Melka Marine, Inc. v. United States

187 F.3d 1370, 1999 U.S. App. LEXIS 18741, 1999 WL 607162
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 12, 1999
Docket16-1190
StatusPublished
Cited by36 cases

This text of 187 F.3d 1370 (Melka Marine, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Melka Marine, Inc. v. United States, 187 F.3d 1370, 1999 U.S. App. LEXIS 18741, 1999 WL 607162 (Fed. Cir. 1999).

Opinion

MICHEL, Circuit Judge.

Melka Marine, Inc. (“Melka”) appeals from the decision of the United States Court of Federal Claims, dismissing Mel-ka’s complaint which sought damages in connection with a waterfront construction contract awarded by the United States Department of the Navy. See Melka Marine, Inc. v. United States, 41 Fed.Cl. 122 (1998). After denying a motion and cross-motion for summary judgment, the Court of Federal Claims conducted a one-day trial on November 24, 1997. On June 10, 1998, the Court issued an opinion and order denying Melka’s claims in their entirety and dismissing Melka’s complaint. Mel-ka appeals, contending that it has proven it is entitled to damages stemming from government-caused delay between November 16, 1994 and March 30, 1995. Because the Court applied an incorrect test and Melka has shown that it may be entitled to recover at least some damages for a portion of the time period (if the correct test is used), we affirm-in-part, vacate-in-part, and remand for further proceedings in accordance with this opinion.

BACKGROUND

On October 17, 1994, the United States (the “government”), through the Department of the Navy, awarded Melka a contract that included dredging work in the Potomac River near Washington, DC, as well as the construction of a breakwater, repairs to an existing boat ramp, a quay-wall, and a finger pier, and various other repair work. The contract required the government to obtain a dredging permit from the United States Army Corps of Engineers prior to the commencement of the dredging and breakwater work, but not for the repair work.

On November 4, 1994, the government notified Melka that the permit had not yet been obtained, but was expected at any time. In the meantime, the government noted that no “dredge work can start until this permit is approved, however, construction repairs are not dependent on this permit.” Melka mobilized all of its equipment to the job site by November 15,1994.

On November 16, 1994, Melka sent a letter to the government stating that Mel-ka’s proposed schedule for completing the work, previously submitted, would be negatively impacted by the government’s failure timely to obtain a permit and that, as requested, it would re-sequence the work to avoid inactivity. The government did not respond to this letter. On November 21, Melka began the re-sequenced work by starting work on the boat ramp. Work was suspended the next day, however, due to the discovery of a six-inch pipe in the ramp and the discovery of a prior boat ramp beneath the existing ramp, which would necessitate a different ramp design.

As a result of these delays and the delay in obtaining a permit, on November 29 the government issued a formal “Suspension of Work” order. The order suspended the commencement of dredging and breakwater work “for an indefinite period.” Two days later on December 1, the government revised its “Suspension of Work” order. The letter stated in part:

The Corps of Engineers permit for this project is not expected to be approved until mid-January or mid-February. Therefore, all work relating to the dredging and breakwater repairs cannot begin until the permit is received.
Work may commence on the repairs to the quaywall and to the finger pier.... All equipment on site that will not be utilized on the repairs to the boat ramp, quaywall, or finger pier can be demobilized. Take any other steps necessary to minimize the incurrence of *1374 costs due to the suspension of permit related work.

By December 27, 1994, Melka had demobilized its dredging and breakwater equipment while it continued the re-sequenced repair work, which was substantially completed by January 4, 1995.

Melka later mobilized its dredging and breakwater equipment elsewhere for use on other jobs. The two most significant jobs that Melka undertook during this period were the Steuart Petroleum project from January 4-18, 1995, and the Leesyl-vania Park project from January 20, 1995 through March 31, 1995. Melka originally scheduled these jobs to be performed after the government project, but the government-imposed delay allowed Melka to perform these jobs earlier.

Melka also bid on other projects during this period which it did not receive, but that it would have been able to perform at some point had they been awarded the projects. Indeed, Leonard Melka testified that Melka bid upon "every project [that it] could find to bid on." Counsel for Melka also indicated at trial that Melka did not turn down any work that had been offered to it during the January time frame.

On February 2, 1995, the parties met to discuss the continuing delay in obtaining the permit. At the meeting, the government informed Melka that work on the dredging and breakwater, rather than commencing in February 1995, could not begin until October 15, 1995, and requested that it agree to perform this work under the original contract price. By letter dated February 14, 1995, Melka agreed and proposed a completion date of February 29, 1996. 1 All work was completed by February 1996.

On appeal, as below, Melka asserts that it is entitled to recovery of its unabsorbed overhead from November 16, 1994 through March 30, 1995. 2 We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3) (1994).

DISCUSSION

I.

We review legal conclusions of the Court of Federal Claims de novo, while its factual findings at trial are reviewed for clear error. See Harbert/Lummus Agrifuels Projects v. United States, 142 F.3d 1429, 1432 (Fed.Cir.1998).

Melka alleges that it is entitled to reimbursement of its unabsorbed home office overhead costs caused by the government's delay as calculated by the formula articulated in Eichleay Corp., ASBCA No. 5183, 60-2 BCA (CCH) 2688, 1960 WL 538 (1960). 3 The Eichleay for *1375 mula is the only means approved in our case law for calculating recovery for unabsorbed home office overhead. See E.R. Mitchell Constr. Co. v. Danzig, 175 F.3d 1369, 1372 (Fed.Cir.1999). Home office overhead typically includes accounting and payroll services, salaries for upper-level managers, general insurance, utilities, taxes, and depreciation. See Interstate Gen. Gov't Contractors, Inc. v. West, 12 F.3d 1053, 1058 (Fed.Cir.1993).

Melka must satisfy two requirements in order to show that it is entitled to Eichleay damages: (1) the government required the contractor to stand by during government-caused delay of indefinite duration; and (2) while and because of standing by, the contractor was unable to take on other work. Interstate, 12 F.3d at 1056.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
C.J. Mahan Construction Company
Armed Services Board of Contract Appeals, 2025
Speedway Orion JV
Armed Services Board of Contract Appeals, 2023
Alderman Building Company, Inc.
Armed Services Board of Contract Appeals, 2020
Matcon Diamond, Inc.
Armed Services Board of Contract Appeals, 2020
Relyant, LLC
Armed Services Board of Contract Appeals, 2018
Rex Systems Inc.
Armed Services Board of Contract Appeals, 2016
KBJ, Inc.
Armed Services Board of Contract Appeals, 2016
H. J. Lyness Construction, Inc. v. United States
121 Fed. Cl. 287 (Federal Claims, 2015)
Oak Environmental Consultants, Inc. v. United States
77 Fed. Cl. 688 (Federal Claims, 2007)
Orlosky Inc. v. United States
68 Fed. Cl. 296 (Federal Claims, 2005)
Broward County v. Brooks Builders, Inc.
908 So. 2d 536 (District Court of Appeal of Florida, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Jackson Construction Co. v. United States
62 Fed. Cl. 84 (Federal Claims, 2004)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
187 F.3d 1370, 1999 U.S. App. LEXIS 18741, 1999 WL 607162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/melka-marine-inc-v-united-states-cafc-1999.