C. Sanchez and Son, Incorporated v. United States

6 F.3d 1539, 39 Cont. Cas. Fed. 76,578, 1993 U.S. App. LEXIS 25561
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 5, 1993
Docket19-2185
StatusPublished
Cited by183 cases

This text of 6 F.3d 1539 (C. Sanchez and Son, Incorporated v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. Sanchez and Son, Incorporated v. United States, 6 F.3d 1539, 39 Cont. Cas. Fed. 76,578, 1993 U.S. App. LEXIS 25561 (Fed. Cir. 1993).

Opinion

PAULINE NEWMAN, Circuit Judge.

C. Sanchez and Son was awarded a fixed price contract with the United States Army Corps of Engineers in connection with the construction of an artificial battlefield at Fort Hunter Liggett, California. The contract required the installation of several electrical systems including interior wiring, an underground electrical distribution system, a telephone system, a lighting system and a lightning protection system, and included trenching and backfilling of ground in the course of installation of underground wiring. Sanchez subcontracted with I.C.G. Electric, Inc. to perform work on the project. Sanchez, on behalf of I.C.G., seeks equitable adjustments to compensate for certain increased costs.The United States Claims Court granted summary judgment against Sanchez on three claims. 1 We affirm as to two claims and reverse and remand as to one claim.

Summary Judgment

Summary judgment is appropriate when “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” RUSCC 56(c) 2 . The moving party has the burden of showing the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986). In response to a properly supported motion for summary judgment the opposing party “must set forth specific facts showing that there is a genuine issue for trial”. RUSCC 56(f).

The evidence of the nonmoving party is to be believed, and all reasonable factual inferences are to be drawn in its favor. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 2513, 91 L.Ed.2d 202 (1986); Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 1609, 26 L.Ed.2d 142 (1970). A genuine issue of material fact arises when the nonmovant presents sufficient evidence upon which a reasonable fact finder, drawing the requisite inferences and applying the applicable evidentiary standard, could decide the issue in favor of the nonmovant. Anderson, 477 U.S. at 254-55, 106 S.Ct. at 2513-14. The grant of summary judgment is reviewed for correctness, see Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987), the appellate court determining whether the matter was amenable to summary resolution and, if *1542 so, whether the law was correctly applied to the facts.

I

Aluminunu-Sheathed Cable

The contract specified the use of certain steel-sheathed cable for the data transmission line. The Okonite Company, as supplier, experienced delay in acquiring adequate quantities of the specified steel-sheathed cable, and proposed substituting, at no additional cost, aluminum-sheathed cable. Aluminum-sheathed cable is more expensive than steel-sheathed cable, and Sanchez described aluminum-sheathed cable as “superi- or”. The Army rejected the requested substitution, stating that steel was superior in blocking magnetic interference on the data line.

Sanchez states that the Army conducted no investigation and cited no technical authority concerning the interference-blocking properties of aluminum versus steel, and that the Army’s denial of this request without adequate technical review breached the duty to cooperate and not hinder the contractor’s performance. As a result of this denial Sanchez experienced delay in the contract schedule, for which it seeks recompense.

The government must avoid actions that unreasonably cause delay or hindrance to contract performance. Malone v. United States, 849 F.2d 1441, 1445 (Fed.Cir.1988); Lewis-Nicholson, Inc. v. United States, 550 F.2d 26, 32, 213 Ct.Cl. 192 (1977); George A. Fuller Co. v. United States, 69 F.Supp. 409, 108 Ct.Cl. 70, 94 (1947). The Army promptly informed Sanchez of its view that the purpose of the requirement for steel-sheathed cable would not be met by aluminum. The record does not contain facts tending to show that the Army acted arbitrarily or unreasonably, or that aluminum-sheathed cable was known to have the requisite interference-blocking properties of steel-sheathed cable. Indeed Sanchez does not assert that aluminum is as effective as steel in this regard. The only statement of superiority in the record is that aluminum provides a superior hermetic seal, a property not asserted by Sanchez to be related to the property of blocking magnetic interference.

The burden of showing suitability for the intended purpose was upon Sanchez. Sanchez has not presented facts which, if established, would support entitlement to delay damages for the Army’s refusal to accept the substitution of aluminum-sheathed cable. Summary judgment on this claim was correctly entered in favor of the government.

II

The Rollover Protective Structure

I.C.G. planned to use a Vermeer T-600D trenching machine to dig the trenches required by the contract, and the contract was bid accordingly. Not included in the bid was the cost of installing a rollover protective structure (“ROPS”) on the trencher. After contract performance had begun, the Army directed I.C.G. to install a ROPS. I.C.G. objected but complied, and seeks recovery of the costs incurred. See J.B. Williams Co. v. United States, 450 F.2d 1379, 1394, 196 Ct.Cl. 491 (1971) (government directive to proceed beyond contractor’s reasonable interpretation of contract was a constructive change and entitled contractor to an equitable adjustment).

I.C.G. explained that it did not believe a ROPS was required on the Vermeer T-600D trencher, because of the contract terms and because of its past experience using this trencher in government construction projects. I.C.G. referred to the absence of a requirement for a ROPS on trenchers in the Army Corps of Engineers Safety and Health Requirements Manual (“Safety Manual”), which was incorporated by reference into the contract. The Safety Manual does not mention trenchers in its section on requirements for rollover protection structures:

a. ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DLT Solutions, LLC
Armed Services Board of Contract Appeals, 2024
Omran, Inc.
Armed Services Board of Contract Appeals, 2024
ServeFed, Inc.
Armed Services Board of Contract Appeals, 2023
Radmacher Brothers Excavating Co., Inc.
Armed Services Board of Contract Appeals, 2023
Alfajer, Ltd.
Armed Services Board of Contract Appeals, 2023
Sheffield Korte Joint Venture
Armed Services Board of Contract Appeals, 2023
RLB Contracting, Inc.
Armed Services Board of Contract Appeals, 2023
Trident Engineering & Procurement, P.C.
Armed Services Board of Contract Appeals, 2023
U.S. Bank National Association
Armed Services Board of Contract Appeals, 2023
David Boland, Inc.
Armed Services Board of Contract Appeals, 2022
Doe v. United States
Federal Claims, 2021
KF&S Corp.
Armed Services Board of Contract Appeals, 2020
Anis Avasta Construction Company
Armed Services Board of Contract Appeals, 2020
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Chugach Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2020
Macro-Z Technology
Armed Services Board of Contract Appeals, 2019
Cky Inc. v. United States
Federal Claims, 2018

Cite This Page — Counsel Stack

Bluebook (online)
6 F.3d 1539, 39 Cont. Cas. Fed. 76,578, 1993 U.S. App. LEXIS 25561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-sanchez-and-son-incorporated-v-united-states-cafc-1993.