Peter Kiewit Sons' Co. v. United States

109 Ct. Cl. 390, 1947 U.S. Ct. Cl. LEXIS 55, 1947 WL 5089
CourtUnited States Court of Claims
DecidedOctober 6, 1947
DocketNo. 46432
StatusPublished
Cited by102 cases

This text of 109 Ct. Cl. 390 (Peter Kiewit Sons' Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peter Kiewit Sons' Co. v. United States, 109 Ct. Cl. 390, 1947 U.S. Ct. Cl. LEXIS 55, 1947 WL 5089 (cc 1947).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

Plaintiffs sue for an additional amount to which they allege they are entitled for excavation required for the construction of certain work at Fort Crook, Nebraska. Defendant invited bids for the work on May 15,1943, and plaintiffs, Peter Kiewit Sons’ Company, a corporation, and George Condon and Chester W. Cunningham, partners, trading as Condon-Cunningham Company, in answer to defendant’s invitation, submitted bids, but they were not the low bidders. All bids were rejected and plaintiffs were requested to enter into negotiations for a contract with defendant for the performance of the work. They entered into a contract on May 27, 1943, to do all the work specified for the sum of $1,573,672.72. This amount was $74,990.00 less than their bid.

The work to be done included all necessary excavation and grading of the site and the construction of units 4, 5, and 6 of Modification Center No. 8, and of a pump house, a ground storage water tank, a control house, a pedestrian tunnel, and a target butt. The controversy is over the unit price to be paid for the excavation within the building lines and the price to be paid for the erection of the target butt.

1. For the excavation within the building lines down to the bottom of the concrete floor slab defendant has paid plaintiffs at the rate of 22 cents a cubic yard. Plaintiffs claim they are entitled to payment at $1.29 per cubic yard. Defendant admits in its brief that plaintiffs are entitled to $1.29 for the amount of excavation below the elevation of the top of [416]*416the floor slab, but says they are entitled to only 22 cents a cubic yard for the excavation above the elevation of the top of the floor slab.

Article 1 of the contract set out the unit prices at which the specified work was to be done. Item 2 called for “common excavation for buildings and structures (except the pedestrian tunnel) including all excavation for utilities within the building or structure lines, and disposal of surplus materials (except for hangar doors in existing hangar).” Such excavation was to be paid for at $1.29 a cubic yard. Item 24 called for “unclassified excavation.” This was to be paid for at 22 cents a cubic yard.

Defendant claims that the excavation within the building lines and above the top of the floor slab comes within the designation of unclassified excavation, to be paid for at 22 cents a cubic yard, whereas plaintiffs claim that it comes within common excavation for buildings and structures to be paid for at $1.29 a cubic yard.

Plaintiffs claim that the excavation in question is covered by section II of the specifications, whereas defendant claims it is covered by section XXI. Section II is headed, “Excavation, Filling and Backfilling for Buildings and Structures.” Section XXI is headed, “Site Grading, Pipe Culverts, and Observation Tower Removal.”

Defendant says that the excavation in question comes within the definition of “Site Grading” which under section XXI is to be paid for as unclassified excavation, at 22 cents a cubic yard. Section 21-01 says that “The work covered by this section includes the furnishing of all material, equipment and labor required to perform all general excavation, including stripping of topsoil, rough or over-all or over-lot grading, and all borrow and fill, removal of existing drainage structures and lines and removal and relocating an observation tower * * Defendant says that the grading in question was “rough or over-all or over-lot grading.”

Plaintiffs say that “rough or over-all or over-lot grading” has no application to the grading within the building lines, since such grading is covered by section II, which is to be paid for at $1.29 a cubic yard as common excavation.

[417]*417All excavation coming within section II is declared to be common excavation to be paid for at $1.29 a cubic yard. Section 2-03 (e) provides that “All excavation shall be classified as common excavation.” This, of course, means all excavation coming within the scope of section II. The question is, what excavation does come within section II. This is set out, in part, in section 2-01, which provides:

The work covered by this section includes the furnishing of all material and equipment * * * and labor required for the excavation, filling and backfill-ing for the foundations, footings, concrete floors and slabs for buildings and structures, including that required for the installation of piping and conduit within the building lines as shown on the drawings. * * *

A comparison of the provisions of section 2-01 and 21-01, quoted above, leaves in doubt whether or not the grading of the site down to “the foundations, footings, concrete floors and slabs for buildings and structures” is to be paid for as “site grading” or whether all the excavation necessary on the site for the erection of the “foundations, footings, concrete floors and slabs” is to be paid for as common excavation for “buildings and structures.” Defendant says that all the excavation down to the concrete floor slabs is “site grading” and that only the grading below this point comes within the provisions of section II of the specifications. Plaintiffs say that all excavation for buildings and structures is common excavation.

We would be inclined to agree with the defendant, except for the fact that section 2-10, providing for “measurement for payment” provides:

Measurement for payment for excavation will be based on the number of cubic yards excavated within the following limits: Between the original ground surface as determined by a survey made by the Contracting Officer prior to the commencement of excavating operations and the net depths as specified herein or as shown on the drawings.

This provision seems to us to exclude from within “site grading” the excavation to be done within the building lines, because this section 2-10 provides that the excavation to be paid for as common excavation shall be all of that done [418]*418within the building lines which is “between the original ground surface * * * and the net depths as specified herein or as shown on the drawings.” “Original ground surface” can only mean the ground surface before any grading had been done.

Section II must be taken as a limitation on section XXI which covers “rough or over-all or over-lot grading.” Section XXI, taken alone, would seem to cover such grading over all the lot, whether within the building lines or not, but section II says that the excavation for the buildings, to be paid for as common excavation, is to be measured “between the original ground surface” and the “net depths as specified,” which of necessity excludes any previous grading.

When plaintiffs agreed on the price of $1,573,672.72, which was about $75,000 less than their bid, they understood the specifications to mean that they would be paid for all excavation within the building lines at $1.29 a cubic yard. They so testified and we have found this as a fact. We think they were justified in so interpreting the specifications. Where the Government draws specifications which are fairly susceptible of a certain construction and the contractor actually and reasonably so construes them, justice and equity require that that construction be adopted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Optex Systems, Inc.
Armed Services Board of Contract Appeals, 2014
Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
Bell BCI Co. v. United States
81 Fed. Cl. 617 (Federal Claims, 2008)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
Larry D. Barnes, Inc. v. United States
45 F. App'x 907 (Federal Circuit, 2002)
Metcalf Construction Co. v. United States
53 Fed. Cl. 617 (Federal Claims, 2002)
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Telex Communications, Inc. v. United States
42 Cont. Cas. Fed. 77,281 (Federal Claims, 1998)
Conoco Inc. v. United States
35 Fed. Cl. 309 (Federal Claims, 1996)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
PBI Electric Corp. v. United States
35 Cont. Cas. Fed. 75,669 (Court of Claims, 1989)
Sperry Corp. v. United States
33 Cont. Cas. Fed. 74,234 (Court of Claims, 1986)
Raytheon Co. v. United States
31 Cont. Cas. Fed. 71,309 (Court of Claims, 1983)
Solar Turbines International v. United States
31 Cont. Cas. Fed. 71,259 (Court of Claims, 1983)
Folk Construction Co. v. United States
31 Cont. Cas. Fed. 71,247 (Court of Claims, 1983)
Highway Products, Inc. v. United States
530 F.2d 911 (Court of Claims, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
109 Ct. Cl. 390, 1947 U.S. Ct. Cl. LEXIS 55, 1947 WL 5089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peter-kiewit-sons-co-v-united-states-cc-1947.