day period for decision had expired, Dawco *876 filed suit in the Claims Court seeking an additional $591,678 for the landscape portion of the contract.

B. Claims Court Proceedings

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D2 Government Solutions
Armed Services Board of Contract Appeals, 2024
Goodloe Marine, Inc.
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
M. Nicolas Enterprises, Llc.
Federal Claims, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Kellogg Brown & Root Services v. Secretary of the Army
973 F.3d 1366 (Federal Circuit, 2020)
Supreme Foodservice GmbH
Armed Services Board of Contract Appeals, 2020
Rustler Construction, Inc. v. District of Columbia
211 A.3d 187 (District of Columbia Court of Appeals, 2019)
American Boys Construction Company
Armed Services Board of Contract Appeals, 2017
Semco, LLC v. Grand Ltd.
221 So. 3d 1004 (Louisiana Court of Appeal, 2017)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Vistas Construction of Illinois, Inc.
Armed Services Board of Contract Appeals, 2016
BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
Dobyns v. United States
118 Fed. Cl. 289 (Federal Claims, 2014)
Delaware Cornerstone Builders, Inc. v. United States
117 Fed. Cl. 539 (Federal Claims, 2014)
weston/bean Joint Venture v. United States
115 Fed. Cl. 215 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
930 F.2d 872, 37 Cont. Cas. Fed. 76,056, 1991 U.S. App. LEXIS 5359, 1991 WL 44865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dawco-construction-inc-v-the-united-states-cafc-1991.