InterCon Construction, Inc. v. TEAM Industrial Services, Inc.

CourtDistrict Court, N.D. Iowa
DecidedNovember 4, 2022
Docket6:18-cv-02081
StatusUnknown

This text of InterCon Construction, Inc. v. TEAM Industrial Services, Inc. (InterCon Construction, Inc. v. TEAM Industrial Services, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
InterCon Construction, Inc. v. TEAM Industrial Services, Inc., (N.D. Iowa 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF IOWA EASTERN DIVISION

INTERCON CONSTRUCTION, INC.,

Plaintiff, Case No. 18-CV-2081-KEM

vs. FINDINGS OF FACT, TEAM INDUSTRIAL SERVICES, CONCLUSIONS OF LAW, AND INC., ORDER FOR JUDGMENT

Defendant. ____________________

Table of Contents I. FINDINGS OF FACT ......................................................................................................... 2 II. CONCLUSIONS OF LAW ................................................................................................ 19 A. Breach of Contract ........................................................................................................ 20 B. Damages ......................................................................................................................... 24 C. Contractual Indemnification ........................................................................................ 30 III. CONCLUSION .................................................................................................................. 31

Plaintiff InterCon Construction, Inc., brought suit against Defendant TEAM Industrial Services, Inc., for breach of contract and contractual indemnification under Iowa law. Doc. 1. InterCon’s claims stem from a procedure performed by TEAM on a natural gas construction project that initially failed, but that TEAM later completed with success. The parties consented to the exercise of jurisdiction by a United States magistrate judge (Doc. 13), and I held a week-long bench trial on the claims. I find for InterCon on the breach-of-contract claim and for TEAM on the contractual indemnification claim and award InterCon $14,359.01 in damages. I. FINDINGS OF FACT1 InterCon contracted with Northern Natural Gas Company (NNG) in May 2016 to remove and install underground pipes for natural gas. Doc. 50. The scope of work included a “hot tap and line stop,” and InterCon had to secure an NNG-approved company to perform this work. Ex. 1 at 37. Generally speaking, a “hot tap” involves cutting into an active natural gas pipeline, and a “line stop” involves diverting gas from an active gas pipeline to a bypass pipe, so that work can be performed on the now inactive portion of the pipeline without stopping the flow of gas to its destination. See Doc. 50. The contract between NNG and InterCon provided that InterCon would begin construction once NNG issued a “notice to proceed” and that the “substantial completion date” for the work was August 8, 2016. Ex. 1 at 7, 37. Under the contract, InterCon could submit “change orders” for additional payment for delays “solely attributable” to NNG, but NNG would not compensate InterCon for avoidable delays. Id. at 15, 35. The contract contained a time-is-of-the-essence clause, generally providing that InterCon would perform the work “regularly, diligently, and uninterruptedly at such rate of progress” to meet the substantial-completion date. Id. at 10. NNG did not issue the notice to proceed until more than a year later, in November 2017. Ex. 36. InterCon informally secured TEAM to perform the hot tap and line stop work around that same time. Ex. 34. InterCon subcontracted the hot tap and line stop

1 After a bench trial, “the court must find the facts specially and state its conclusions of law separately.” Fed. R. Civ. P. 52(a)(1). The following findings are based on plaintiff’s burden of proving its claims by a preponderance of the evidence. Holliday v. Rain & Hail L.L.C., 690 N.W.2d 59, 64 (Iowa 2004); see also Lynch v. Travelers Indem. Co., 452 F.2d 1065, 1068 n.2 (8th Cir. 1972) (“In diversity actions, the burden of proof, as a substantive matter, is controlled by state law.”). “A preponderance of the evidence is the evidence ‘that is more convincing than opposing evidence’ or ‘more likely true than not true.’ It is evidence superior in weight, influence, or force.” Martinek v. Belmond-Klemme Cmty. Sch. Dist., 772 N.W.2d 758, 761 (Iowa 2009) (citations omitted) (quoting Holliday, 690 N.W.2d at 63-64). work to TEAM pursuant to a December 4, 2017 subcontract. Doc. 50;2 Ex. 5. The subcontract contained a flow-down clause, binding TEAM to the same obligations to NNG in the prime contract as InterCon. Ex. 5 at 1. Both the prime contract and subcontract provided that TEAM’s work included a double line stop with bypass piping. Ex.1 at 37; Ex. 5 at 2. The subcontract also noted TEAM’s contractual obligations included “[a]ny remedial work necessary or required to bring the Work into compliance with the Contract documents.” Ex. 5 at 3. The subcontract did not provide that TEAM had to complete the work in a specific amount of time—indeed, it gave TEAM fifteen “calendar day(s) after notification by [InterCon] to commence its operations.” Id. at 4. It did state, however, that TEAM had to “completely and satisfactorily perform the Work in accordance with the Schedule, as defined below” (the subcontract did not later define schedule); that TEAM had to perform “in a proper, efficient and workmanlike manner”; that TEAM must “prosecute the Work undertaken in a prompt and diligent manner whenever such Work, or any part of it, becomes available, . . . so as to promote the general progress of the entire construction”; that TEAM must not, “by delay or otherwise, interfere with or hinder the Work of [InterCon]”; and that TEAM “shall proceed diligently with the Work.” Id. at 2, 4, 10. The subcontract also contained a “time is of the essence” clause and noted TEAM agreed “to pay [InterCon] any actual and direct damage [InterCon] may sustain by reason of such delay by [TEAM].” Id. at 4. Both parties contractually waived the right to recover “special, indirect, punitive or consequential damages resulting from or arising out of [the subcontract], including, without limitation, loss of profit or business interruptions including loss or delay of operations, however caused” (this clause was bolded, underlined, and in all caps). Id. at 7. The subcontract indicated Iowa law controlled its interpretation. Id. at 10.

2 TEAM’s factual arguments contrary to the stipulation are not well-taken, and I find them waived. InterCon started the project on November 13, 2017, after NNG issued the notice to proceed. Ex. 36; Tr. 40-41.3 InterCon’s schedule when the project started provided that TEAM would begin working on December 4 and finish its part of the project on December 11 (with no work on Sunday, December 10). 4 Ex. 34, 87. The schedule provided TEAM with seven working days to complete the hot tap and line stop (TEAM’s bid estimated it would need to be on site five days to perform the work). Id. When TEAM completed its portion of the work, gas would flow through the new line and the project would be “substantially complete” (meaning the schedule set the substantial completion deadline for December 11). Ex. 87; Tr. 25-26, 91. The schedule set final completion for December 19, 2017, to allow InterCon seven working days to backfill and remove equipment. Ex. 87. On November 20, 2017, InterCon submitted a change order to NNG, requesting additional payment for three days’ worth of work based on “the workspace not being as long as shown on the bid documents.” Ex. 42. As a result, the new substantial completion date was December 13, 2017. Id. NNG denied the change-order request. Id. The next day, InterCon updated the schedule, noting “the bore” took “longer than originally anticipated.” Ex. 40; Tr. 24.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bockelman v. MCI Worldcom, Inc.
403 F.3d 528 (Eighth Circuit, 2005)
Lovlie v. Plumb
250 N.W.2d 56 (Supreme Court of Iowa, 1977)
Holliday v. Rain & Hail L.L.C.
690 N.W.2d 59 (Supreme Court of Iowa, 2004)
Molo Oil Co. v. River City Ford Truck Sales, Inc.
578 N.W.2d 222 (Supreme Court of Iowa, 1998)
Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
FIRST NAT. BANK IN CRESTON v. Smith
331 N.W.2d 120 (Supreme Court of Iowa, 1983)
Mel Frank Tool & Supply, Inc. v. Di-Chem Co.
580 N.W.2d 802 (Supreme Court of Iowa, 1998)
Estate of Pearson v. Interstate Power & Light Co.
700 N.W.2d 333 (Supreme Court of Iowa, 2005)
FNBC Iowa, Inc. v. Jennessey Group, L.L.C.
759 N.W.2d 808 (Court of Appeals of Iowa, 2008)
Magnusson Agency v. Public Entity National Co.-Midwest
560 N.W.2d 20 (Supreme Court of Iowa, 1997)
Kuehl v. Freeman Bros. Agency, Inc.
521 N.W.2d 714 (Supreme Court of Iowa, 1994)
Connie's Construction Co. v. Fireman's Fund Insurance Co.
227 N.W.2d 207 (Supreme Court of Iowa, 1975)
Midland Mutual Life Insurance Co. v. Mercy Clinics, Inc.
579 N.W.2d 823 (Supreme Court of Iowa, 1998)
Martinek v. Belmond-Klemme Community School District
772 N.W.2d 758 (Supreme Court of Iowa, 2009)
Nora Springs Cooperative Co. v. Brandau
247 N.W.2d 744 (Supreme Court of Iowa, 1976)
Mopper v. Circle Key Life Insurance Company
172 N.W.2d 118 (Supreme Court of Iowa, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
InterCon Construction, Inc. v. TEAM Industrial Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/intercon-construction-inc-v-team-industrial-services-inc-iand-2022.