Lockheed Martin Aeronautics Company

Armed Services Board of Contract Appeals·Decided August 3, 2022·No. ASBCA No. 62209·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Lockheed Martin Aeronautics Company ) ASBCA No. 62209 ) Under Contract No. FA8625-07-C-6471 )

APPEARANCES FOR THE APPELLANT: Stephen J. McBrady, Esq. J. Chris Haile, Esq. Skye Mathieson, Esq. Michelle D. Coleman, Esq. John Nakoneczny, Esq. Crowell & Moring LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Deputy Chief Trial Attorney Caryl A. Potter, III, Esq. Lawrence M. Anderson, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PAGE ON THE PARTIES’ SECOND SET OF CROSS-MOTIONS FOR SUMMARY JUDGMENT

This appeal is made pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101-7109 (CDA). It arises from the $143,529,290 claim brought by Lockheed Martin Aeronautics Company (Lockheed Martin, LMA, LM, appellant, or contractor) against the Air Force (Air Force, USAF, government, or respondent). The underlying contract required LMA to upgrade 49 government-owned C-5 Galaxy aircraft. Appellant seeks to recover for costs associated with allegedly excessive “over and above” (O&A) repairs for particular airplanes and cumulative impacts; it relies upon the “measured mile” legal theory to prove its claim. Lockheed Martin previously was compensated for direct costs of this work, which was required by the government’s issuance of “manufacturing deficiency reports” (MDRs 1). This decision addresses the parties’ second set of cross-motions for summary judgment. 2 We do not reach the

1 According to appellant, the “parties have also referred to MDRs as ‘Material Deficiency Reports’” (app. mot. & opp’n at 10 n.2). 2 Where relevant, we reference the Board’s decision on the parties’ first set of seven cross-motions for summary judgment dated April 13, 2022. The Board there granted only appellant’s second and third cross-motions and (inter alia) found that Lockheed Martin’s claim was timely made. Also, where relevant, we adopt merits of Lockheed Martin’s claim but grant appellant’s motions and deny the government’s. 3

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The Contract

1. On April 30, 2007, the Air Force awarded Contract No. FA8625-07-C-6471, the “Reliability Enhancement and ReEngining Program” (RERP) to Lockheed Martin (R4, tab 3) as an undefinitized action (complaint (compl.) ¶ 15). The contractor was required to provide a set of upgrades to each of 49 government-owned C-5 Galaxy aircraft. This included the installation of new CF6-80C2 commercial engines and other enhancements to subsystems and major components; the work was done under mostly fixed-price contract line items (CLINs). (R4, tab 3 at 3-13) “The C-5 Galaxy is the largest military transport aircraft in the United States [g]overnment’s fleet” (compl. ¶ 10).

2. The 49 RERP aircraft to be reworked were informally designated by the parties as P-1 through P-49. LMA, 22-1 BCA ¶ 38,112 at 185,114 (citing JSF 1). These aircraft were grouped into seven lots comprised of varying numbers of planes for the RERP work. The 21 aircraft at issue in this appeal are aircrafts P-7 through P-27; these were part of Lots 3, 4, and 5. Id. (citing JSF 2).

portions of the Statement of Facts (SOF) from that ruling; these include the parties’ joint stipulations of fact (JSF) that were accepted by the Board. See Lockheed Martin Aeronautics Co., ASBCA No. 62209, 22-1 BCA ¶ 38,112 at 185,114; for ease of reference, we cite this decision hereafter as LMA, 22- 1 BCA ¶ 38,112. 3 We refer collectively to the government’s second set of motions for summary judgment as “gov’t mot.” References to “Appellant’s Cross-Motions for Summary Judgment Regarding the Government’s Affirmative Defense of Release, and Response in Opposition to the Government’s Motions for Summary Regarding Release, Entitlement, and Count III” are to “app. mot. & opp’n.” We similarly cite “Respondent’s Reply (Corrected) In Support of Its Second [Set of] Motion[s] for Summary Judgment and Opposition to Appellant’s Cross-Motions” as “gov’t reply & opp’n,” and “Respondent’s Sur-Reply in Support of Its Second [Set of] Motion[s] for Summary Judgment” as “gov’t surreply.” In like fashion, “Appellant’s Reply in Support of Its Cross-Motions for Summary Judgment Regarding the Government’s Affirmative Defense of Release” and “Appellant’s Sur-reply to the Respondent’s Reply in Support of Respondent’s Motion for Summary Judgment on Entitlement” are respectively referred to as “app. reply” and “app. surreply.”

2 3. The total amount of the contract was “NTE [not to exceed] $23,000,000” (R4, tab 3 at 4). The contract incorporated by reference Federal Acquisition Regulation (FAR) 52.233-1, DISPUTES (JUL 2002) – ALTERNATE I (DEC 1991) (id. at 35). It also contained FAR 52.243-01, CHANGES – FIXED-PRICE (AUG 1987), which applied “to Firm-Fixed-Price CLIN(s), Fixed-Price Incentive (Firm Target) CLIN(s) only” as well as FAR 52.243-03, CHANGES – TIME-AND- MATERIALS OR LABOR-HOURS (SEP 2000), which applied “to Time-and- Materials [T&M] CLIN(s) only” (id. at 36). 4

4. The contract included the full text of clause B036, CONTRACT TYPE: TIME-AND-MATERIALS (FEB 1997) (TAILORED):

(a) The Contractor shall furnish at the hourly rates stated below, all necessary and qualified personnel, managing and directing the same to complete all T&M CLINS within the performance period specified in Section F. In performance of these CLIN(s), Contractor shall be reimbursed for direct labor (exclusive of any work performed in an unpaid overtime status) at the hourly rates listed in Section J as an attachment.

CATEGORIES HOURLY RATE

Rates will be established each year and incorporated into the contract as an attachment.

(b) For the purposes of the clause of this contract entitled “Payments Under Time-and-Material and Labor-Hour Contracts,” the total ceiling price of the CLIN(s) specified in paragraph (a) above is $0.00. Applies to [T&M] CLINS only.

(R4, tab 3 at 14) (emphasis in original)

5. Contract clause FAR 52.243-07, NOTIFICATION OF CHANGES (APR 1984) provided in ¶ (b) that the “Number of calendar days is (insert 30 for RDSC/C) ‘30 days.’” Although the contract incorporated this clause by reference, when this paragraph is read in full with the insertion, it provides in relevant part:

....

4 “CLIN” is an acronym for “Contract Line Item Number.”

3 (b) Notice. The primary purpose of this clause is to obtain prompt reporting of Government conduct that the Contractor considers to constitute a change to this contract. Except for changes identified as such in writing and signed by the Contracting Officer [CO], the Contractor shall notify the Administrative Contracting Officer [ACO] in writing promptly, within 30 days from the date that the Contractor identifies any Government conduct (including actions, inactions, and written or oral communications) that the Contractor regards as a change to the contract terms and conditions . . .

(R4, tab 3 at 36)

6. Contract clause H106, RAPID REPAIR AND RESPONSE (R3) (MAR 2006) provides in relevant part at ¶ 3.f:

f. If an R3 activity(s) causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, the [CO] will make an equitable adjustment in the contract price, the delivery schedule, or both. The Contractor shall assert its right to an adjustment under this paragraph within 90 days from completion of the R3 activity that the Contractor believes causes an increase in cost or schedule. The right to an equitable adjustment shall be the Contractor’s exclusive remedy and the Government shall not be liable to suit for breach of contract for actions accomplished in accordance with the R3 clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Lockheed Martin Aeronautics Company, (asbca 2022).

Lockheed Martin Aeronautics Company (Lockheed Martin Aeronautics Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Ricci v. DeStefano
557 U.S. 557 (Supreme Court, 2009)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Grumman Aerospace Corporation v. Wynne
497 F.3d 1350 (Federal Circuit, 2007)
Smithkline Beecham Corp. v. Apotex [Corrected Date]
439 F.3d 1312 (Federal Circuit, 2006)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Craft MacHine Works, Inc. v. The United States
926 F.2d 1110 (Federal Circuit, 1991)
Dawco Construction, Inc. v. The United States
930 F.2d 872 (Federal Circuit, 1991)