Jonal Corporation v. District of Columbia

533 F.2d 1192, 175 U.S. App. D.C. 57
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 21, 1976
Docket74-1191
StatusPublished
Cited by26 cases

This text of 533 F.2d 1192 (Jonal Corporation v. District of Columbia) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jonal Corporation v. District of Columbia, 533 F.2d 1192, 175 U.S. App. D.C. 57 (D.C. Cir. 1976).

Opinions

MERHIGE, District Judge:

Appellant, a Maryland corporation doing business in the District of Columbia, takes this appeal from the summary judgment of the District Court holding that decisions of the District of Columbia Contract Appeals Board are subject to the limited scope of judicial review provided in the Wunderlich Act, 41 U.S.C. §§ 321-22 (1970). Jonal sought payment of $71,726.13 allegedly due for work done pursuant to a contract with the District of Columbia to build several water pollution control plant buildings.1 Since the amount in controversy exceeds [1194]*1194$50,000, jurisdiction was conferred on the District Court by D.C.Code Ann., § 11-501(4) (1973).2

The facts, as appear in the record, are that following the completion of competitive bidding procedures, the District of Columbia, on April 13, 1967, awarded a contract for the construction of two water pollution control plant supply buildings to the appellant Jonal. The parties entered into a written contract on May 1, 1967 which incorporated by reference all the bid plans and specifications, and all the terms of the bid invitation. Article 15 of the contract contained the following provisions:

Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within thirty (30) days to the Contract Appeals Board, whose decision shall be final and conclusive upon the parties thereto, subject to the limitation of Sec. 3(b)(2) of Reorganization Plan No. 5 of 1952. In the meantime the contractor shall diligently proceed with the work as directed.

After the appellant began work in accordance with the contract, disputes arose over the proper interpretation to be given various notes appearing on the contract drawings. Jonal Corporation claimed that it had not contracted to perform specified items of work,3 but the contracting officer decided to the contra and directed Jonal to proceed with the execution of the contract. Jonal accordingly performed the work under protest, and then submitted claims for compensation to the contracting officer for the alleged additional work. The contracting officer denied the claims and Jonal appealed to the District of Columbia Contract Appeals Board pursuant to the procedure outlined in Article 15 of the contract.

On March 7 and 8, 1972 hearings were held before a three-man panel of the Contract Appeals Board. The members of the Board empanelled to hear the matter were Louis P. Robbins, Assistant Corporation Counsel for the District of Columbia,4 Lou Frana, Assistant Corporation Counsel for the District of Columbia, and Gerald I. Sawyer, a Contracting Officer employed by the District of Columbia Department of Highways. Mr. Robbins and Mr. Frana were appointed by C. Francis Murphy, Chairman of the Contract Appeals Board for the District of Columbia and Corporation Counsel for the District of Columbia. Mr. Sawyer was appointed to the panel by Mr. Robbins. The counsel for the District of Columbia before the Board was James E. Lemert, assigned by Mr. Murphy to both defend the case and prosecute the District of Columbia’s case against Jonal for liquidated damages. On February 16, 1973, the Board issued its findings of fact, conclusions of law, opinions and decisions denying appellant’s claims.

On April 4, 1973, appellant filed suit, giving rise to this appeal, against the District of Columbia to recover the costs, expenses and damages occasioned by the alleged modifications in the original contract specifications. The District of Columbia answered the complaint on April 27, 1973 and moved for summary judgment on June 19, 1973, contending that disputes arising out of contracts entered into by the District are reviewable under the standards prescribed by the Wunderlich Act, and that the Court’s review was restricted to the question of whether decision of the Contract Appeals Board was supported by “substantial evidence.” On July 5, 1973, the appellant filed a “Counterstatement of Undisputed Facts” and a statement of “Points and Authorities in Opposition to Defendant’s Motion for Summary Judgment.” In those papers Jonal contended that the Court must first decide whether Organization Order No. 9, establishing the Board and its con[1195]*1195stituency, violates, on its face, the Due Process Clause of the Fifth Amendment to the Constitution of the United States. In addition, the appellant argues that the Board was so created as to be inherently tainted, allowing the District Court to review de novo the Board’s decision. Finally, the appellant noted that it “reserve(d) the right to file supplemental points and authorities in opposition to defendant’s arguments on the limitation of (the District) Court’s review, and the finality to be accorded the ruling of the Contract Appeals Board, . . . after the issues raised by this pleading are resolved.”

On November 27,1973, the District Court issued its memorandum and order which are the subject of this appeal. The trial judge held that appellant’s constitutional claim “must fail for want of jurisdiction since the claim was not properly pleaded as a matter of form.” The trial judge also held that the Wunderlich Act’s standards of review are applicable to the case and, in accordance with those standards, that the appellee was entitled to summary judgment on the merits. “After a review of the whole administrative record, the Court finds that the District of Columbia Contract Appeals Board’s decision was based on substantial evidence, and was not arbitrary or capricious.” Op. at 6.

The appellee argues, in support of the District Court’s ruling, that the appellant’s procedural due process claim was belatedly proffered and improperly pleaded. This position has some justification. The Contract Appeals Board was established in 1953 and its composition, function and authority have remained essentially unchanged since its inception. See Reorganization Order No. 29, pt. VII, D.C.C.E. § 1-App. II 125 (1966), effective September 17, 1953. See also Organization Order No. 9, pt. VI, D.C.Code Ann. § 1-App. 235-36 (1973), effective June 6, 1968; Reorganization Plan No. 3 of 1967 § 303, 3 C.F.R. 345 (Comp.1967), 5 U.S.C. App. § 588 (1970). Yet, Jonal Corporation’s constitutional objection to the Board’s composition was not presented until after the contract containing the questioned grievance procedure had been knowledgeably executed in 1967 by its representative,5 the administrative procedure had been completely exhausted on the contract issues, the case had been filed and fully pleaded in the District Court, and the defendant had filed a motion for summary judgment. Since the constitutional defect is allegedly inherent in the grievance procedure, the plaintiff, in fairness, ought to have presented its position at an earlier stage of the process.6 We need, however, not reach the issue of whether such a delay in presenting the claim operates to bar this Court from further considering the argument, for we conclude that the appellant’s procedural due process contention is lacking in substance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krzywicki v. Harker
District of Columbia, 2024
Ethicon Endo-Surgery, Inc. v. Covidien Lp
812 F.3d 1023 (Federal Circuit, 2016)
American Chiropractic Ass'n v. Shalala
108 F. Supp. 2d 1 (District of Columbia, 2000)
Petrousky v. United States
728 F. Supp. 890 (N.D. New York, 1990)
Rafeedie v. Immigration & Naturalization Service
880 F.2d 506 (D.C. Circuit, 1989)
Former Employees of Bass Enterprises Production Co. v. United States
706 F. Supp. 897 (Court of International Trade, 1989)
Sherman v. District of Columbia Commission on Licensure to Practice Healing Art
476 A.2d 667 (District of Columbia Court of Appeals, 1984)
Network Technical Services, Inc. v. D.C. Data Co.
464 A.2d 133 (District of Columbia Court of Appeals, 1983)
Club 99, Inc. v. District of Columbia Alcoholic Beverage Control Board
457 A.2d 773 (District of Columbia Court of Appeals, 1982)
Baltimore Contractors, Inc. v. United States
643 F.2d 729 (Court of Claims, 1981)
Main Road v. Aytch
565 F.2d 54 (Third Circuit, 1977)
Ritz v. O'DONNELL
413 F. Supp. 1365 (District of Columbia, 1976)
Jonal Corporation v. District of Columbia
533 F.2d 1192 (D.C. Circuit, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
533 F.2d 1192, 175 U.S. App. D.C. 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jonal-corporation-v-district-of-columbia-cadc-1976.