Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc.

435 U.S. 519, 98 S. Ct. 1197, 55 L. Ed. 2d 460, 1978 U.S. LEXIS 21, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20288, 11 ERC (BNA) 1439
CourtSupreme Court of the United States
DecidedApril 3, 1978
Docket76-419
StatusPublished
Cited by2,316 cases

This text of 435 U.S. 519 (Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 98 S. Ct. 1197, 55 L. Ed. 2d 460, 1978 U.S. LEXIS 21, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20288, 11 ERC (BNA) 1439 (1978).

Opinion

*523 Mr. Justice Rehnquist

delivered the opinion of the Court.

In 1946, Congress enacted the Administrative Procedure Act, which as we have noted elsewhere was not only “a new, basic and comprehensive regulation of procedures in many agencies,” Wong Yang Sung v. McGrath, 339 U. S. 33 (1950), but was also a legislative enactment which settled “long-continued and hard-fought contentions, and enacts a formula upon which opposing social and political forces have come to rest.” Id., at 40. Section 4 of the Act, 5 U. S. C. § 553 (1976 ed.), dealing with rulemaking, requires in subsection (b) that *524 “notice of proposed rule making shall be published in the Federal Register . . . describes the contents of that notice, and goes on to require in subsection (c) that after the notice the agency “shall give interested persons an opportunity to participate in the rule making through submission of written data, views, or arguments with or without opportunity for oral presentation. After consideration of the relevant matter presented, the agency shall incorporate in the rules adopted a concise general statement of their basis and purpose.” Interpreting this provision of the Act in United States v. AlleghenyLudlum Steel Corp., 406 U. S. 742 (1972), and United States v. Florida East Coast R. Co., 410 U. S. 224 (1973), we held that generally speaking this section of the Act established the maximum procedural requirements which Congress was willing to have the courts impose upon agencies in conducting rulemaking procedures. 1 Agencies are free to grant additional procedural rights in the exercise of their discretion, but reviewing courts are generally not free to impose them if the agencies have not chosen to grant them. This is not to say necessarily that there are no circumstances- which would ever justify a court in overturning agency action because of a failure to employ procedures beyond those required by the statute. But such circumstances, if they exist, are extremely rare.

Even apart from the Administrative Procedure Act this Court has for more than four decades emphasized that the formulation of procedures was basically to be left within the discretion of the agencies to which Congress had confided the responsibility for substantive judgments. In FCC v. Schreiber, 381 U. S. 279, 290 (1965), the Court explicated *525 this principle, describing it as “an outgrowth of the congressional determination that administrative agencies and administrators will be familiar with the industries which they regulate and will be in a better position than federal courts or Congress itself to design procedural rules adapted to the peculiarities of the industry and the tasks of the agency involved.” The Court there relied on its earlier ease of FCC v. Pottsville Broadcasting Co., 309 U. S. 134, 138 (1940), where it had stated that a provision dealing with the conduct of business by the Federal Communications Commission delegated to the Commission the power to resolve “subordinate questions of procedure . . . [such as] the scope of the inquiry, whether applications should be heard contemporaneously or successively, whether parties should be allowed to intervene in one another’s proceedings, and similar questions.”

It is in the light of this background of statutory and decisional law that we granted certiorari to review two judgments of the Court of Appeals for the District of Columbia Circuit because of our concern that they had seriously misread or misapplied this statutory and decisional law cautioning reviewing courts against engrafting their own notions of proper procedures upon agencies entrusted with substantive functions by Congress. 429 U. S. 1090 (1977). We conclude that the Court of Appeals has done just that in these cases, and we therefore remand them to it for further proceedings. We also find it necessary to examine the Court of Appeals’ decision with respect to agency action taken after full adjudicatory hearings. We again conclude that the court improperly intruded into the agency’s decisionmaking process, making it necessary for us to reverse and remand with respect to- this part of the cases also.

I

A

Under the Atomic Energy Act of 1954, 68 Stat. 919, as amended, 42 U. S. C. § 2011 et seq., the Atomic Energy Comm *526 ission 2 was given broad regulatory authority over the development of nuclear energy. Under the terms of the Act, a utility seeking to construct and operate a nuclear power plant must obtain a separate permit or license at both the construction and the operation stage of the project. See 42 U. S. C. §§ 2133, 2232, 2235, 2239. In order to obtain the construction permit, the utility must file a preliminary safety analysis report, an environmental report, and certain information regarding the antitrust implications of the proposed project. See 10 CFR §§2.101, 50.30 (f), 50.33a, 50.34 (a) (1977). This application then undergoes exhaustive review by the Commission’s staff and by the Advisory Committee on Reactor Safeguards (ACRS), a group of distinguished experts in the field of atomic energy. Both groups submit to the Commission their own evaluations, which then become part of the record of the utility’s application. 3 See 42 U. S. C. §§ 2039, 2232 (b). The Commission staff also undertakes the review required by the National Environmental Policy Act of 1969 (NEPA), 83 Stat. 852, 42 U. S. C. §4321 et seq., and prepares a draft environmental impact statement, which, after being circulated for comment, 10 CFR §§ 51.22-51.25 (1977), is revised and becomes a final environmental impact statement. § 51.26. Thereupon a three-member Atomic Safety and Licensing Board conducts a public adjudicatory hearing, 42 U. S. C. §

Related

Huzhou Muyun Wood Co. v. United States
2017 CIT 162 (Court of International Trade, 2017)
Nrdc v. Usepa
Ninth Circuit, 2017
Brodsky v. United States Nuclear Regulatory Commission
783 F. Supp. 2d 448 (S.D. New York, 2011)
GOVERNMENT OF THE PROVINCE OF MANITOBA v. Salazar
691 F. Supp. 2d 37 (District of Columbia, 2010)
Gardner v. United States Bureau of Land Management
633 F. Supp. 2d 1212 (D. Oregon, 2009)
Khalili v. Holder
557 F.3d 429 (Sixth Circuit, 2009)
Blue Ocean Institute v. Gutierrez
585 F. Supp. 2d 36 (District of Columbia, 2008)
United States Ex Rel. Purcell v. MWI Corp.
520 F. Supp. 2d 158 (District of Columbia, 2007)
Hammond v. Norton
370 F. Supp. 2d 226 (District of Columbia, 2005)
Basel Action Network v. Maritime Administration
370 F. Supp. 2d 57 (District of Columbia, 2005)
Hagelin v. Federal Election Commission
332 F. Supp. 2d 71 (District of Columbia, 2004)
City of Shoreacres v. Waterworth
332 F. Supp. 2d 992 (S.D. Texas, 2004)
Australians for Animals v. Evans
301 F. Supp. 2d 1114 (N.D. California, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
435 U.S. 519, 98 S. Ct. 1197, 55 L. Ed. 2d 460, 1978 U.S. LEXIS 21, 8 Envtl. L. Rep. (Envtl. Law Inst.) 20288, 11 ERC (BNA) 1439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vermont-yankee-nuclear-power-corp-v-natural-resources-defense-council-scotus-1978.