United States v. Anthony Grace & Sons, Inc.

384 U.S. 424, 86 S. Ct. 1539, 16 L. Ed. 2d 662, 1966 U.S. LEXIS 2753
CourtSupreme Court of the United States
DecidedOctober 10, 1966
Docket439
StatusPublished
Cited by193 cases

This text of 384 U.S. 424 (United States v. Anthony Grace & Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 86 S. Ct. 1539, 16 L. Ed. 2d 662, 1966 U.S. LEXIS 2753 (1966).

Opinion

Mr. Justice White

delivered the opinion of the Court.

In United States v. Carlo Bianchi & Co., 373 U. S. 709, we held that, aside from questions of fraud, a reviewing *425 court is limited to the administrative record made below in determining the finality to be given departmental decisions and findings made by a Board of Contract Appeals pursuant to a standard government disputes clause. In the present case we are called upon to decide whether the reviewing court or the Board of Contract Appeals should make the original record on an issue which the Board did not resolve because it erroneously dismissed the appeal before it as untimely.

The question is framed by the following facts. The Department of the Air Force issued an invitation for bids for the construction of a military housing project at Topsham Air Force Station, Maine. The invitation included a tentative minimum wage schedule which the contractor would have to meet. It also advised that the wage schedule would be finally redetermined by the Secretary of Labor not more than 90 days prior to the commencement of construction and that the Federal Housing Commissioner would then adjust the contract price to reflect any changes made in the wage schedules. 1 In addition, the successful bidder was required to complete certain preparatory acts in order to close the contract and to post a $25,000 deposit to ensure the closing of the contract. Respondent, Anthony Grace & Sons, Inc., was the low acceptable bidder and a letter of acceptability was sent to it. That letter reminded *426 respondent that failure to close the contract within a specified number of days was sufficient justification to warrant the Department of the Air Force in cancelling the bid and letter of acceptability, in retaining the deposit for liquidated damages and in determining additional liability for actual damages. A disputes clause in the letter of acceptability made such decision by the Department of the Air Force final unless, within 30 days from the receipt of the decision, respondent appealed to the Armed Services Board of Contract Appeals, whose decision would be final and conclusive unless fraudulent or capricious or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence. 2 After receiving subsequent wage schedules from the Secretary of Labor, respondent concluded that certain work was being placed in higher wage categories than was provided in the specifications which accompanied the bid invitation. On the basis of this alleged deviation from the original specifications respondent asked *427 first the Housing Commissioner and then the Department of the Air Force to raise the contract price. These requests were refused and respondent then notified the Air Force that it would be unable to complete the closing until this matter was cleared up. In the ensuing exchange of letters, the contracting officer informed respondent that its bid and the letter of acceptability were being canceled and its deposit was being retained. Pursuant to the disputes clause, respondent appealed this decision to the Armed Services Board of Contract Appeals, which dismissed the appeal as out of time without considering the merits of the case. Respondent then sued in the Court of Claims to recover its deposit and for damages resulting from the Government’s alleged wrongful cancellation. That court concluded that the appeal to the Board was timely and that the Board had erred in not reaching the merits of the case. With Judges Davis and Laramore dissenting, the court then decided to remand the case to its own trial commissioner, rather than to the Board of Contract Appeals, to make a record and consider the case on its merits. The Government asked us to grant certiorari to consider whether this was in violation of the principles announced in the Wunderlich Act 3 and United States v. Carlo Bianchi & Co., supra. We granted certiorari, 382 U. S. 901, and we now reverse.

*428 This question was anticipated in Bianchi, supra, where we considered what a reviewing court should do when the administrative record is defective, or inadequate or reveals the commission of a prejudicial error. Two suggestions were given:

“First, there would undoubtedly be situations in which the court would be warranted, on the basis of the administrative record, in granting judgment for the contractor without the need for further administrative action. Second, in situations where the court believed that the existing record did not warrant such a course, but that the departmental determination could not be sustained under the standards laid down by Congress, we see no reason why the court could not stay its own proceedings pending some further action before the agency involved. Cf. Pennsylvania R. Co. v. United States, 363 U. S. 202. Such a stay would certainly be justified where the department had failed to make adequate provision for a record that could be subjected to judicial scrutiny, for it was clearly part of the legislative purpose to achieve uniformity in this respect.” 373 U. S. 709, 717-718.

The policy reflected in this language, which requires utilization of the administrative procedures contractually bargained for, was clearly intended by Congress, see H. R. Rep. No. 1380, 83d Cong., 2d Sess. (1954); United States v. Carlo Bianchi & Co., supra, at 715-718, and it has been consistently reflected in a long line of decisions by this Court. See United States v. Wunderlich, 342 U. S. 98; *429 United States v. Moorman, 338 U. S. 457; United States v. Holpuch Co., 328 U. S. 234; United States v. Blair, 321 U. S. 730; United States v. Callahan Walker Construction Co., 317 U. S. 56; Kihlberg v. United States, 97 U. S. 398. Pre-eminently, this policy is grounded on a respect for the parties’ rights to contract and to provide for their own remedies.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Theodore James Meason v. the State of Texas
Court of Appeals of Texas, 2023
Blakely, Ex Parte Quincy Demond
Court of Appeals of Texas, 2018
People v. Anderson CA4/2
California Court of Appeal, 2016
Com. v. Brown, W.
Superior Court of Pennsylvania, 2015
In re K.S. CA3
California Court of Appeal, 2015
Sufi Network Services, Inc. v. United States
755 F.3d 1305 (Federal Circuit, 2014)
Coffee Connections, Inc. v. United States
113 Fed. Cl. 741 (Federal Claims, 2013)
Commonwealth v. Michael
431 A.2d 333 (Superior Court of Pennsylvania, 1981)
Merritt-Chapman & Scott Corp. v. United States
528 F.2d 1392 (Court of Claims, 1976)
Commonwealth v. Hollenbaugh
295 A.2d 78 (Supreme Court of Pennsylvania, 1972)
R.E.D.M. Corporation v. The United States
428 F.2d 1304 (Court of Claims, 1970)
Max Drill, Inc. v. The United States
427 F.2d 1233 (Court of Claims, 1970)
Bird & Sons, Inc. v. The United States
420 F.2d 1051 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
384 U.S. 424, 86 S. Ct. 1539, 16 L. Ed. 2d 662, 1966 U.S. LEXIS 2753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-anthony-grace-sons-inc-scotus-1966.