Baltimore Contractors, Inc. v. United States

643 F.2d 729, 28 Cont. Cas. Fed. 81,101, 226 Ct. Cl. 394, 1981 U.S. Ct. Cl. LEXIS 102
CourtUnited States Court of Claims
DecidedFebruary 25, 1981
DocketNo. 272-70
StatusPublished
Cited by6 cases

This text of 643 F.2d 729 (Baltimore Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Contractors, Inc. v. United States, 643 F.2d 729, 28 Cont. Cas. Fed. 81,101, 226 Ct. Cl. 394, 1981 U.S. Ct. Cl. LEXIS 102 (cc 1981).

Opinions

FRIEDMAN, Chief Judge,

delivered the judgment of the court and the following opinion:

This government contract case is before the court on defendant’s exceptions to the recommended decision of Trial Judge Spector. The trial judge held that, because of [395]*395various defects in the operating methods and procedures of the Board of Contract Appeals that decided the case, the plaintiff is entitled to a trial de novo on the issues the Board adjudicated. We hold that the Board proceedings in this case were so defective that the Board’s findings and decision are not entitled to the usual finality accorded Board decisions under the Wunderlich Act, 41 U.S.C. §§ 321-22. We conclude, however, that the plaintiff is not entitled to a trial de novo, but only to a de novo decision, based on the record before the Board, to be made by a different trial judge.

I.

A. In 1964, the plaintiff entered into a contract with the Architect of the Capitol (Architect) to construct for $11,777,000 two underground garages and related structures as part of the Rayburn House Office Building project. A number of disputes arose during the performance of the contract, and in 1970 the plaintiff filed suit in this court seeking damages for the claims involved in those disputes. The government moved to dismiss because of the plaintiffs failure to exhaust its administrative remedies before the Contract Appeals Board. The court denied the motion but suspended the case pending completion of the Board proceedings. [193 Ct. Cl. 1100 (1971)]. Those proceedings were concluded in 1975, when the Board denied the last of the plaintiffs claims.

The plaintiff here challenges the decision of the Contract Appeals Board respecting the plaintiffs claims under the "disputes” clause of the contract. It also seeks damages for breach of contract claims that the Board did not decide for lack of jurisdiction. The plaintiff further alleges that the proceedings before the Board were defective in various respects, and it seeks a trial de novo on the issues the Board adjudicated.

In 1976, Trial Judge Spector granted the plaintiffs motion for a trial de novo to the extent it related to (1) the claimed defects in the Board proceedings and (2) the breach of contract claims not decided by the Board. In an en banc [396]*396order this court upheld those rulings. Baltimore Contractors v. United Slates, 210 Ct. Cl. 678 (1976).

Following the trial on the issue of the propriety of the Board’s procedures and practices,1 the trial judge rendered the decision under review. On the basis of detailed findings and a lengthy opinion, he concluded that the Board proceedings were "defective, inadequate, and (in the case of the breach claims) unavailable,” that the Board’s decision therefore was not entitled to finality under the Wunderlich Act, and, "as a corollary to that conclusion, that plaintiff is entitled to a trial [de novo] of its claims in this court.”

B. The trial judge made a number of detailed findings, many of which we adopt,2 relating to the deficiencies in the House Board’s operations and procedures. To the extent necessary to our decision, we now summarize them.

1. The Organization and Staffing of the House Board. The Act authorizing construction of a new House Office Building directed the Architect to manage the project under the supervision of the House Office Building Commission (House Commission) composed of the Speaker and two other House Members. Pub. L. 84-24, 69 Stat. 41, § 1201, 40 U.S.C. § 175 note. The Architect supervised the preparation, negotiation, and execution of the construction contract. He also acted as the contracting officer in administering the contract and entertaining claims under the disputes [397]*397clause of the contract by the contractor for additional compensation. The contract contained the standard disputes clause under which the contractor could appeal a decision of the contracting officer to the head of the department, which in this cáse was the House Office Building Commission. The Commission created a Contract Appeals Board (House Board) to act as its "duly authorized representative” under the contract for deciding those appeals.

The House Commission appointed as members of the House Board employees of the General Accounting Office (GAO), to serve part time in that capacity in addition to performing their usual duties at their agency. The original House Board consisted of three GAO employees, two of whom were lawyers in the General Counsel’s office. The House Board subsequently was increased to six members, all GAO employees.

In connection with an earlier contract to construct the new Senate Office Building, which contract the Architect also had administered, the Senate Office Building Commission had designated members of the U.S. Army Corps of Engineers Contract Appeals Board to serve as an advisory board to the Senate Commission in deciding appeals from the Architect’s decisions under that contract. Another contractor on the House Office Building had protested the use of the GAO lawyers as part-time members of the House Board. According to the testimony of counsel for that contractor, which was disputed but which the trial judge apparently credited, Mr. Winkelmann, the Architect’s general counsel, informed counsel for the contractor, Mr. Cuneo, that

the HOBC would not authorize as its representative under the "Disputes” clause either the U.S. Army Corps of Engineers Board of Contract Appeals, or the Armed Services Board of Contract Appeals (ASBCA), because the HOBC wanted the board to be staffed by employees of the legislative branch. Mr. Winkelmann stated to Mr. Cuneo, and the latter so testified, that the Corps of Engineers Board had previously returned advisory decisions unfavorable to the Architect in matters involving the construction of the Senate Office Building, and that "[t]his [398]*398time, we’re going to use our own Board, our own lawyers, * * * the General Accounting Office lawyers.” [Fdg. 26.]

Following the filing of the present case, the plaintiff in 1972 asked the House Commission to relinquish jurisdiction over the claims then before the House Board, so that this court could decide all the claims in this case. In response to this request, Mr. Pettibone, a lawyer on the staff of the Architect’s General Counsel who was representing the Architect in the plaintiffs appeal to the House Board from the Architect’s decisions, submitted a memorandum to the Architect opposing the plaintiffs request.

He stated that to allow such an action would "leave the Government exposed, unprotected and at the mercy of a predatory contractor with trumped-up claims of $5 million.” In his response to the HOBC on July 24, 1972 the Architect of the Capitol in turn adopted the foregoing language of his trial attorney and otherwise based his reply on the Pettibone memorandum. [Fdg. 60.]

When plaintiff subsequently renewed with the House Commission its request to consolidate all of its claims into a single trial before this court, the Architect’s staff prepared the agenda for the House Commission meeting that considered the request.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SUFI Network Services, Inc. v. United States
102 Fed. Cl. 656 (Federal Claims, 2012)
Bell BCI Co. v. United States
56 Fed. Cl. 465 (Federal Claims, 2003)
Griffin & Dickson v. United States
35 Cont. Cas. Fed. 75,627 (Court of Claims, 1989)
Baltimore Contractors, Inc. v. United States
34 Cont. Cas. Fed. 75,267 (Court of Claims, 1987)
Degenaars Co. v. United States
31 Cont. Cas. Fed. 71,186 (Court of Claims, 1983)
Gulf & Western Industries, Inc. v. United States
671 F.2d 1322 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
643 F.2d 729, 28 Cont. Cas. Fed. 81,101, 226 Ct. Cl. 394, 1981 U.S. Ct. Cl. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-contractors-inc-v-united-states-cc-1981.