Fields v. United States

39 Cont. Cas. Fed. 76,580, 29 Fed. Cl. 376, 1993 U.S. Claims LEXIS 162, 1993 WL 385702
CourtUnited States Court of Federal Claims
DecidedSeptember 30, 1993
DocketNo. 273-88C
StatusPublished
Cited by22 cases

This text of 39 Cont. Cas. Fed. 76,580 (Fields v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fields v. United States, 39 Cont. Cas. Fed. 76,580, 29 Fed. Cl. 376, 1993 U.S. Claims LEXIS 162, 1993 WL 385702 (uscfc 1993).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

Introduction

This case is now before the court on plaintiffs May 26, 1992 application for attorney fees in the amount of $22,831.00 under the Equal Access to Justice Act (EAJA), 28 U.S.C. § 2412 (1991 ed.), and defendant’s opposition thereto. Previously, in June 1991, following an appeal to this Court on May 6, 1988, from an adverse contracting officer’s decision on May 8, 1987, the defendant admitted liability, in part, for certain of plaintiff’s claims and thereby paid the plaintiff $4,400, plus interest. Thereafter, on April 17, 1992, the parties filed a joint stipulation for entry of judgment on the merits. Based upon the foregoing stipulation, on April 27,1992, the court entered judgment on the merits in favor of the plaintiff in the amount of $13,100, plus interest. Pursuant to the settlement agreement, plaintiff retained the right to pursue attorney fees under the EAJA.

As an initial matter, and to prevail, plaintiff as a party must show that he meets the following eligibility requirements of the EAJA:

(i) that an application for fees was filed within thirty (30) days of final judgment— (a) alleging that he was a prevailing party, (b) averring an amount sought, and (c) containing an itemized statement from an attorney stating actual time expended and the rate at which fees are charged (plaintiff must allege that defendant’s position was not substantially justified);

(ii) that plaintiff as a party individual or an unincorporated business had a net worth which did not exceed $2,000,000 and $7,000,000, respectively, at the time the civil action was filed (May 6, 1988);

(iii) that as such party, he incurred such fees in a civil action; and

(iv) that the unincorporated business, at the time of the filing of this action, did not have more than 500 employees.

If plaintiff establishes that he is eligible, defendant must then go forward and show that its position was substantially justified or that special circumstances exist which would make an award unjust, in order to preclude an EAJA award. 28 U.S.C. § 2412(d)(1)(B) and Pierce v. Underwood, 487 U.S. 552, 565, 108 S.Ct. 2541, 2550, 101 L.Ed.2d 490 (1987). Failing such by the defendant, the final step in the analysis is the determination of the amount of the award. After a careful review of the submissions of the parties, the court is constrained to deny plaintiff’s application for failure to sufficiently establish eligibility.1

Facts

On September 14, 1984, plaintiff Ed Fields was awarded contract No. 53-04N7-[378]*3784-56 by the United States Forest Service, United States Department of Agriculture (Forest Service), to provide site preparation services for 18 acres of land, which was the proposed site of a seed orchard. Work under the contract included the removal of existing trees, brush, and stumps, most of which were to be burned. The contract also required ripping, leveling, surface disking, and cover crop seeding. The contract was modified four times based upon a specification change therein, additional work, and alterations in the contract price caused by reduction in work performed.

There were differing opinions between plaintiff and the contracting officer as to expenses plaintiff claimed to have incurred in connection with the contract modifications. Plaintiff was to remove all rocks, eight inches or larger, which were found on 30% of the total acreage. However, after commencing the rock removal process, plaintiff alleged that he found and removed rocks eight inches (8") or larger on the entire site. Thus, plaintiff claimed that he was owed an additional $22,010, the cost of removing the extra rocks, the rerip-ping of an area, and the additional work done on .72 of an acre. In addition to the foregoing, plaintiff claimed expenses of $1,384 for the cost of an on-site 1,500-gallon water tank truck, and $5,200 for the added expense of carrying out all burning activities at night. The record shows that the presence of the truck and night burning were both requirements of the District Fire Management Officer. Finally, plaintiff also alleged that he was wrongfully denied the full contract price for disking and seeding, and other additional work.

The contracting officer issued his final decision, regarding plaintiffs claims, on May 8, 1987, awarding to plaintiff $1,710 for removal of the extra rocks, and $1,750 of the $5,650 requested for the additional work performed. The claims regarding the truck rental, the night burning, and the balance of the contact price for disking and seeding were all denied. Plaintiffs additional award of $3,460 by the contractor was reduced to $1,612.62 due to an alleged overpayment for the seeding.

Within one year after the contracting officer’s decision on May 8, 1987, plaintiff filed an appeal to the U.S. Claims Court2 on May 6, 1988, requesting payment of $34,241.03, the difference between the claim for damages submitted to and the amount allowed by the contracting officer. The government originally denied any and all liability in its answer filed on July 5, 1988. Thereafter, the parties filed a joint preliminary status report averring that both parties wished to conduct discovery. The court ordered discovery on August 19, 1988, which was to be completed on or before December 2, 1988. Following thereon, preliminary offers were made and rejected by both plaintiff and defendant. In fact, the parties agreed to settle all claims for $17,500 on May 23, 1989, which was inclusive of all fees and costs. However, five months later, on October 17, 1989, the government’s attorney informed the plaintiff that he was unable to secure approval by his superior of the proposed settlement. Shortly thereafter, on November 7, 1989, the government served on plaintiff Defendant’s Offer of Judgment in the amount of $12,600, inclusive of attorney fees and costs, which, of course, was not accepted. Plaintiff failed to file this Offer of Judgment with the Clerk of the Court.

Approximately three and one-half (3V2) months later, on February 23, 1990, defendant filed a motion for summary judgment, which took approximately nine (9) months to fully brief. Plaintiff filed his opposition on July 31, 1990, and the defendant’s reply brief was filed on November 6, 1990. On November 7, 1990, the government filed Defendant’s Amended Proposed Findings of Uncontroverted Fact, in which some of plaintiff’s claims were conceded.

On November 19, 1990, the court held a status conference and, the next day, entered an order directing the parties to exchange written settlement proposals. De[379]*379fendant, on February 26, 1991, withdrew its summary judgment motion without prejudice, and thereafter moved to proceed with discovery. Requests for production of documents were served, and the documents requested were produced by both sides in late 1991. In June 1991, plaintiff received a check for $4,400, plus interest, for additional claims to which the defendant conceded in part.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Q Integrated Companies, LLC v. United States
133 Fed. Cl. 479 (Federal Claims, 2017)
Brass v. United States
129 Fed. Cl. 160 (Federal Claims, 2016)
Hyperion, Inc. v. United States
118 Fed. Cl. 540 (Federal Claims, 2014)
Gate Guard Services L.P. v. Perez
14 F. Supp. 3d 825 (S.D. Texas, 2014)
Watterson Construction Co. v. United States
106 Fed. Cl. 609 (Federal Claims, 2012)
Metropolitan Van & Storage, Inc. v. United States
101 Fed. Cl. 173 (Federal Claims, 2011)
Impresa Construzioni Geom. v. United States
93 Fed. Cl. 733 (Federal Claims, 2010)
Information Sciences Corp. v. United States
86 Fed. Cl. 269 (Federal Claims, 2009)
Sosebee v. Astrue
494 F.3d 583 (Seventh Circuit, 2007)
Asphalt Supply & Service, Inc. v. United States
75 Fed. Cl. 598 (Federal Claims, 2007)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Lion Raisins, Inc. v. United States
57 Fed. Cl. 505 (Federal Claims, 2003)
Doe v. United States
54 Fed. Cl. 337 (Federal Claims, 2002)
Mantle Ranches, Inc. v. United States Park Service
993 F. Supp. 1335 (D. Colorado, 1998)
United States v. 819.98 Acres of Land
133 F.3d 933 (Tenth Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,580, 29 Fed. Cl. 376, 1993 U.S. Claims LEXIS 162, 1993 WL 385702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fields-v-united-states-uscfc-1993.