Design & Production, Inc. v. United States

36 Cont. Cas. Fed. 75,844, 20 Cl. Ct. 207, 1990 U.S. Claims LEXIS 151, 1990 WL 49779
CourtUnited States Court of Claims
DecidedApril 23, 1990
DocketNo. 553-84C
StatusPublished
Cited by9 cases

This text of 36 Cont. Cas. Fed. 75,844 (Design & Production, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Design & Production, Inc. v. United States, 36 Cont. Cas. Fed. 75,844, 20 Cl. Ct. 207, 1990 U.S. Claims LEXIS 151, 1990 WL 49779 (cc 1990).

Opinion

[208]*208ORDER

HORN, Judge.

This application for attorney’s fees, filed on January 11, 1990, comes before the court on plaintiff’s application for costs and expenses, pursuant to the Equal Access to Justice Act, 28 U.S.C. § 2412(d) (1982 & Supp. Y 1987). Based on a review of the submissions of the parties, the court, hereby, awards $56,451.40 in attorneys’ fees and other costs.1

[209]*209BACKGROUND

On September 14, 1989, the court issued its Opinion in Design and Production, Inc. v. United States, 18 Cl.Ct. 168 (1989). In that Opinion, the court found that the plaintiff, Design and Production, Inc. (hereinafter, D & P), was entitled to recovery on most of its claim, but that the defendant was not entitled to recovery on its counterclaim. Judgement in this case was entered on October 13,1989, following a joint stipulation by the parties regarding damages in the amount of $728,129.00, together with interest. The award constituted an equitable adjustment for work directed by authorized government officials for the construction of the theater walls, a portion of the acoustical work, painting, installation of the hardware for the theater doors, and portions of the drywall and ceiling work in the queuing and exit areas. The award also included compensation for insurance, bonds and permits, general and administrative expenses and a reasonable profit. Defendant’s counterclaim was denied in its totality because the work and equipment for which the defendant sought recovery was either not required by the contract, was deleted from the contract requirements by an authorized representative of the government, or because defendant failed to substantiate its claim at trial.

Plaintiff’s original claim arose from the performance of work in the United States Pavilion at the 1984 Louisiana World Exhibition. The plaintiff alleged that, at the direction of Department of Commerce officials, it performed work which was outside the scope of plaintiff’s original contract, No. TA-83-SAC-02240. Plaintiff’s suit in this court was filed on October 26, 1984, approximately eight months after it submitted its claim for payment to the government, on March 2, 1984, but prior to the issuance of the contracting officer’s decision. Following denial of D & P’s claim by the contracting officer, on February 1, 1985, based on his finding that the construction of the theaters and the related work was within the scope of the original contract, the defendant amended its previously filed answer, to include a counterclaim.

Plaintiff, D & P, subsequently filed, by leave of court,2 an amended complaint adding the findings of the Defense Contract Audit Agency’s (hereinafter, DCAA) Advisory Audit Report on Contract No. TA-83SAC-02240, issued on February 14,1986, in which the DCAA increased the recommended general and administrative costs. In the amended complaint, the plaintiff also claimed that it was entitled to recover the full amount of the subcontract, as well as its overhead expenses, plus a reasonable allotment for profit. The plaintiff further alleged that specific portions of the work performed under the subcontract were additional to the original scope of its contract with the defendant. Specifically, D & P alleged that the following were not within the scope of the contract: construction of demising walls separating the pavilion theaters from adjoining queuing and exit hallways (hereinafter, theater walls), installation of lighting in the theaters, application of acoustical spray to the walls and ceiling in the theaters, and construction of the walls and ceilings in the queuing areas adjacent to the theaters. D & P’s claim also included recovery for the cost of the subcontractor’s work in constructing the ceiling and performing mechanical work in the projection booth and for installing speaker brackets in the theaters, as well as for insurance, bonds, and permits, pur[210]*210chased by the subcontractor in performance of the subcontract.

The government, in its counterclaim, alleged that D & P failed to supply and install all of the electronic equipment that was called for in the contract. The government also alleged that D & P failed to fully perform the work agreed to in the contract in exhibit Areas Three and Eight and for the administrative area of the pavilion.

The plaintiff, D & P, and its attorneys have filed an application to this court in accordance with the Equal Access to Justice Act, 28 U.S.C. § 2412 (1982 & Supp. V 1987) for fees and expenses in the amount of $62,482.66, broken down as follows: $51,848.07 in attorney’s fees and expenses; $6,031.26 in consultant fees; $3114.18 for project fees (a scale model); $528.78 for photographs of exhibitry; and $960.37 for trial transcripts. In the application, plaintiff contends that it was the prevailing party in the litigation on a unified claim, that it incurred the fees and expenses in bringing suit against the government, and that it was an eligible party under the Equal Access to Justice Act (hereinafter, EAJA) at the time the suit was filed. Plaintiff also alleges that the position of the United States was not substantially justified and that no special circumstances exist to warrant denial of an award.

The government, argues that D & P is not an eligible party under the EAJA and was not the prevailing party in all aspects of the litigation. The defendant also argues that the position of the government was substantially justified and that special circumstances do exist which would make an award unjust. The defendant finally argues that if, however, D & P is found to be an eligible, prevailing party, the court should segregate the claim into discrete issues and allocate fees accordingly.

DISCUSSION

Congress enacted the Equal Access to Justice Act to ensure that individuals with limited resources and small businesses would not be “deterred from seeking review of, or defending against, unreasonable government action because of the expense involved in securing vindication of their rights.” Gavette v. Office of Personnel Management, 808 F.2d 1456, 1459, (Fed.Cir.1986) (citing H.R.REP. No. 1418, 96th Cong., 2d Sess. 5, reprinted in 1980 U.S.CODE CONG. & ADMIN.NEWS 4953, 4984). The relevant provision of the EAJA is as follows:

[A] court shall award to a prevailing party other than the United States fees and other expenses ... incurred by that party in any civil action ..., brought by or against the United States in any court having jurisdiction of that action, unless the court finds that the position of the United States was substantially justified or that special circumstances would make an award unjust.

Equal Access to Justice Act, 28 U.S.C. § 2412(d)(1)(A) (1982 & Supp. V 1987).

At the same time, it was not intended by those enacting the EAJA that there be a mass subsidization of the costs of litigation to those easily able to afford legal services. The EAJA, therefore, included four threshold eligibility requirements which a party must meet in order to receive an award for fees and expenses:

(1) The party must be the “prevailing party” in the original action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hubbard v. United States
80 Fed. Cl. 282 (Federal Claims, 2008)
Hansen v. Deercreek Plaza, LLC
420 F. Supp. 2d 1346 (S.D. Florida, 2006)
Applegate v. United States
52 Fed. Cl. 751 (Federal Claims, 2002)
Baldi Bros. Constructors v. United States
52 Fed. Cl. 78 (Federal Claims, 2002)
Fields v. United States
39 Cont. Cas. Fed. 76,580 (Federal Claims, 1993)
Nicholson v. United States
29 Fed. Cl. 180 (Federal Claims, 1993)
United States v. Boeing Co., Inc.
747 F. Supp. 319 (E.D. Virginia, 1990)
Design & Production, Inc. v. United States
36 Cont. Cas. Fed. 75,907 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,844, 20 Cl. Ct. 207, 1990 U.S. Claims LEXIS 151, 1990 WL 49779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/design-production-inc-v-united-states-cc-1990.