Nicon, Inc. v. United States

331 F.3d 878, 2003 U.S. App. LEXIS 11498, 2003 WL 21339165
CourtCourt of Appeals for the Federal Circuit
DecidedJune 10, 2003
Docket02-5097
StatusPublished
Cited by43 cases

This text of 331 F.3d 878 (Nicon, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nicon, Inc. v. United States, 331 F.3d 878, 2003 U.S. App. LEXIS 11498, 2003 WL 21339165 (Fed. Cir. 2003).

Opinions

Opinion for the court filed by Circuit Judge CLEVENGER. Opinion concurring in part filed by Circuit Judge PAULINE NEWMAN.

CLEVENGER, Circuit Judge.

Nicon, Inc., seeks damages for unabsorbed home office overhead resulting from a delay period between award of a government contract and termination for convenience, during which the government never issued a notice to proceed and Nicon was allegedly forced to remain on “standby.” On cross-motions for summary judgment, the Court of Federal Claims granted the government’s motion, holding that Ni-con could not recover damages for unabsorbed home office overhead under the Eichleay formula because the formula could not be modified to fit a fact situation where the contractor has not yet begun to perform. Nicon, Inc. v. United States, 51 Fed.Cl. 324 (Fed.Cl.2001). We vacate the summary judgment in favor of the government and remand for further proceedings to determine if Nicon may recover unabsorbed overhead damages as part of its termination for convenience settlement by some other method of allocation.

I

Nicon is a small contractor from Tampa, Florida. On March 30, 1998, the Department of the Army, Mobile District Corps of Engineers, awarded Nicon a $1.4 million contract to repair Dorm 371 at MacDill Air Force Base in Hillsborough County, Florida. On April 3, 1998, a disappointed bidder filed a bid protest, which suspended action on the contract before any of the repair work was commenced. On April 24, 1998, the government notified Nicon of the protest and instructed it to “take no further actions as to the preparation and forwarding of submittals to the Resident Office.” Nicon responded immediately, informing the government that it would “cease any further mobilization efforts associated with the ... project.”

The bid protest was dismissed on July 15, 1998, but the government never directed Nicon to proceed with the contract. On October 14, 1998, Nicon wrote a letter to the government to complain about the delay in issuing the notice to proceed and apparently received no response. Nicon wrote again to request permission to proceed on November 12, 1998, but the government still failed to issue a notice to proceed. After this second letter, Nicon met with government representatives to discuss revised pricing for the contract. However, the government then terminated the contract for convenience on January 12, 1999. This termination occurred before the government ever issued a notice to proceed and before Nicon secured payment and performance bonds for the contract. A period of 107 days elapsed between the March 30, 1998, award of the contract to Nicon and the July 15, 1998, dismissal of the bid protest, and another [882]*882181 days (for a total of 288 days) elapsed thereafter before the government’s termination of Nicon’s contract for convenience on January 12, 1999.

After the termination, Nicon submitted a Termination Settlement Proposal to the government. In the proposal, it sought direct costs and associated overhead and profit, as well as unabsorbed home office overhead for the time period between award of the contract and termination. As an allocation method, Nicon used a modified version of the Eichleay formula to calculate its unabsorbed home office overhead damages. After negotiation, Nicon was awarded $184,757 in direct costs, related overhead, and profit. However, the contracting officer denied Nicon’s claim for $387,513 in unabsorbed home office overhead for the 288-day alleged delay period.

Nicon then filed suit in the Court of Federal Claims to recover the unabsorbed overhead damages it had sought in its termination settlement proposal and which the contracting officer had denied. Its complaint contained two counts: Count I was for pre-termination delay damages, and Count II was for post-termination delay damages. Upon cross-motions for summary judgment as to Count I, the Court of Federal Claims granted summary judgment in favor of the government, concluding that Nicon was seeking to apply an alternative to the accepted Eichleay formula and that it could not modify the formula as Nicon requested. The Court of Federal Claims later granted Nicon’s motion to dismiss Count II.

Nicon appeals the Court of Federal Claims’s decision, and we have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

II

This appeal is from the Court of Federal Claims’s grant of summary judgment in favor of the government. We review a grant of summary judgment by the Court of Federal Claims de novo, Gump v. United States, 86 F.3d 1126, 1127 (Fed.Cir.1996), drawing all factual inferences in favor of the nonmovant, Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

In the course of performance of any contract, a contractor incurs both direct and indirect costs. Direct costs are those costs that are directly attributable to the performance of a specific contract and can be traced specifically to that contract. Charles G. Williams Constr., Inc. v. White, 271 F.3d 1055, 1057-58 (Fed.Cir.2001). Indirect costs include such things as home office overhead, defined as costs “that are expended for the benefit of the whole business, which by their nature cannot be attributed or charged to any particular contract.” Altmayer v. Johnson, 79 F.3d 1129, 1132 (Fed.Cir.1996). Generally, a contractor recovers these indirect costs by allocating a proportionate share to each of its contracts. C.G. Williams, 271 F.3d at 1058. However, when the government causes a delay or suspension of performance, this “decreases the stream of direct costs against which to assess a percentage rate for reimbursement.” C.B.C. Enters., Inc. v. United States, 978 F.2d 669, 671 (Fed.Cir.1992). In such a situation, a portion of the home office overhead is “unabsorbed.”

The Eichleay formula is used to “equitably determine allocation of unabsorbed overhead to allow fair compensation of a contractor for government delay.” Wickham Contracting Co. v. Fischer, 12 F.3d 1574, 1578 (Fed.Cir.1994). The formula, which was originally set forth by the Armed Services Board of Contract Appeals in Eichleay Corp., 60-2 B.C.A. (CCH) ¶ 2688, at 13,568 (A.S.B.C.A. July 29, 1960), determines a contractor’s dam[883]*883ages for unabsorbed home office overhead using three steps:

(1) (Contract billings Total billings for contract period) Total overhead for contract period = Overhead alloca-ble to the contract
(2) Allocable overhead Days of performance = Daily contract overhead
(3) Daily contract overhead Days of delay = Amount recoverable

Capital Elec. Co. v. United States, 729 F.2d 743

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D-STAR Engineering Corp.
Armed Services Board of Contract Appeals, 2025
Targe Logistic Services Company
Armed Services Board of Contract Appeals, 2024
GSI Construction Corp.
Armed Services Board of Contract Appeals, 2024
Fluor Intercontinental, Inc.
Armed Services Board of Contract Appeals, 2022
Aclr, LLC v. United States
Federal Claims, 2021
Matcon Diamond, Inc.
Armed Services Board of Contract Appeals, 2020
4H Construction Corporation
Armed Services Board of Contract Appeals, 2019
2Connect W.L.L.
Armed Services Board of Contract Appeals, 2017
Deas Construction, Inc.
Armed Services Board of Contract Appeals, 2016
Rex Systems Inc.
Armed Services Board of Contract Appeals, 2016
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)
Pros Cleaners
Armed Services Board of Contract Appeals, 2015

Cite This Page — Counsel Stack

Bluebook (online)
331 F.3d 878, 2003 U.S. App. LEXIS 11498, 2003 WL 21339165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nicon-inc-v-united-states-cafc-2003.