Cky Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedOctober 12, 2018
Docket16-948
StatusPublished

This text of Cky Inc. v. United States (Cky Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cky Inc. v. United States, (uscfc 2018).

Opinion

United States Court of Federal Claims No. 16-948 C October 12, 2018 __________________________________

CKY INC.,

Plaintiff,

v.

UNITED STATES OF AMERICA,

Defendant. __________________________________

Daniel Lawrence Baxter, Esquire, Wilke, Fleury, et al. Sacramento, CA, for plaintiff.

Douglas Thomas Hoffman, Esquire, United States Department of Justice, Commercial Litigation Branch, Civil Division, Washington, D.C., for defendant.

ORDER AND OPINION

HODGES, Senior Judge.

Plaintiff CKY alleges that it suffered damages during the performance of a contract and seeks recovery of $4,528,676 from the United States. Defendant asserts that CKY’s action is based on an unreasonable interpretation of the contract. The Government has filed a motion for summary judgment, a motion to dismiss count four of the Complaint, and a counterclaim for liquidated damages.

BACKGROUND

The United States through its International Boundary and Water Commission (the “Commission”) awarded a $6,399,900 small business set-aside construction contract to CKY in June of 2012. The Commission applies the boundary and water treaties between the United States and Mexico under the foreign policy guidance of the United States Department of State. The Commission is responsible for flood control in the border region, which involves maintenance on levees.

-1- The purpose of the contract was to widen and “rehabilitate” the top surface of the Urban Presidio Levee in Presidio, Texas by excavating old embankment material and depositing new embankment material. CKY was required to “excavate into the existing levee to create a series of keys and benches as shown in the plans,” then fill the benches with new embankment material.1

The contract required embankment material be tested to ensure that it met the material requirements before it was deposited on the levee. The embankment soil exposed by the excavation had to meet performance specifications, such as moisture content and compaction. After the approved embankment material was broadcast on the levee, it was tested again to ensure that each layer of the levee passed the contract’s performance requirements.

CKY struggled to pass subgrade moisture and density tests, resulting in scheduling delays and requests for extended work hours. CKY alleges that government contracting officers directed the placement of suitable embankment material over “unacceptable, non- constructible subgrade.” This was a modification of the contract, according to CKY, that constitutes an oral and implied-in-fact contract on which it relied “in exchange for compensation from the Commission for completion of said work.”

Plaintiff filed a Complaint in August 2016, seeking more than $4,528,676 in damages. CKY alleges that the contract documents and additional materials incorporated therein misrepresented pertinent site conditions on the project. The actual site conditions on the project were not reasonably foreseeable, CKY contends, and that it incurred additional costs because the subgrade material in a levee that it would develop did not satisfy the embankment material specifications in the contract. The Complaint lists the following causes of action: (1) differing site conditions; (2) defective specifications; (3) constructive change; and (4) breach of an oral and implied-in-fact contract.

The Government filed a motion for summary judgment and a counterclaim in August 2017. After oral arguments, we deferred ruling on defendant’s motions to allow CKY additional discovery.

LEGAL STANDARDS

Summary judgment is appropriate when “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” RCFC 56(a). A responding party may not merely deny that a fact is true or is genuinely disputed, but “must

1 We observe the following explanation of construction terminology: “The rehabilitation of the levee . . . generally involved excavating into the existing levee material by cutting (or “grading,” or “benching”) steps (or “keys,” or “benches”) into the levee.” (ECF No. 22 at 7, ¶ 2.) -2- support the assertion by . . . citing to particular parts of materials in the record, including depositions, documents . . . affidavits or declarations . . . or other materials.” RCFC 56(c)(1). The moving party “always bears the initial responsibility of informing the [court] of the basis for its motion” but the rule does not require “that the party moving for summary judgment to produce evidence showing the absence of a genuine issue of material fact.” Celotex Corp. v. Catrett, 477 U.S. 317, 324-25 (1986). Alternatively, “the burden on the moving party may be discharged by showing . . . that there is an absence of evidence to support the nonmoving party’s case.”

DISCUSSION

The Government’s contentions in support of summary judgment include: (1) a reasonable contractor could not have interpreted the contract in such a way as to expect the subgrade to meet the embankment specification; and (2) plaintiff gave inadequate notice of a differing site condition. The case turns on these two legal issues for which no material fact is in dispute, according to defendant.

The voluminous record of this case does not provide evidence sufficient to support CKY’s claims that the Government is entitled to a judgment as a matter of law for the reasons below.

I. The Government’s Motion for Summary Judgment

The primary issue concerns the suitability of the levee subgrade. The Government asserts that the four counts of plaintiff’s Complaint are based on CKY’s unreasonable interpretation of the contract as it applies to the subgrade specifications, and that each count “rel[ies] on a very specific contract interpretation for the subgrade material as ‘acceptable and constructible’”

A. Reasonable Contract Interpretation

CKY claims that the omission of express subgrade material specifications meant that the subgrade soil was required to comply with all embankment material specifications. We cannot agree.

In general, “a contract is read in accordance with its express terms and the plain meaning thereof.” C. Sanchez and Son, Inc. v. United States, 6 F.3d 1539, 1543 (Fed. Cir. 1993). A court must “interpret the contract in a manner that gives meaning to all of its provisions and makes sense.” Mcabee Const., Inc. v. United States, 97 F.3d 1431, 1435 (1996). There must be “a reasonable meaning to all parts of an instrument,” as opposed to “leav[ing] a portion of it useless, inexplicable, inoperative, void, insignificant, meaningless, or superfluous.” Hol-Gar Mfg. Corp. v. United States, 169 Ct. Cl. 384, 395 (1965).

-3- The Commission addressed embankment material specifications in pre-award communications as follows:

Question: The geotechnical report does not have results for pinhole and crumb test results on existing levee. Will the existing levee meet the contract requirements for embankment? If not, how will this be handled on a day to day basis?

Response: The existing levee was constructed with soil that met ASTM D4647ND1 or ND2 classification. Due to contamination in situ and the Contractor’s excavation processes, [the Commission] cannot state that excavated material will meet these requirements. The Contractor is required to meet the embankment specification regardless of the source of the embankment material.

(“Question 4” of Amendment A003.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wise v. United States
249 U.S. 361 (Supreme Court, 1919)
Hol-Gar Manufacturing Corp. v. The United States
351 F.2d 972 (Court of Claims, 1965)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Dj Manufacturing Corporation v. United States
86 F.3d 1130 (Federal Circuit, 1996)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
Cky Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cky-inc-v-united-states-uscfc-2018.