Hol-Gar Manufacturing Corp. v. The United States

351 F.2d 972, 169 Ct. Cl. 384, 1965 U.S. Ct. Cl. LEXIS 57
CourtUnited States Court of Claims
DecidedJanuary 22, 1965
Docket199-60
StatusPublished
Cited by318 cases

This text of 351 F.2d 972 (Hol-Gar Manufacturing Corp. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hol-Gar Manufacturing Corp. v. The United States, 351 F.2d 972, 169 Ct. Cl. 384, 1965 U.S. Ct. Cl. LEXIS 57 (cc 1965).

Opinion

PER CURIAM:

This case was referred pursuant to former Rule 45(a) (now Rule 57(a)) to Trial Commissioner Herbert N. Maletz, with directions to make findings of fact and recommendations for a conclusion of law. The commissioner has done so in an opinion and report filed on July 10, 1963. The plaintiff has excepted to the opinion and certain of the findings of fact. The parties have filed briefs and the case has been argued orally. Since the court agrees with the commissioner’s findings, his opinion and his recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is therefore not entitled to recover and the petition is dismissed.

OPINION OF COMMISSIONER

Plaintiff, a Pennsylvania corporation engaged exclusively in manufacturing generator sets and other equipment for agencies of the Government, was, as low bidder, awarded a contract in March 1958 to supply 5500 portable generator sets to the U. S. Army Corps of Engineers. A supplemental agreement was entered into by the parties in June 1958 increasing the contract by 1,375 units, for a total quantity of 6,875 sets. The unit price of the sets was $1,050; the total contract amount, $7,225,625. Plaintiff sues for the extra cost involved in equipping each generator set with thermostatically operated shutters (a device to control automatically the passage of air from the engine cooling system radiator through the front opening of the generator housing). It claims that such shutters were not required by the specifications but were insisted upon by the defendant’s contracting officer and, therefore, constituted a change in the contract. An administrative appeal by plaintiff to the Armed Services Board of Contract Appeals was unsuccessful.

The specification governing the contract in question was MIL-G-12373, dated December 9, 1952, as amended by Amendment 2, dated August 21, 1957. Item 10 of the amended specification entitled “Housing” read as follows:

Suitable opening for the engine cooling system radiator, with thermostatically operated shutters having auxiliary manual control; substan *974 tial protective grill to protect shutters. 1

Item 22 of the amended specification entitled “Cooling system” read as follows:

Liquid cooling, with pusher-type fan (grille not required) for radiator. Thermostatic control for shutters, with auxiliary manual control. Manually adjustable doors in housing to control air flow. 2

Against this background the principal issue here is whether these provisions, on their face, required plaintiff to equip the generator sets manufactured under the contract with thermostatically operated shutters for the engine cooling system radiator. The dispute, turning as it does on an interpretation of the language of the contract specifications, is a legal question on which the administrative ruling of the contract appeals board is not final as against the plaintiff, nor binding on this court. See 41 U.S.C. § 322; Edwards Eng. Corp. v. United States, 161 Ct.Cl. 322, 328 (1963) and cases cited; Beacon Construction Co. v. United States, 314 F.2d 501, 502, 161 Ct.Cl. 1, 3 (1963) and cases cited; Guyler v. United States, 314 F.2d 506, 509, 161 Ct.Cl. 159, 165 (1963). See also River Construction Co. v. United States, 159 Ct.Cl. 254, 262-266 (1962). 3

At the outset it would appear that the plain language of Item 10 of the specification, as amended, required the inclusion of thermostatically operated shutters on the generator sets, in conjunction with the opening for the engine radiator. For that Item, to repeat, requires:

Suitable opening for the engine cooling system radiator, with thermostatically operated shutters having auxiliary manual control; substantial protective grill to protect shutters.

There is the further consideration that Item 10 of the original specification called for a “Suitable opening with substantial, manually controlled doors for the engine cooling system radiator; grille not required.” There seems no doubt that the Item as so worded imposed a positive requirement for manually controlled doors for the radiator. Merely by comparing the language of the original and amended specification, it seems clear that Amendment 2 modified the original Item 10 so as to require (1) thermostatically operated shutters rather than manually controlled doors for the radiator; (2) an auxiliary manual control for the shutters; and (3) a grille to protect the shutters. 4 It also seems apparent that Item 22 of the amended specifica *975 tion contained a complementary requirement; i. e., “Thermostatic control for shutters, with auxiliary manual control.” Such controls for the shutters were called for by the original specification as well; but since that specification imposed no requirement for the shutters themselves, Government representatives did not insist on installation of the control mechanism since it would be superfluous. But after issuance of Amendment 2 specifying a shutter requirement, this no longer was the case.

Having been furnished the original specification and Amendment 2 as enclosures to the Bid Invitation, and having read Item 10 and the amendment thereto, it is somewhat difficult to perceive how plaintiff, as an experienced Government contractor in the manufacture of generator sets, could have concluded that thermostatically operated shutters were not required. Indeed it is elementary that the language of a contract must be given that meaning that would be derived from the contract by a reasonably intelligent person acquainted with the contemporaneous circumstances. New York Trust Co. v. Island Oil & Transport Corp., 34 F.2d 655, 656 (2d Cir. 1929); Hammond Ford, Inc. v. Ford Motor Co., 204 F.Supp. 772, 773 (S.D.N.Y.1962); 4 Williston, Contracts, § 611 at 553 (3d ed. 1961). 5

Plaintiff insists, however, that Item 10, as amended, imposed no positive requirement for thermostatically operated shutters. It maintains that the comma after the word “radiator” should be disregarded and that if disregarded, the term “with thermostatically operated shutters” modifies the word “radiator”. In short, in plaintiff’s view, Item 10, as amended, requires merely a suitable opening for an engine cooling system radiator having thermostatically operated shutters. To support this contention, plaintiff adverts to the second sentence in Item 22 “Thermostatic control for shutters, with auxiliary manual control” and asserts that the term “with auxiliary manual control” in that sentence modifies the word “shutters” and that the sentence must, therefore, be read as though there were no comma after the word “shutters”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Boland, Inc.
Armed Services Board of Contract Appeals, 2022
Granite Construction Company
Armed Services Board of Contract Appeals, 2020
DynCorp International LLC
Armed Services Board of Contract Appeals, 2019
Yee v. United States
Federal Circuit, 2019
Coppola v. DVA
Federal Circuit, 2019
General Dynamics - National Steel and Shipbuilding Company
Armed Services Board of Contract Appeals, 2019
LKJ Crabbe Inc.
Armed Services Board of Contract Appeals, 2018
CDM Constructors, Inc.
Armed Services Board of Contract Appeals, 2018
Cky Inc. v. United States
Federal Claims, 2018
A.T.I. TACOSE S.C.a R.L.
Armed Services Board of Contract Appeals, 2017
Ferox, LLC v. Conseal International, Inc.
175 F. Supp. 3d 1363 (S.D. Florida, 2016)
weston/bean Joint Venture v. United States
123 Fed. Cl. 341 (Federal Claims, 2015)
LRV Environmental, Inc.
Armed Services Board of Contract Appeals, 2015
Stathis v. United States
120 Fed. Cl. 552 (Federal Claims, 2015)
Allen v. United States
119 Fed. Cl. 461 (Federal Claims, 2015)
Griffin & Griffin Exploration, LLC v. United States
116 Fed. Cl. 163 (Federal Claims, 2014)
Chevron U.S.A., Inc. v. United States
116 Fed. Cl. 202 (Federal Claims, 2014)
Shell Oil Company v. United States
751 F.3d 1282 (Federal Circuit, 2014)
Mata v. United States
114 Fed. Cl. 736 (Federal Claims, 2014)
All Star Technical Services, Inc.
Armed Services Board of Contract Appeals, 2014

Cite This Page — Counsel Stack

Bluebook (online)
351 F.2d 972, 169 Ct. Cl. 384, 1965 U.S. Ct. Cl. LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hol-gar-manufacturing-corp-v-the-united-states-cc-1965.