Gunnell Construction Company, Inc., a Delaware Corporation v. District of Columbia, a Municipal Corporation

551 F.2d 425, 23 Cont. Cas. Fed. 80,972, 179 U.S. App. D.C. 239, 1977 U.S. App. LEXIS 10307
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 28, 1977
Docket76-1046
StatusPublished
Cited by2 cases

This text of 551 F.2d 425 (Gunnell Construction Company, Inc., a Delaware Corporation v. District of Columbia, a Municipal Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gunnell Construction Company, Inc., a Delaware Corporation v. District of Columbia, a Municipal Corporation, 551 F.2d 425, 23 Cont. Cas. Fed. 80,972, 179 U.S. App. D.C. 239, 1977 U.S. App. LEXIS 10307 (D.C. Cir. 1977).

Opinion

Opinion for the court filed by Circuit Judge WRIGHT.

J. SKELLY WRIGHT, Circuit Judge:

Appellant Gunnell Construction Company appeals from a judgment of the District Court which denied its claim for additional compensation under a contract with the District of Columbia. In January 1961 Gunnell and the District entered into an agreement for construction of the Bertie Backus Junior High School in the District. The contract called for Gunnell to drive some 836 piles to various depths. Once work commenced appellant encountered difficulty driving the piles and ultimately incurred $134,969.56 in costs above its estimate, allegedly because subsurface conditions differed in material respects from test borings, supplied by the District, upon which its estimate had been based.

The contract between Gunnell and the District contained a “Disputes” clause 1 requiring Gunnell to submit its claim for ad *427 ditional compensation to a Contracting Officer with a right of appeal to the District of Columbia Contract Appeals Board. This procedure was followed and both the Contracting Officer and the Board rejected appellant’s claim. Appellant then sought review of the Board’s actions in the District of Columbia Court of Appeals, which dismissed the petition for review on the ground that the District of Columbia Administrative Procedure Act does not apply to the Board. Gunnell Const. Co. v. Contract Appeals Board, 282 A.2d 556 (D.C. App.1971). Following the Court of Appeals’ statement that review could be had only by an action on the contract, Gunnell filed this suit in the District Court. During pretrial the District moved for entry of an order to the effect that the case should be submitted on the basis of the administrative record created by the Board. This motion was granted over Gunnell’s objection. Applying the standard of review of the Wunderlich Act, 2 the District Court entered judgment against appellant.

In this appeal Gunnell does not challenge the District Court’s finding that the order of the Contract Appeals Board was supported by substantial evidence. Instead, Gunnell takes the position that it was entitled to a trial de novo before the District Court. Three arguments are made in favor of this position: first, that the Wunderlich Act does not apply to the District of Columbia; second, that the composition of the Board was biased, denying it due process of law; and third, that the Board failed to abide by its own regulations in assigning members to the panel that heard Gunnell’s claim.

Gunnell first argues that the Wunderlich Act, which by its terms applies only to “contracts] entered into by the United States,” 41 U.S.C. § 321 (1970), does not apply to contracts entered by the District of Columbia, an entity legally distinct from the United States. Because the Act does not apply, appellant concludes, a trial de novo is required. We do not agree.

The Wunderlich Act was passed to reverse the decision in United States v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113 (1951), which held that a decision of a government contract board of appeals was final and unreviewable unless actual fraud could be shown. The Act, which makes such a board’s decision final unless fraudulent, arbitrary, capricious, “grossly erroneous,” or not supported by substantial evidence, was intended to broaden the common law standard of review of contract appeal board actions. It is therefore immaterial whether the Wunderlich Act applies by its terms to District of Columbia contracts. If it does apply, the District Court was correct in ruling that the case should be decided on the administrative record. If it does not, the applicable law is that of United States v. Wunderlich, supra, which would give Gunnell even less judicial review than it has already received, and the trial court’s application of the Act would be harmless error. In addition, we agree with the trial court that District of Columbia v. Heman Ward, Inc., 261 A.2d 836, 838 (D.C.App.1970), which holds that the principles of the Wunderlich Act apply to contract disputes to which the District of Columbia is a party, governs this case and bars a trial de novo.

Appellant’s second and third arguments turn on the composition of the panel of the Contract Appeals Board which decided appellant’s case. The Board was established *428 under District of Columbia Organization Order No. 9 which provides, in relevant part:

* * * There is established a Contract Appeals Board, D.C., consisting of one or more active or retired Assistant Corporation Counsel designated by the Corporation Counsel, one of whom shall serve as Chairman of the Board, and two or more persons appointed or designated by the Commissioner [now Mayor of the District of Columbia] from among officers assigned to the Corps of Engineers and detailed to assist the Commissioner * * *, or from among active or retired District of Columbia officers and employees who have had practical experience in the administration of government contracts. Except as otherwise provided by its rules, all business of the Board shall be conducted by panels of not less that three members at least one of whom shall be an active or retired Assistant Corporation Counsel member, but any two members of a panel shall constitute a quorum for the transaction of any business of the Board.

D.C.Org. Order No. 9 Part VI, 1 D.C.Code, Appendix, at 235 (1973) (emphasis added). The Board’s rules parallel this provision. 3

In this case a panel consisting of two active Corporation Counsel and one “technical” member 4 was appointed to hear Gunnell’s claim. At the hearing only two “law” members were present. However, the Board’s rules allow an absent member to participate in the decision of a case so long as that member is familiar with the transcript of the hearing, 5 and counsel for the District concedes that it was not known how many members of the panel would actually decide the case until a decision was rendered, see br. for appellee at 16. 6 When the decision was rendered it was signed by only the two “law” members of the panel.

Gunnell argues that a decision rendered by such a “law” quorum is defective in two respects: first, because it deprives Gunnell of a “technical” member in contravention of the purpose of the Organization Order and the Board’s own rules; and second, because the quorum of the panel was infected by a serious possibility of bias since both panel members were subordinates of the Corpora *429

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones & Artis Construction Co. v. District of Columbia Contract Appeals Board
549 A.2d 315 (District of Columbia Court of Appeals, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
551 F.2d 425, 23 Cont. Cas. Fed. 80,972, 179 U.S. App. D.C. 239, 1977 U.S. App. LEXIS 10307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gunnell-construction-company-inc-a-delaware-corporation-v-district-of-cadc-1977.