Owens-Corning Fiberglas Corporation and Polytron Company, by and Through Walsh Construction Company v. The United States

419 F.2d 439, 190 Ct. Cl. 211, 1969 U.S. Ct. Cl. LEXIS 166
United States Court of Claims·Decided December 12, 1969·No. 301-66·Published·Cited by 22 cases

Opinion

ON PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT AND DEFENDANT’S CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This case was referred to Trial Commissioner Louis Spector with directions to prepare and file an opinion on the issues of plaintiff’s motion for summary judgment and defendant’s cross-motion for summary judgment under the order of reference and Rule 99(c) [since September 1, 1969, Rule 166(c)]. The commissioner has done so in an opinion and *440 report filed on April 21, 1969, wherein such facts as are necessary to the opinion are set forth. On November 4, 1969, defendant filed with the court defendant’s notice that it does not intend to request review of the commissioner’s report. On November 14, 1969, plaintiff filed a motion that the court adopt the opinion of the commissioner which was filed April 21, 1969. The case has been submitted to the court on the briefs of the parties without oral argument. Since the court agrees with the opinion and recommended conclusion of the trial commissioner, it hereby adopts the same as the basis for its judgment in this case as hereinafter set forth. Therefore, plaintiff’s motion for summary judgment is granted, defendant’s cross-motion is denied and judgment is entered for plaintiff in accordance with the opinion. Further proceedings are stayed pursuant to Rule 167 [prior to September 1, 1969, Rule 100] for a period of ninety (90) days to afford the parties an opportunity to obtain an administrative resolution by the agency of the equitable adjustment to which plaintiff is entitled.

OPINION OF COMMISSIONER

SPECTOR, Commissioner:

This case grows out of a unique contract between plaintiff Walsh Construction Company and the Atomic Energy Commission. The purpose of the contract is not fully revealed by the record because it called for the construction of an environment for tests, and the details concerning the tests were classified. As a result, plaintiff was not fully apprised of the purpose to which this construction was to be put, a fact which has an important bearing on the principal issue presented, namely, the proper interpretation to be placed upon defendant’s specification.

Other issues are presented by the caption of this case, Owens-Corning and Polytron being first and second-tier subcontractors of the plaintiff prime contractor, Walsh. They were the subcontractors directly concerned with performing the segment of work out of which the dispute arose, and they are described in the caption as acting “by and through Walsh Construction Company.” Defendant asserts that they are “not proper plaintiffs,” and also .that Walsh’s right to recover is barred by the so-called Severin doctrine. 1

General Statement of Facts

On October 15, 1959, the Atomic Energy Commission (hereinafter referred to as AEC), invited proposals for a fixed-price construction contract in furtherance of an operation designated as the Structural Response Program. The test site is at Mercury, Nevada. Walsh was awarded a contract dated November 4, 1959, in the amount of $1,131,828, described as construction of “a shaft, tunnels, and drifts and other related work.”

The work consisted of construction of a perpendicular mine-like shaft approximately 800 feet deep, with tunnels and drifts running out from the main shaft. A drawing furnished as Appendix A .to the hearing examiner’s opinion on appeal, shows that these lateral tunnels and drifts were divided into about 20 sections or compartments which were to be lined with various structural materials (steel, corrugated metal, concrete). Polyurethane (a type of plastic foam) was to be installed between the material to be tested and the jagged rock surface of the excavated tunnel or drift. The polyurethane was apparently to act as a shock absorber, since another shaft was to be sunk at a specified distance from the one above described, and the AEC planned to detonate .therein either a nuclear or conventional explosive. In this *441 way the agency intended to test the effect of the blast on the various structural materials lining the compartments in the original shaft.

Work was to be completed within 150 days, that is, by April 3, 1960. With respect to that part of the work relating to placement of the polyurethane, Walsh entered into a subcontract on January 19, 1960, in the approximate amount of $125,000, with the Fiberglas and Engineering Supply Division (hereinafter referred to as Fenco) of the Owens-Corning Fiberglas Corporation for the placement of the polyurethane. The subcontract incorporated by reference various clauses of the prime contract including the “Disputes” and “Changes” clauses. Thereafter Fenco, in February 1960, entered into two purchase orders totaling $100,000 with the Polytron Corporation (a subsidiary of Pacific Vegetable Oil Company), for the purchase of the polyurethane material and a machine suitable for its mixing and application. Mr. Jennings, President of Polytron, is an expert in the field of polyurethane.

Specification section 5-03 sets forth the requirements for the polyurethane, as follows:

5-03 PLASTIC FOAU
The plastic foam used for backpacking shall be polyurethane foam similar to that manufactured by Union Carbide Chemical Company. The foam shall be formed in place by mixing liquid reactants as furnished by the Manufacturer and in accordance with the latter’s recommendation. The reactants shall combine completely during the foaming step known as the “one-shot” process. The foam shall have a density of 6 lbs. per cubic foot with the following specified properties:
Parallel to foaming direction
Perpendicular to foaming direction
Yield stress (psi) ....... 170 120
Modulus of elasticity (psi) 6800 3600
No load shall be imposed on the foam and the form shall be left in place until the foam has attained a strength equal to half of the specified yield strength as manifested by a sample piece. To avoid damaging the foam during stripping of the form, a plastic membrane shall be used to line the form prior to foaming. After the form is removed, the membrance shall be left in place. The foam shall be used as the outside form for the concrete lining.
Testing of the foam is governed by provision SC-25 entitled “Furnishing of Samples of Materials,” as follows:
a. To permit laboratory analysis and testing of materials used in the test sections of the drifts, test samples shall be prepared packaged and shipped f.o.b. Urbana, Illinois.
**********
8. Foam — Five (5) one foot cubes of plastic foam from each 15 ft. tunnel section shall be provided. These cubes may be poured into corrugated paper boxes or similar containers. Each cube is to be marked appropriately to identify the tunnel section for which it was poured.

Free access — add to your briefcase to read the full text and ask questions with AI

Owens-Corning Fiberglas Corporation and Polytron Company, by and Through Walsh Construction Company v. The United States, 419 F.2d 439, 190 Ct. Cl. 211, 1969 U.S. Ct. Cl. LEXIS 166 (cc 1969).

419 F.2d 439 (Owens-Corning Fiberglas Corporation and Polytron Company, by and Through Walsh Construction Company v. The United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2020
Interstate Contracting Corp. v. City of Dallas
135 S.W.3d 605 (Texas Supreme Court, 2004)
Metric Constructors v. United States
314 F.3d 578 (Federal Circuit, 2002)
George Hyman Construction Co. v. United States
39 Cont. Cas. Fed. 76,601 (Federal Claims, 1993)
American Maritime Transport, Inc. v. United States
35 Cont. Cas. Fed. 75,722 (Court of Claims, 1989)
Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica
717 F. Supp. 1021 (S.D. New York, 1989)
Affholder, Inc. v. Preston Carroll Co.
866 F.2d 881 (Sixth Circuit, 1989)
Brazier Forest Products, Inc. v. United States
33 Cont. Cas. Fed. 74,925 (Court of Claims, 1987)
Pan Arctic Corp. v. United States
33 Cont. Cas. Fed. 73,742 (Court of Claims, 1985)
Public Health Trust of Dade County v. M.R. Harrison Construction Corp.
454 So. 2d 659 (District Court of Appeal of Florida, 1984)
Folk Construction Co. v. United States
31 Cont. Cas. Fed. 71,247 (Court of Claims, 1983)
Mitsui & Co. v. Puerto Rico Water Resources Authority
528 F. Supp. 768 (D. Puerto Rico, 1981)
Quarles Petroleum Co. v. United States
551 F.2d 1201 (Court of Claims, 1977)
Keydata Corp. v. United States
504 F.2d 1115 (Court of Claims, 1974)
University of Alaska v. Modern Construction, Inc.
522 P.2d 1132 (Alaska Supreme Court, 1974)
Stop & Shop Companies, Inc. v. Gilbane Building Co.
304 N.E.2d 429 (Massachusetts Supreme Judicial Court, 1973)
Kenneth Reed Construction Corp. v. United States
475 F.2d 583 (Court of Claims, 1973)