Orlosky Inc. v. United States

68 Fed. Cl. 296, 2005 U.S. Claims LEXIS 305, 2005 WL 2850811
United States Court of Federal Claims·Decided October 24, 2005·No. No. 01-634C·Published·Cited by 18 cases

Opinion

OPINION

CHRISTINE O.C. MILLER, Judge.

Only by barge or plane can one make his way to a small island miles off the coast of Southern California. Far from the scenic coast that is Point Mugu, California — no preaward site visit tainted the contractor’s perception — on the isolated island of San Nicolas, a constant influx of fog, cool temperatures, and high sustained winds adds to the challenge for those who call the U.S. Naval Air Weapons Station at San Nicolas Island home. Plaintiffs owner is one who wishes that an extended stay had not been required.

The United States Department of the Navy (the “Navy”) awarded Contract No. N62474-95-C-4778 to Orlosky Inc. (“plaintiff’) on November 8, 1995, to perform electrical work on the island. The work involved replacing high-voltage safety equipment and re-coordinating the electrical mapping of the island in response to the various additions and changes that had taken place since the last coordination. The contract, as modified, ultimately contemplated a two-hundred-day project for a fixed price of $240,118.72, and bidders were obliged to visit the island to see the local conditions before bidding on the contract. Plaintiff failed to do so — at its peril — and received the contract; therefore, upon defendant’s summary judgment motion, plaintiff lost its differing site conditions claim insofar as it was based on anything that would have been discoverable on the site inspection. See Orlosky Inc. v. United States, 64 Fed.Cl. 63 (2005) (order granting in part and denying in part motion for summary judgment).

Plaintiff proceeded to try claims for delay, breach of warranty of specifications, and breach of the covenant of good faith and fair dealing, for which plaintiff sought recovery in the amount of $565,481.00. Trial succeeded in diverting the focus away from plaintiffs pre-bid failures to the Navy’s mistreatment of a small contractor mired in a difficult situation. The acts that plaintiff proved at trial, with assistance due to the illuminating candor demonstrated by certain defense witnesses, strike at the heart of the Navy’s duties to deal fairly with its contractor, and the law affords relief for this kind of breach. Plaintiff also recovers on other claims, though not to the extent that it had hoped.

The factual background that follows, and the facts explicated in more detail in the subsequent legal discussion, constitute findings of fact based on this court’s consideration of all documentary evidence and its assessments of each fact and expert wit[299] nesses.1

FACTUAL AND PROCEDURAL BACKGROUND

Plaintiff Orlosky Inc. is a corporation organized under the laws of Nevada. It was created by Joseph R. Orlosky and his colleagues in or around late 1994 for the purpose of obtaining military construction contracts from the United States Navy.

San Nicolas Island is one of the California Channel Islands off the coast of Point Mugu. It is part of the U.S. Naval Weapons Center at Point Mugu, used for missile tests and warfare training because of its isolated environment and shoreline characteristics. The island has a high-voltage electrical system, including a grid of high-voltage power lines, supplying power to the various structures. The addition of new buildings requires modification of the electrical system because each structure receives electricity from what is referred to as a single-line system. As changes are made to the power use, the overall electrical system must be modified to keep pace with the actual use. These upgrades included the completion of a “coordination study,” which Mr. Orlosky described as “a study of a system that could consist of more than one leg of a ... high voltage network whereby the study would reveal the loads at different points throughout the system and certain curves of surge throughout the system.” Transcript of Proceedings, Orlosky Inc. v. United States, No. 01-634C, at 18 (Fed. Cl. June 13-17, 2005) (“Tr”).

Because San Nicolas Island required a new coordination study, the Navy issued Solicitation No. N62474-95-B-4778 on July 7, 1995, for that purpose. The solicitation also required the contractor to replace several, but not all, of a certain type of electrical equipment used on the island called reclosers. Reclosers operate essentially as high-voltage circuit breakers, responding automatically to surges or other electrical problems by shutting off the electricity. As explained by Mr. Orlosky,

It opens and closes and to shut off. [L]et’s say you have a short circuit, someone runs into a telephone pole or runs into a transformer and shorts out the transformer down stream the micro-processor will surge the increase in amperage. It will send a signal to disconnect the recloser for a moment and then it kicks it back on to see of there’s another surge and it will do this many times depending on how you program it.

Tr. at 170-71. The equipment includes a cooling tank filled with oil, a microprocessor, insulator pins jutting out from the top for the incoming and outgoing voltage, and, among other internal parts, a transformer. Power comes in from the generator through the transformer into the recloser. While the reclosers to be replaced did not have a microprocessor, the new version did.

The solicitation made available to bidders the specifications and various plans and drawings for use in preparation of the bids. It also provided bidders with an opportunity to conduct a pre-bid site visit to San Nicolas Island, which was scheduled for July 26, 1995. Six bidders attended the site visit, but plaintiff was not one of them.2

[300] Bidding opened on August 8, 1995, and plaintiff and six others submitted bids. Although plaintiffs bid of $240,118.11 was not the lowest, the Navy rejected the lower bidders and awarded the contract to plaintiff on November 8,1995, for its full bid amount. A letter of that date informed plaintiff of its award and directed plaintiff to proceed under the contract. The Navy required a performance bond in the amount of the bid and a payment bond for half that amount. The contract completion date was set for March 25, 1996 — a date that incorporated an eighty-day extension to the original project duration under an amendment to the solicitation executed July 26,1995. Shortly after award, the completion date again was extended to June 11,1996.

The contract required plaintiff to prepare a construction schedule within fifteen days of award and an equipment delivery schedule within twenty-one days of award. Contract § 01010, ¶¶ 1.20.2.1 & .2. The original schedule plaintiff submitted, stated that plaintiff would finish the job by March 25,1996.

Plaintiff also had to submit a quality control plan within thirty days after receipt of the notice of award. Because of the location of the work, the Navy provided plaintiff with transportation to and from the island, both for plaintiffs personnel and for its equipment. The equipment had to be barged out to the island, and personnel were transported in passenger aircraft. Plaintiff was responsible for arranging the transport of its equipment, following the Navy’s barge schedules.

Free access — add to your briefcase to read the full text and ask questions with AI

Orlosky Inc. v. United States, 68 Fed. Cl. 296, 2005 U.S. Claims LEXIS 305, 2005 WL 2850811 (uscfc 2005).

68 Fed. Cl. 296 (Orlosky Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
Linda Rugina Company D/B/A Ruginas Afrikan Village
Armed Services Board of Contract Appeals, 2020
Starwalker PR LLC
Armed Services Board of Contract Appeals, 2020
Electric Boat Corporation
Armed Services Board of Contract Appeals, 2019
SKE Base Services GmbH
Armed Services Board of Contract Appeals, 2018
BAE Systems San Francisco Ship Repair
Armed Services Board of Contract Appeals, 2016
H. J. Lyness Construction, Inc. v. United States
121 Fed. Cl. 287 (Federal Claims, 2015)
Reema Consulting Services, Inc. v. United States
107 Fed. Cl. 519 (Federal Claims, 2012)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
JGB Enterprises, Inc. v. United States
83 Fed. Cl. 20 (Federal Claims, 2008)
Oak Environmental Consultants, Inc. v. United States
77 Fed. Cl. 688 (Federal Claims, 2007)
Axion Corp. v. United States
75 Fed. Cl. 99 (Federal Claims, 2007)