Lee Masonry, Inc. v. City of Franklin, Tennessee Stansell Electric Company, Inc. v. City of Franklin, Tennessee

CourtCourt of Appeals of Tennessee
DecidedApril 28, 2010
DocketM2008-02844-COA-R3-CV
StatusPublished

This text of Lee Masonry, Inc. v. City of Franklin, Tennessee Stansell Electric Company, Inc. v. City of Franklin, Tennessee (Lee Masonry, Inc. v. City of Franklin, Tennessee Stansell Electric Company, Inc. v. City of Franklin, Tennessee) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lee Masonry, Inc. v. City of Franklin, Tennessee Stansell Electric Company, Inc. v. City of Franklin, Tennessee, (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE October 13, 2009 Session

LEE MASONRY, INC. v. CITY OF FRANKLIN, TENNESSEE STANSELL ELECTRIC COMPANY, INC. V. CITY OF FRANKLIN, TENNESSEE

Appeal from the Chancery Court for Williamson County No. 30483/31022 Timothy L. Easter, Judge

_________________________________

No. M2008-02844-COA-R3-CV - Filed April 28, 2010

Two trade contractors alleged that the City breached its contract with them by failing to take reasonable measures to guard against delays and disruptions by other contractors in the City’s coordination, management, and scheduling of the contractors and by failing to pay the retainages they were due. The contractors sought damages for the delays. The City raised three defenses: (1) the “no damages for delays” provision of the contracts; (2) untimely notice of claims by the contractors; and (3) the contractors’ acknowledgment and acceptance of time extensions without a reservation for increased compensation in the change orders they executed. The trial court concluded that all three of the City’s defenses failed and awarded damages to the contractors. We affirm the trial court’s decisions.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed

A NDY D. B ENNETT, J., delivered the opinion of the Court, in which F RANK G. C LEMENT, J R. and R ICHARD H. D INKINS, JJ., joined.

William N. Bates, Gregory L. Cashion, and Craig N. Mangum, Nashville, Tennessee, for the appellant, City of Franklin, Tennessee.

Todd E. Panther, Nashville, Tennessee, for the appellee, Lee Masonry, Inc.

Stafford F. McNamee, Jr., Brentwood, Tennessee, for the appellee, Stansell Electric Company, Inc. OPINION

F ACTUAL AND P ROCEDURAL B ACKGROUND

This is a contract dispute between two trade contractors, Lee Masonry, Inc. (“LMI”) and Stansell Electrical Company, Inc. (“SEC”), and the City of Franklin, Tennessee (“City”). The plaintiffs allege that the City breached its contract with them by failing to coordinate, manage, and schedule the various trade contractors on the Franklin Municipal Services Complex project by neglecting to take reasonable measures that would guard against delays and disruptions by other contractors and by failing to pay the retainages the plaintiffs were due.

LMI filed suit against the City on March 23, 2004; SEC filed suit on October 8, 2004. The City answered each suit denying the allegations and alleging that each plaintiff failed to satisfy contractual conditions precedent to obtaining any relief for delay and disruption. On November 1, 2004, the court entered an order to consolidate the two cases.1 A six-day trial took place in March 2008. In a detailed memorandum opinion dated August 8, 2008, the court made findings of fact, which are not in dispute.

Before construction on the project began, the City paid for a geotechnical exploration into the subsurface conditions of the construction site and received a report on February 11, 2002. The report addressed numerous problems with the soil, including wet soil and soil that was unsuitable for buildings. A portion of the site was designated wetland. The site work was delayed until approximately February 1, 2003, for a permit to be issued by the EPA to allow the project to go forward. The former City Manager and the Job Superintendent for Rock City, the City’s construction manager for the project, acknowledged that the location was a bad site. The trial court found that “[t]he soils were very porous, stayed wet, and there was bad soil virtually all over. The grading contractor ran into springs all over the site and french drains had to be constructed to get rid of the water.”

Rock City prepared a pre-bid schedule that established dates when certain jobs would be completed on certain buildings and served as a guide for the trade contractors while they bid on the project. According to the pre-bid schedule, masonry work was to begin March 18,

1 The City initially filed a third-party complaint against Rock City Construction Co., Inc., its construction manager on the project. The City alleged that because Rock City was its agent, any contractual duties that were owed to LMI or SEC that were breached by the City were a result of Rock City’s performance or non-performance of its duties to the City. The City voluntarily dismissed Rock City in September 2005. The City and Rock City collaborated at trial with the City’s acknowledgment that Rock City was its agent and the City was vicariously liable for everything Rock City did on the project.

-2- 2003, and be completed by June 16, 2003, while electrical work was to run from April 1, 2003, to August 22, 2003. The trial court found that “LMI and SEC based their entire forecast including bid pricing, manpower scheduling and substantial completion for this job on a Pre-bid Schedule.”

The trial court discussed the collaborative nature of construction projects. On a construction site, certain jobs must be completed before others may begin. This inevitably results in certain contractors waiting for others to finish before they can begin. A major draw to contractors working on this particular project was the fact that six different structures were being built at the same time, allowing the contractors to work around each other and minimize downtime. As the trial court found, “[t]his was conveyed to the trade contractors, and LMI and SEC relied on this incentive while developing their bids.”

On March 12, 2003, LMI entered into a contract with the City agreeing to perform all masonry work on the project for $271,300. On April 9, 2003, SEC entered into a contract with the City agreeing to perform all electrical work on the project for $650,000. The language of the two contracts is identical in all relevant and material aspects. Pursuant to Article 8 of the agreements, there were a number of other documents incorporated by reference, including but not limited to the Standard General Conditions of the Construction Contract (“General Conditions”) and the Specifications. All of the contract documents were prepared by the City and presented to LMI and SEC on a take-it-or-leave-it-basis.

The trial court determined that paragraphs 2.9 and 6.6 of the General Conditions and section 01310 of the Specifications require LMI and SEC to abide by a construction schedule prepared by the City. According to the trial court, the documents contemplate that the City would develop a fully integrated construction schedule before work on the project began. The General Conditions state that time is of the essence of the agreement. The trial court found that LMI and SEC “reasonably relied upon the City’s fulfillment of this obligation.” At the time of the agreements, the only schedule that existed was the pre-bid schedule.

The first contractor scheduled to begin work was Civil Construction Company (“Civil”). Civil started on time in February 2003 but immediately encountered problems with the soil. One problem was that the soil was too porous, a problem that the geotechnical report had uncovered. Another problem that delayed the project occurred when Civil mistakenly used the wrong technique in blasting an area designated for the solid waste transfer station, resulting in “overshot” rock. Civil was forced to dig up shattered, overshot rock and fill the area with usable soil before building on the site could commence. Civil was given extra time by the City to correct the mistake, and Rock City changed the schedule. Instead of starting on the solid waste transfer station, Rock City moved all work to the training center. By this point, the project was already well behind the pre-bid schedule. On

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brock & Blevins Company, Inc. v. The United States
343 F.2d 951 (Court of Claims, 1965)
Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
Nicon, Inc. v. United States
331 F.3d 878 (Federal Circuit, 2003)
Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
Estate of Walton v. Young
950 S.W.2d 956 (Tennessee Supreme Court, 1997)
Scholz v. S.B. International, Inc.
40 S.W.3d 78 (Court of Appeals of Tennessee, 2000)
Simonton v. Huff
60 S.W.3d 820 (Court of Appeals of Tennessee, 2000)
Stamp v. Honest Abe Log Homes, Inc.
804 S.W.2d 455 (Court of Appeals of Tennessee, 1990)
Allstate Insurance Co. v. Watson
195 S.W.3d 609 (Tennessee Supreme Court, 2006)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Buice v. Scruggs Equipment Co.
267 S.W.2d 119 (Court of Appeals of Tennessee, 1953)
Rogers v. First Tennessee Bank National Ass'n
738 S.W.2d 635 (Court of Appeals of Tennessee, 1987)
Coble Systems, Inc. v. Gifford Co.
627 S.W.2d 359 (Court of Appeals of Tennessee, 1981)
Jackson v. Miller
776 S.W.2d 115 (Court of Appeals of Tennessee, 1989)
Johnson v. Johnson
37 S.W.3d 892 (Tennessee Supreme Court, 2001)
Richland Country Club, Inc. v. CRC Equities, Inc.
832 S.W.2d 554 (Court of Appeals of Tennessee, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Lee Masonry, Inc. v. City of Franklin, Tennessee Stansell Electric Company, Inc. v. City of Franklin, Tennessee, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-masonry-inc-v-city-of-franklin-tennessee-stans-tennctapp-2010.