Servidone Construction Corporation, Plaintiff/cross-Appellant v. The United States

931 F.2d 860, 37 Cont. Cas. Fed. 76,082, 1991 U.S. App. LEXIS 6974, 1991 WL 61769
CourtCourt of Appeals for the Federal Circuit
DecidedApril 24, 1991
Docket90-5115, 90-5121
StatusPublished
Cited by123 cases

This text of 931 F.2d 860 (Servidone Construction Corporation, Plaintiff/cross-Appellant v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Servidone Construction Corporation, Plaintiff/cross-Appellant v. The United States, 931 F.2d 860, 37 Cont. Cas. Fed. 76,082, 1991 U.S. App. LEXIS 6974, 1991 WL 61769 (Fed. Cir. 1991).

Opinion

RADER, Circuit Judge.

Servidone Construction Corporation (Ser-vidone) encountered unexpected site conditions when building an earthen dam for the United States Army Corps of Engineers (the Corps). The United States Claims Court held the Corps liable for increased costs caused by site conditions. Servidone Constr. Corp. v. United States, 19 Cl.Ct. 346 (1990). This court affirms.

*861 BACKGROUND

The Claims Court presented thorough findings of fact. Servidone, 19 Cl.Ct. at 349-56. This opinion therefore supplies only a brief factual summary.

In September 1981, the Corps awarded Servidone a contract to construct an embankment, a spillway, outlet works, and several roads on an earthen dam near Dallas-Fort Worth. Servidone’s winning bid was $25,781,338.18.

Servidone began work in May 1982. Over the next two years, Servidone encountered many problems due to differing site conditions. After incurring costs well beyond its bid price, Servidone filed a certified claim for equitable adjustment of the contract on March 1, 1984. Servidone did not complete the contract work until August 1985.

On June 4, 1984, Servidone filed suit under the Contract Disputes Act (CDA), 41 U.S.C. § 609(a)(1) (1982), in the Claims Court. Servidone complained that the Coiqjs breached an implied duty to provide adequate information for contract performance (Type I differing site condition). Ser-vidone also complained that it encountered unusual soil conditions covered by the contract’s differing site condition clause (Type II differing site condition). Finally, Servi-done complained that the Corps caused delays by excessive quality assurance testing.

The Claims Court found the Government liable for Servidone’s increased costs caused by the Type II differing site condition. The Claims Court computed damages with the total cost method. Servidone, 19 Cl.Ct. at 384. The total cost method derives damages as the difference between a contractor’s actual costs and its original bid. Phillips Constr. Co. v. United States, 394 F.2d 834, 840 n. 8, 184 Ct.Cl. 249 (1968). The Claims Court determined that Servidone incurred $23,703,582.00 in costs above its estimated costs or bid. However, the Claims Court also found that Servidone bid too low. To compensate for Servidone’s unreasonably low bid, the trial court substituted a reasonable bid in the damages computation. This substitution reduced Servidone’s claimed costs by $9,262,459.00. These findings produced an award to Servidone of $14,441,123.00. The trial court awarded Servidone interest on this sum from the date the Government contracting officer received Servidone’s certified claim. The Claims Court rejected Servidone’s request for recovery of over $13 million in interest on borrowings to cover the additional performance costs.

On appeal, the Government questions both the damages and interest awards. On cross-appeal, Servidone questions the court’s substitution of a higher bid for Ser-vidone’s bid under the total cost method. Servidone also challenged the Claims Court’s denial of $13 million in interest on borrowings.

DISCUSSION

To receive an equitable adjustment from the Government, a contractor must show three necessary elements—liability, causation, and resultant injury. Wunderlich Contracting Co. v. United States, 351 F.2d 956, 968, 173 Ct.Cl. 180 (1965). Servidone presented causation evidence on three theories, one of which—the Type II differing site condition—the trial court sustained. This court discerns no basis for determining that the Claims Court clearly erred in this finding of liability.

To show the amount of injury, Servidone presented evidence under the total cost method. Servidone, 19 Cl.Ct. at 384. Under this method, the contractor must show: (1) the impracticability of proving actual losses directly; (2) the reasonableness of its bid; (3) the reasonableness of its actual costs; and (4) lack of responsibility for the added costs. WRB Corp. v. United States, 183 Ct.Cl. 409, 426 (1968). Although finding Servidone’s bid unreasonable, the Claims Court awarded damages. Servidone, 19 Cl.Ct. at 384-85. In doing so, the Claims Court employed a modified total cost method. This modified method substituted a reasonable bid amount for Servidone’s original estimate.

A trial court must use the total cost method with caution and as a last resort. Under this method, bidding inaccuracies *862 can unjustifiably reduce the contractor’s estimated costs. Moreover, performance inefficiencies can inflate a contractor’s costs. These inaccuracies and inefficiencies can thus skew accurate computation of damages. Despite this risk, this court's predecessor condoned the total cost method in those extraordinary circumstances where no other way to compute damages was feasible and where the trial court employed proper safeguards. Great Lakes Dredge & Dock Co. v. United States, 119 Ct.Cl. 504, 559, 96 F.Supp. 923, 926 (1951), cert. denied, 342 U.S. 953, 72 S.Ct. 624, 96 L.Ed. 708 (1952); Boyajian v. United States, 423 F.2d 1231, 1241, 191 Ct.Cl. 233 (1970).

The Claims Court found that Servidone met the four-part test and thus approved the total cost method in this case. Servidone, 19 Cl.Ct. at 384. The Claims Court granted Servidone a recovery under the modified total cost method:

[T]he total cost approach was used as “only a starting point" with such adjustments thereafter made in such computations as allowances for various factors as to convince the court that the ultimate, reduced, figure fairly represented the increased costs the contractor directly suffered from the particular action of defendant which was the subject of the complaint.

Boyajian, 423 F.2d at 1240 (citation omitted); see also, MacDougald Constr. Co. v. United States, 122 Ct.Cl. 210 (1952). The Claims Court modified the total cost method to account for Servidone’s bid inaccuracies. The Claims Court took extensive testimony to determine a reasonable bid amount. This court discerns no clear error in the trial court’s substitution of a reasonable amount for Servidone’s bid under the total cost method.

The Claims Court also considered the extent to which Servidone was responsible for added costs. Servidone, 19 Cl.Ct. at 386. In particular, the court considered Servidone’s inexperience with the highly plastic soils at the work site. The trial court then assessed appropriate overhead, profit, and equipment costs. This assessment included a correct application of the contract provision governing equipment costs. After exhaustive testimony, the trial court reached its findings about Servi-done’s actual costs, in which this court discerns no clear error.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BB Government Services Srl
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
GLJ, Inc.
Armed Services Board of Contract Appeals, 2022
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)
Anthony and Gordon Construction Co.
Armed Services Board of Contract Appeals, 2021
Baistar Mechanical, Inc. v. United States
128 Fed. Cl. 504 (Federal Claims, 2016)
East Coast Repair & Fabrication, LLC v. United States
199 F. Supp. 3d 1006 (E.D. Virginia, 2016)
Vistas Construction of Illinois, Inc.
Armed Services Board of Contract Appeals, 2016
JMR Construction Corp. v. Environmental Assessment & Remediation Management, Inc.
243 Cal. App. 4th 571 (California Court of Appeal, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
931 F.2d 860, 37 Cont. Cas. Fed. 76,082, 1991 U.S. App. LEXIS 6974, 1991 WL 61769, Counsel Stack Legal Research, https://law.counselstack.com/opinion/servidone-construction-corporation-plaintiffcross-appellant-v-the-united-cafc-1991.