Interstate General Government Contractors, Inc. v. Togo West, Secretary of the Army

12 F.3d 1053, 39 Cont. Cas. Fed. 76,599, 1993 U.S. App. LEXIS 31585, 1993 WL 498936
CourtCourt of Appeals for the Federal Circuit
DecidedDecember 6, 1993
Docket92-1430
StatusPublished
Cited by74 cases

This text of 12 F.3d 1053 (Interstate General Government Contractors, Inc. v. Togo West, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Interstate General Government Contractors, Inc. v. Togo West, Secretary of the Army, 12 F.3d 1053, 39 Cont. Cas. Fed. 76,599, 1993 U.S. App. LEXIS 31585, 1993 WL 498936 (Fed. Cir. 1993).

Opinion

MICHEL, Circuit Judge.

Interstate General Government Contractors, Inc. (IGGC) appeals from a decision of the Armed Services Board of Contract Appeals (Board) denying IGGC’s claim for an equitable adjustment for alleged unabsorbed home office overhead caused by the government’s delay in issuing a notice to proceed (NTP) on a contract to renovate army barracks. Interstate Gen. Gov’t Contractors, Inc., ASBCA No. 43369, 92-2 BCA ¶ 24,956, 1992 WL 59384 (March 17, 1992). The Board first held that IGGC was not entitled to recover pursuant to the Eichleay formula, 1 its sole theory of recovery, because it failed to prove, as required by Eichleay, that it was “standing by” awaiting the NTP. Although the Board applied an incorrect legal test concerning standing by, the Board’s ultimate decision denying recovery is affirmable on its second holding, that IGGC, which finished early, completely failed to prove that it incurred any costs for home office overhead that were not absorbed by the payments of direct costs during the original performance period.

BACKGROUND

IGGC entered, into contract number DAKF10-89-C-0472 on September 29, 1989 to repair/replace heating, ventilation, and air conditioning piping in Pinwheel Barracks at Hunter Army Airfield, Georgia. The contract specified that “[t]he contractor shall begin performance within 10 calendar days and complete within 472 calendar days after receipt of the notice to proceed.” Interstate Gen., 92-2 BCA ¶ 24,956 at 124,364,1992 WL 59384. The contract also contained a standard protest clause pursuant to 48 C.F.R. § 52.233-3 (1985) providing authority for the contracting officer (CO),to issue a stop-work order if a bid protest were filed, and for an equitable adjustment to the contractor if a stop-work order resultéd in increased performance time or cost.

The government conceded that under normal circumstances, the NTP would have issued about October 16, 1989. Interstate Gen., 92-2 BCA ¶ 24,956-at 124,365, 1992 WL 59384. However, IGGC was notified by letter from the CO on October 13,1989 that due to a bid protest, the NTP would be withheld pending a final decision thereon. Id. The Board found that during pendency of the protest IGGC was expected by the CO to “remain ready to commence performance within a ‘reasonable time’ after the decision was rendered.” Id.

The bid protest was dismissed on February 16, 1990. The NTP issued on March 1, 1990, with instructions for IGGC to begin performance within ten calendar days and to •complete the work within 472 calendar days Of issuance of the NTP. IGGC completed performance in 323 calendar days after issuance of the NTP. Therefore, the contract was completed 459 days after October 16, 1989, the date that the NTP would have issued had there been no bid protest. Consequently, completion occurred within the originally-agreed on performance period which would have applied had no delay occurred.

On January 23, 1991, IGGC filed a claim with the CO for $24,749.11 in unabsorbed home office overhead it alleged was caused by the government delay, arguing that the notice of October 13, 1989 constituted a constructive stop-work order under the protest clause. Unabsorbed overhead calculated ac *1056 cording to the Eichleay formula was claimed, but direct costs were not. IGGC submitted letters from its insurance agent, stating that IGGC had reached its bonding capacity with the performance and payment bonds for the barracks contract, precluding it from bidding on any additional contracts during the pen-dency of the protest. Id. The letters further stated that the bonding' company refused to increase IGGC’s bonding capacity and would not have looked favorably on it accepting unbonded work. Id. IGGC’s Vice-President and' General Manager, Mr. Christiansen, testified that during the delay, “none of IGGC’s workers were idle, that two laborers hired for this job were let go while other workers Svere shuttled on to other jobs,’ and that the superintendent, who was standing by ready to start, was ‘reassigned other duties on-another job.’” Id.

The CO issued a final decision denying IGGC’s claim on July 29, 1991. IGGC appealed the denial of its unabsorbed overhead claim to the Board.

The Board found that the CO’s October 13, 1989 letter was tantamount to a stop-work order and “[ajccordingly, IGGC [was] entitled to an equitable adjustment for unabsorbed overhead during the protest period upon its carrying its burden of. proof that damages were incurred.” Id. at 124,367, 1992 WL 59384. The Board, however, found that IGGC failed to make a prima facie showing that it was on “standby” due to the government delay, noting that “IGGC’s work force was gainfully working at other jobs and not standing by awaiting the NTP.” Id. The Board held that “[t]he record [did] not support IGGC’s contention [that] it was incurring unabsorbed overhead during the period of the stop-work order.” Id.

IGGC' appealed to this court pursuant to the Contract Disputes Act of 1978, 41 U.S.C. § 607(g)(1)(A) (1988). Our jurisdiction rests on that Act and 28 U.S.C. § 1295(a)(10) (1988).

ANALYSIS

I.

IGGC argues on appeal that the Board applied an incorrect legal standard regarding standby, and therefore, wrongly held it was not entitled to recovery under Eichleay. The Board found that IGGC was not on standby because the work force on the particular contract was reassigned to other work or let go. Interstate Gen., 92-2 BCA ¶ 24,-956 at 124,367, 1992 WL 59384. Therefore, there were no contract workers “standing by” during the delay period. .

Only after the Board’s decision in this case did this court decide C.B.C. Enterprises, Inc. v. United States, 978 F.2d 669 (Fed.Cir.1992), clarifying the applicable tests. Thus, although the Board did apply the wrong test, its confusion is understandable. The court generally stated that applying the Eichleay formula is appropriate “provided that com-pensable delay occurred; and that the contractor could not-have taken on any other jobs during the contract period.” Id. at 673-74 (citing Capital Elec. Co. v. United States, 729 F.2d 743, 745-46 (Fed.Cir.1984)). C.B.C. specifically acknowledged .two prerequisites to application of the Eichleay formula to recover unabsorbed overhead, assuming government-caused and hence “compensable” delay: (1) that the contractor be on standby 2 and (2) that the contractor be unable to take on other work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hang Zhang v. Daniel Driscoll
N.D. California, 2025
(PC) Jackson v. Quick
E.D. California, 2024
Speedway Orion JV
Armed Services Board of Contract Appeals, 2023
Malekar v. Birley
N.D. California, 2023
Carley v. Warden Neven
D. Nevada, 2023
Solis v. City of Sunnyvale
N.D. California, 2020
Dorsey v. Paramo
S.D. California, 2020
Skylstad v. State of Washington
W.D. Washington, 2020
Bent v. Barr
N.D. California, 2020
Madden v. United States
D. Arizona, 2020
Matcon Diamond, Inc.
Armed Services Board of Contract Appeals, 2020

Cite This Page — Counsel Stack

Bluebook (online)
12 F.3d 1053, 39 Cont. Cas. Fed. 76,599, 1993 U.S. App. LEXIS 31585, 1993 WL 498936, Counsel Stack Legal Research, https://law.counselstack.com/opinion/interstate-general-government-contractors-inc-v-togo-west-secretary-of-cafc-1993.