Universal Shelters of America, Inc. v. United States

87 Fed. Cl. 127, 2009 U.S. Claims LEXIS 115, 2009 WL 1351414
CourtUnited States Court of Federal Claims
DecidedMay 12, 2009
DocketNo. 00-726C
StatusPublished
Cited by6 cases

This text of 87 Fed. Cl. 127 (Universal Shelters of America, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Shelters of America, Inc. v. United States, 87 Fed. Cl. 127, 2009 U.S. Claims LEXIS 115, 2009 WL 1351414 (uscfc 2009).

Opinion

OPINION AND ORDER

WOLSKI, Judge.

This case, brought under the Contract Disputes Act, 41 U.S.C. §§ 601-13 (“CDA”), concerns the United States Navy’s decision to terminate, for cause, a contract for commercial items. Under this contract, plaintiff Universal Shelters of America (“Universal”) was to provide the Navy with four temporary, reusable structures to be placed on the decks of decommissioned ships to shelter dismantlement operations and contain the resulting-debris. Universal was to design the structures to meet contract specifications, including the ability to withstand winds of a certain speed, and to supply the parts and a technical representative to guide the Navy’s assembly and installation of the structures. Each containment unit was to be made up of three separate sections which could, by rolling on rails, retract into the largest section or telescope to full-length. When the first containment was being assembled and installed, overnight winds caused one section, already sitting on the deck of a ship, to tilt to one side, and damaged another section that was on a nearby pier. The Navy, dissatisfied with Universal’s response to a cure notice, terminated the contract for cause, concluding that the design of the containment structures failed to meet the contract specifications. Universal challenges this decision, and the government seeks reprocurement and incidental costs. A trial on these two matters was held, and, as is described in detail below, the Court finds that the termination was [132]*132proper, but that jurisdiction is lacking to award damages to the government at this time.

I. BACKGROUND

A. The Contract

On January 13, 2000, the Navy’s Fleet and Industrial Supply Center issued a priority rated request for quotations, requiring offers to be received in eight days for items to be delivered within seven weeks. Joint Exhibit (“JX”) 1 at 1-2, 5. A contract was awarded to Universal on January 24, 2000, for the purchase of four “rolling telescoping contain-ments” and the assistance of an on-site technical representative to aid Navy personnel in the assembly and installation of the structures. JX 2 at 1, 3-4,12. The containments were for the use of the Puget Sound Naval Shipyard (“PSNS”), located in Bremerton, Washington. Id. at 4, 6, 12. Under the contract, the delivery date for the unassem-bled containments was February 29, 2000, and the technical representative’s services were to be completed on or by March 10, 2000. Id. at 3-4, 6. Universal was to be paid $89,134 for each set of two containments, and $11,200 for the installation assistance, for a total of $189,468. Id.

Two containments were purchased to be initially used on the deck of the former USS Texas and two for initial use on the former USS Virginia, two decommissioned nuclear cruisers which were being dismantled at PSNS. See id. at 4; see also Trial Tr. (“Tr.”) at 103-05. In the contract specifications, the items purchased for each ship were described as “(2) crane liftable rolling telescoping con-tainments.” JX 2 at 12 (¶ 1.1.1). The specifications required:

Each containment shall provide a covered clear space envelope of 53-feet maximum width by a maximum length of 54-feet and a minimum inside height of 17 feet at the center (See Enclosure 1). The containment in part shall roll completely clear of its length and retract to a collapsed depth of not more than 20 feet to allow the opening it covers to be completely accessible to overhead crane operations.

Id. The referenced Enclosure 1 showed that each containment was to consist of three sections. See id. at 21. Other enclosures showed that the minimum inside width of the smallest of the three sections was 45 feet. See id. at 22-23 (Enclosures 2 and 3). The middle section was of unspecified -width, but was necessarily between the 53-feet maximum of the largest section, and the 45-feet minimum of the smallest section. See id. at 22. Each containment was to cover a workspace that was “an opening in the cruiser main deck of 50 feet in length and a width of 44 feet,” JX 2 at 13 (¶ 3.1.1), and was to “eventually be utilized for several different ships in dry dock.” Id. at 12 (¶ 1.1.2); see also id. at 13 (¶ 3.1.1). A foundation providing for a level surface, on which rails were mounted, was to be supplied by PSNS, with enough track for each containment to be rolled completely clear of the workspace, toward the center of the ship’s hull. See id. at 14 (¶ 3.2.1.3.1), 16 (¶ 3.2.4.1.1, ¶¶ 3.2.4.2.1-.2, ¶ 3.2.4.2.3.1), 21. Universal was to provide a “caster/rolling assembly” for use on the tracks, as well as “[tjrack captivation mechanisms” that “prevent wind uplift issues.” Id. at 16 (¶ 3.2.4.1.1).

Each containment was required to have “the roof and sidewalls be enclosed, with the two end walls having openings to allow for travel over installed equipment.” JX 2 at 14 (¶ 3.2.1.3.1). The specifications explained that the dismantling work and ship configuration “require the capability to incrementally retract the sections into each other and then all sections travel clear of the opening in the hull which they are covering.” Id. This relocation of the retracted containment was “to give access to the opening for overhead cranes to access equipment within the opening.” Id. The specifications further explained: “Once the equipment has been serviced the enclosure sections would be expanded back over the opening, providing-weather protection over the hull. The resulting containment shall provide a completely enclosed structure.” Id. The end walls were to have openings, covered with flaps, that when opened had “a minimum opening height of 17 feet at the center,” id. at 15 (Table 1), the same as the “minimum inside height” of the “covered clear space envel[133]*133ope.” See JX 2 at 12 (¶ 1.1.1), 28 (Enclosure 3). A required feature of the containments was the “[f]ull opening of end wall to allow equipment & material access.” Id. at 15 (Table 1).

Among the design requirements was that “[e]ach containment shall be designed and constructed to withstand loading in accordance with the Uniform Building Code (UBC) for the Bremerton Washington region (‘Exposure D’, 83 mph).” Id. at 16 (¶ 3.2.5.1).1 The specification reiterated this wind exposure requirement, which it described as the “level of wind severity,” stating that “[t]he containment and associated foundation shall be designed to meet UBC ‘Exposure D.’ ” Id. at 17 (¶ 3.2.5.1.2). Under the heading of “Rolling contingency,” however, the specification explained: “Full wind load shall be assumed to be applied to the containment when stationary. Contractor shall provide a recommended reduced wind speed which may be used for periods of containment relocation (that is, when containment is rolled to a new position).” Id. (¶ 3.2.5.1.3).

The containment was also required to “be designed to allow crane lift of the individual fully assembled sections which makes up each containment unit.” JX 2 at 13 (¶ 3.1.2.1); see also id. at 18 (¶ 3.8.1.1). The contractor was required to provide the “full rigging procedure” for moving the sections by crane, see id. at 18 (¶ 8.8.3.1), 20 (unnumbered paragraph), including any “applicable limitations” such as “wind conditions or other factors.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newimar, S.A. v. United States
Federal Claims, 2022
Desert Valley Contracting, Inc. Vs. In-Lo Props.
481 P.3d 236 (Nevada Supreme Court, 2021)
Road & Highway Builders, LLC v. United States
102 Fed. Cl. 88 (Federal Claims, 2011)
Northrop Grumman Computing Systems, Inc. v. United States
101 Fed. Cl. 362 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
87 Fed. Cl. 127, 2009 U.S. Claims LEXIS 115, 2009 WL 1351414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-shelters-of-america-inc-v-united-states-uscfc-2009.