Radiation Technology, Inc. v. The United States

366 F.2d 1003, 177 Ct. Cl. 227, 1966 U.S. Ct. Cl. LEXIS 91
CourtUnited States Court of Claims
DecidedOctober 14, 1966
Docket41-64
StatusPublished
Cited by13 cases

This text of 366 F.2d 1003 (Radiation Technology, Inc. v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Radiation Technology, Inc. v. The United States, 366 F.2d 1003, 177 Ct. Cl. 227, 1966 U.S. Ct. Cl. LEXIS 91 (cc 1966).

Opinion

COLLINS, Judge.

The Department of Health, Education, and Welfare agreed, on February 2, 1962, to purchase from plaintiff eight scalertimer-high voltage systems. In April 1962, the Government terminated the con *1004 tract for default. This action is based upon plaintiff’s charge that the termination was wrongful. Defendant has filed a counterclaim for the difference between plaintiff’s contract price and the cost of procuring the equipment from another manufacturer. Both plaintiff and defendant have moved for summary judgment.

The case was referred to Chief Commissioner Marion T. Bennett, who has submitted a report recommending that plaintiff’s motion for summary judgment be denied and defendant’s motion for dismissal of the petition and allowance of the counterclaim be granted. We accept the commissioner’s conclusions as the appropriate outcome in this case.

The facts may be summarized as follows: The contract called for delivery of the eight instruments on April 3, 1962. Four were to be shipped to Rock-ville, Maryland, and the other four to Winchester, Massachusetts. The Public Health Service, which was the contracting agency, planned to use the systems, in conjunction with detectors, to measure the radioactive decay of nuclear particles in the atmosphere.

Plaintiff experienced management and production difficulties and, as a result, found it necessary to seek revision of the delivery schedule. Ultimately, the delivery date was extended to April 12th for Rockville and to April 13th for Winchester. The shipments by plaintiff were made in accord with the revised schedule. Upon arrival at the respective destinations, the instruments were inspected by Government personnel.

At Rockville, William J. Frezel, the author of the contract specifications, sought to ascertain whether plaintiff’s products were in compliance with the requirements of the contract. At Winchester, Edmond Baratta tested the performance of the instruments. Each inspector found the systems which he examined to be defective in a number of respects. On April 19, 1962, the contracting officer, P. H. Shultz, advised plaintiff by telephone of the unsatisfactory nature of the instruments. On April 20th, Mr. Shultz wrote Radiation Technology that, because of its failure “to deliver ScalerTimer-High Voltage Systems in accordance with the specifications * * its right to proceed was terminated. The contracting officer added that plaintiff would be charged with the excess costs of reprocurement. The contracting officer ordered replacements from Picker X-Ray Corporation, and they were shipped within 5 days.

Mr. Shultz wrote Radiation Technology, on May 2d, that his actions had been necessitated by the urgency of the Government’s need for the equipment.

Relying on the disputes clause of the contract, plaintiff appealed to the Secretary of Health, Education, and Welfare. A hearing was held before an ad hoc review board which, on August 15, 1963, recommended denial of the appeal. The board’s decision was adopted by the representative of the Secretary. Subsequently, the present suit was commenced. Plaintiff seeks to recover $13,560, the contract price. The amount of defendant’s counterclaim is $5,553.92.

The basic dispute between the parties relates to the propriety of terminating the contract without granting plaintiff an opportunity to repair the defective systems. This controversy pertains to the default clause which provided in part as follows:

(a) The Government may, * * * by written notice of default to the Contractor, terminate the whole or any part of this contract in any one of the following circumstances:
(i) if the Contractor fails to make delivery of the supplies or to perform the services within the time specified herein or any extension thereof; or
(ii) if the Contractor fails to perform any of the other provisions of this contract, or so fails to make progress as to endanger performance of this contract in accordance with its terms, and in either of these two circumstances does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may *1005 authorize in writing) after receipt of notice from the Contracting Officer specifying such failure.

Defendant asserts that summary termination under (a) (i) was proper contending that the term “delivery” in this subparagraph demands the delivery of conforming goods. This position, it alleges, is in accord with the definition of delivery set forth in both the Uniform Commercial Code and the Uniform Sales Act. Plaintiff concedes that under the authorities cited, delivery is equated with the tender of conforming goods, but argues that, under the contract in issue, the concept of delivery denotes a possessory concept, i. e., the physical transfer of possession. Arguing that use of the word “delivery” should be given a consistent interpretation, plaintiff points to the inspection provision of the contract, which anticipates acceptance or rejection after delivery. 1 It urges that the possibility of a rejection occurring after delivery would be rendered moot if delivery is to be equated with the shipment of conforming goods. Therefore, argues plaintiff, delivery relates only to a physical delivery and since, in this case, such delivery was timely (though on the last day), it is entitled to the 10-day extension available under subparagraph (a.) (ip.

While there is obvious merit to both positions, it must be conceded that both are positions of the extreme. Adherence to plaintiff’s view would preclude the Government’s right to effect a summary termination so long as a timely shipment was made. A contractor could escape an automatic termination through the simple expedient of timely shipment, notwithstanding the distinct possibility that the shipment might be substantially defective. Frustration of delivery schedules becomes the obvious end product if this view is endorsed. By the same token, defendant’s view would suggest similar undesirable consequences. Where delivery is measured against a doctrine of strict conformity, it invites the possibility of a surprise rejection occurring subsequent to a timely shipment. This, coupled with a summary termination power, would place in the hands of a contracting officer an unfettered right to reject and deny a contractor the opportunity to cure a nonconformity in his delivered product. Recourse to the courts becomes the inevitable consequence — a step made necessary because of the inflexibility inhering in defendant’s view.

In our judgment, the accommodation of these conflicting positions can be best effected by defining the term delivery (as used in the default provisions) as the equivalent of a shipment which is in substantial compliance with contract specifications. In striking this balance, we necessarily reject the either/or basis upon which the parties have based their positions.

We read subparagraph (a) (i) as relating only to the issue of timeliness of delivery; it clearly does not define delivery itself. Subparagraph (a) (ii), on the other hand, speaks to circumstances other than those issuing out of delivery, i. e., events occurring prior

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Universal Shelters of America, Inc. v. United States
87 Fed. Cl. 127 (Federal Claims, 2009)
Axion Corp. v. United States
75 Fed. Cl. 99 (Federal Claims, 2007)
Davies Precision Machining, Inc. v. United States
35 Fed. Cl. 651 (Federal Claims, 1996)
Hannon Electric Co. v. United States
39 Cont. Cas. Fed. 76,664 (Federal Claims, 1994)
Franklin Instrument Co. v. United States
30 Cont. Cas. Fed. 70,002 (Court of Claims, 1982)
Baltimore Contractors, Inc. v. United States
643 F.2d 729 (Court of Claims, 1981)
Churchill Chemical Corp. v. United States
602 F.2d 358 (Court of Claims, 1979)
Pelliccia v. United States
525 F.2d 1035 (Court of Claims, 1975)
Franklin E. Penny Co. v. United States
524 F.2d 668 (Court of Claims, 1975)
Astro Science Corp. v. United States
471 F.2d 624 (Court of Claims, 1973)
Blount Brothers Corporation v. The United States
424 F.2d 1074 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
366 F.2d 1003, 177 Ct. Cl. 227, 1966 U.S. Ct. Cl. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/radiation-technology-inc-v-the-united-states-cc-1966.