Lockheed Martin Aeronautics Company

CourtArmed Services Board of Contract Appeals
DecidedApril 13, 2022
DocketASBCA No. 62209
StatusPublished

This text of Lockheed Martin Aeronautics Company (Lockheed Martin Aeronautics Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lockheed Martin Aeronautics Company, (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Lockheed Martin Aeronautics Company ) ASBCA No. 62209 ) Under Contract No. FA8625-07-C-6471 )

APPEARANCES FOR THE APPELLANT: Stephen J. McBrady, Esq. J. Chris Haile, Esq. Skye Mathieson, Esq. Michelle D. Coleman, Esq. John Nakoneczny, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Deputy Chief Trial Attorney Caryl A. Potter, Esq. Lawrence M. Anderson, Esq. Kyle E. Gilbertson, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PAGE ON THE PARTIES’ CROSS-MOTIONS FOR SUMMARY JUDGMENT

This appeal, made under the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109 (CDA), arose from the $143,529,290 claim brought by Lockheed Martin Aeronautics Company (Lockheed Martin, LMA, LM, appellant, or contractor) against the Air Force (Air Force, USAF, government, or respondent). The underlying contract required the contractor to provide a set of upgrades to certain C-5 Galaxy aircraft. Appellant seeks to recover for costs associated with allegedly excessive “over and above” (O&A) work for particular airplanes and cumulative impacts based upon the “measured mile” legal theory. This decision addresses the government’s motion for summary judgment (gov’t mot.) and appellant’s six cross-motions for summary judgment, 1 which focus upon whether LMA’s October 15, 2018 claim was timely. We grant appellant’s 2nd and 3rd cross-motions, 2 but emphasize that we do not reach the merits of its claim.

1 Lockheed Martin’s first through sixth cross-motions are identified as its 1st cross-motion, 2nd cross-motion, etc. 2 The Board previously granted appellant’s motion for partial summary judgment and struck the government’s affirmative defense of laches; see Lockheed Martin Aeronautics Co., ASBCA No. 62209, 21-1 BCA ¶ 37,886. The Board on STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The Contract

1. On April 30, 2007, the Air Force awarded Contract No. FA8625-07-C-6471, the “Reliability Enhancement and ReEngining Program” (RERP) to Lockheed Martin (R4 3, tab 3). The contractor was required to provide a set of upgrades to each of 49 government-owned C-5 Galaxy aircraft. This included the installation of new CF6-80C2 commercial engines and other enhancements to subsystems and major components; the work was done under mostly fixed-price contract line items (CLINs). (Id. at 3-13) The C-5 Galaxy is the largest military transport aircraft in the United States government’s fleet (complaint ¶ 10).

2. The 49 RERP aircraft to be reworked were informally designated by the parties as P-1 through P-49 (Joint Stipulation of Fact (JSF) 1). 4 These aircraft were grouped into seven lots comprised of varying numbers of planes for the RERP work. The 21 aircraft at issue in this appeal are aircraft P-7 through P-27; these were part of Lots 3, 4, and 5. (R4, tab 2 at 3 n.1; JSF 2)

3. The total amount of the contract was “NTE [not to exceed] $23,000,000” (R4, tab 3 at 2). The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002) – ALTERNATE I (DEC 1991) (id. at 35). It also contained FAR 52.243-01, CHANGES – FIXED-PRICE (AUG 1987), which applied “to Firm-Fixed-Price CLIN(s), Fixed-Price Incentive (Firm Target) CLIN(s) only” as well as FAR 52.243-03, CHANGES – TIME-AND- MATERIALS OR LABOR-HOURS (SEP 2000), which applied “to Time-and- Materials [T&M] CLIN(s) only” (id. at 36).

October 26, 2021 granted appellant’s third motion to compel; see Lockheed Martin Aeronautics Co., ASBCA No. 62209, 21-1 BCA ¶ 37,891. Although the Board finds adequate evidence in the existing record to decide the instant motions, the latter decision should facilitate a more amicable resolution of the parties’ discovery disagreements. 3 References to “R4” indicate submissions included in the government’s Rule 4 file. Those to “app. supp. R4” designate those documents furnished by the appellant. 4 The JSF were proposed findings presented in the government’s motion for summary judgment (see gov’t mot. at 1-8). In its opposition and cross-motions for summary judgment (app. opp’n and mot.), Lockheed Martin stated that, for purposes of its 1st-cross-motion, it “accepts as true and adopts the factual (non-legal) assertions in [the] Air Force[’s] ‘Undisputed Material Facts’” at “¶¶ 1-3, 5-6, and 8-20, as set forth” in the government’s motion (id. at 11). We treat these agreed-upon proposed findings as joint stipulations of fact, identify the JSF by the paragraph number used in the government’s motion, and adopt these JSF as our findings to the extent we determined these are supported by the record. 2 4. The contract included the full text of clause B036 CONTRACT TYPE:

TIME-AND-MATERIALS (FEB 1997) (TAILORED):

(a) The Contractor shall furnish at the hourly rates stated below, all necessary and qualified personnel, managing and directing the same to complete all T&M CLINS within the performance period specified in Section F. In performance of these CLIN(s), Contractor shall be reimbursed for direct labor (exclusive of any work performed in an unpaid overtime status) at the hourly rates listed in Section J as an attachment.

CATEGORIES HOURLY RATE

Rates will be established each year and incorporated into the contract as an attachment.

(b) For the purposes of the clause of this contract entitled “Payments Under Time-and-Material and Labor-Hour Contracts,” the total ceiling price of the CLIN(s) specified in paragraph (a) above is $0.00. Applies to [T&M] CLIN(s) only.

(R4, tab 3 at 14)

5. Contract clause FAR 52.243-07, NOTIFICATION OF CHANGES (APR 1984) provided in ¶ (b) that the “Number of calendar days is (insert 30 for RDSS/C) ‘30 days.’” Although the contract incorporated this clause by reference, when this paragraph is read in full with the insertion, it provides in relevant part:

(b) Notice. The primary purpose of this clause is to obtain prompt reporting of Government conduct that the Contractor considers to constitute a change to this contract. Except for changes identified as such in writing and signed by the Contracting Officer [CO], the Contractor shall notify the Administrative Contracting Officer [ACO] in writing promptly, within [30] calendar days from the date that the Contractor identifies any Government conduct (including actions, inactions, and written or oral communications) that the Contractor regards as a change to the contract terms and conditions.

(R4, tab 3 at 36)

3 6. Contract Modification No. P00178, which has an effective date of November 6, 2012, did not increase the contract price (R4, tab 7 at 1). The modification contained the following release of claims by the contractor:

3. This Supplemental Agreement constitutes a full and equitable adjustment between the Government and the Contractor arising out of or in connection with all C-5 RERP Production Schedule impacts, including the pylon sheer plate, improperly manufactured tower fitting, LM Aero manufacturing manning needs, etc., to the date of this Supplemental Agreement execution except for the issues associated with the Bucket Engineering Change Proposal (ECP) 12-00012A, that LM Aero is preparing. The “Bucket ECP” will address the cost impact of those issues; however the Contractor will not seek any further adjustments to the C-5 RERP Production Schedule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kremer v. Chemical Construction Corp.
456 U.S. 461 (Supreme Court, 1982)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Ricci v. DeStefano
557 U.S. 557 (Supreme Court, 2009)
United States v. Tohono O’odham Nation
131 S. Ct. 1723 (Supreme Court, 2011)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Jewell M. Hart v. The United States
910 F.2d 815 (Federal Circuit, 1990)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Holmes v. United States
657 F.3d 1303 (Federal Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Lockheed Martin Aeronautics Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lockheed-martin-aeronautics-company-asbca-2022.