BB Government Services Srl

CourtArmed Services Board of Contract Appeals
DecidedMarch 2, 2023
DocketASBCA No. 63255
StatusPublished

This text of BB Government Services Srl (BB Government Services Srl) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BB Government Services Srl, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) BB Government Services Srl ) ASBCA No. 63255 ) Under Contract No. FA5682-18-C-0032 )

APPEARANCE FOR THE APPELLANT: Jonathan A. DeMella, Esq. Davis Wright Tremaine LLP Anchorage, AK

APPEARANCES FOR THE GOVERNMENT: Caryl A. Potter, Esq. Air Force Deputy Chief Trial Attorney Maj Nicole A. Vele, USAF Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SMITH ON THE GOVERNMENT’S MOTIONS TO STRIKE COUNTS I-III FOR LACK OF JURISDICTION AND DISMISS COUNTS II-III FOR FAILURE TO STATE A CLAIM

This appeal involves a contract for BB Government Services Srl (BBGS) to construct an addition to Building 9109 at Aviano Air Base in Italy. BBGS alleges that the existing building structure was inadequate to support a new two-wing plenum gate required by the contract and seeks to recover $121,214.66 in damages for design and construction of a support portal for the new gate. In Count I of its complaint, BBGS asserts that the support portal was extra work for which it is entitled to an equitable adjustment under the changes clause. In Count II of its complaint, BBGS argues that the Air Force provided defective specifications for the project. In Count III of its complaint, BBGS alleges superior knowledge on the part of the Air Force regarding the adequacy of the existing structural support for the new gate. In Count IV of its complaint, BBGS claims that the Air Force ratified BBGC’s entitlement to compensation for the additional work it performed. The Air Force moves to strike Counts I, II, and III for lack of jurisdiction on the grounds that they present claims that were never presented for a contracting officer’s final decision (COFD). In the event Counts II and III are not stricken, the Air Force moves to dismiss Counts II and III for failure to state a claim upon which relief can be granted. We deny the Air Force’s motions 1

1 The Air Force also moves to strike BBGS’s request to recover attorneys’ fees as premature under the Equal Access to Justice Act. However, we already denied BBGS’s EAJA request as premature by Order dated May 23, 2022. STATEMENT OF FACTS FOR PURPOSES OF THE MOTIONS

On September 20, 2018, the Air Force awarded Contract No. FA5682-18-C- 0032 to BBGS for, among other things, the construction of an addition to Building 9109 at Aviano Air Base in Italy, as well as system renovations, repairs, and upgrades to the building (R4, tabs 8 at 5, 9 at 4). The scope of work was described in the contract’s technical specifications (R4, tab 9 at 5) and the total contract price was $1,234,734.86 (R4, tab 8 at 4). 2 This appeal concerns BBGC’s demolition of an existing sliding gate and the design and construction of a new plenum double wing gate to replace it.

The contract specification relevant to the design and build of the new gate stated:

Design and build of two wings plenum gate gates [sic], total size 15.90 x 7.60 mt. for the Paint Room according to the schemes reported on the drawings and UFC 4-211-02 3-5.2.8.2 Norms to assure a laminar air flow surrounding the aircraft during painting, including the modification of the air supply duct system from the air supply grilles to the gate. Design and build shall be complete with tracks, hinges, hardware, sealing gaskets, accessories, lockset, panic hardware on emergency doors, sheet metal air ducts, modifications to systems eventually interfering with the new ones and accessories. Gate shall be complete with wheels, safety devices in accordance with applicable norms, motor, control panel, cabling, accessories and any other item to provide a job in a workmanlike manner and in accordance with applicable norms.

(R4, tab 9 at 187) (footnote omitted)

During the design process for the new gate, BBGS determined that Building 9109’s existing structure was incapable of supporting the weight of the new gate’s wings (compl. ¶ 11). After discussing the issue with the Air Force, BBGS proposed a solution in an email dated January 13, 2020, and notified the Air Force that it believed it was entitled to a contract adjustment to both price and time (R4, tab 33 at 1). By email dated September 15, 2021, BBGS submitted a document it entitled as a request for equitable adjustment (REA) to the Air Force’s contracting officer (CO) (R4,

2 The contract’s scope of work also involved work on Facility 9110 and demolition of Facilities 973 and 974 at Aviano Air Base, but this work was separate and not at issue in this appeal (R4, tab 9 at 4). 2 tab 38). The REA asserted that Building 9109’s existing steel columns were inadequate to support the new gate and that the additional structural work was outside the scope of the contract’s documents and specifications (id. at 7-9). In its REA, BBGS explicitly advised the CO that the purpose of its submission was to recover the additional costs arising from the fact that the existing structure could not support the new gate (id. at 4) and requested an equitable adjustment of €105,493.12 3 in direct costs as a result (id. at 11). By letter dated December 22, 2021, the CO denied BBGS’s REA, informed BBGS that the denial was a final decision, and advised BBGS of its rights to appeal the decision to the Board:

This is the final decision of the Contracting Officer. You may appeal this decision to the agency board of contract appeals. If you decide to appeal, you must, within 90 days from the date you receive this decision, mail or otherwise furnish written notice to the agency board of contract appeals and provide a copy to the Contracting Officer from whose decision this appeal is taken.

(R4, tab 40 at 2) On April 18, 2022, BBGS appealed the CO’s decision to the Board.

DECISION

The Parties’ Contentions

The Air Force moves to strike Counts I, II, and III for lack of jurisdiction on the grounds that they are separate claims from those presented in BBGS’s September 15, 2021 claim and thus have not been the subject of a COFD (gov’t mot. at 1, 8-14; gov’t reply at 4-7). In the event Counts II and III are not stricken, the Air Force moves to dismiss Counts II and III for failure to state a claim upon which relief can be granted (gov’t mot. at 1; gov’t reply at 7-9). BBGS responds by arguing that Counts I, II, and III all stem from the same set of operative facts as its September 15, 2021, REA (app. opp’n at 6-10) and that Counts II and III adequately state claims that meet the Board’s pleading standard (id. at 11-15).

Standard of Review

As the proponent of the Board’s jurisdiction, BBGS bears the burden of establishing jurisdiction by a preponderance of the evidence. CCIE & Co., ASBCA Nos. 58355, 59008, 14-1 BCA ¶ 35,700 at 174,816. The Board’s jurisdictional requirements to hear an appeal cannot be forfeited or waived. See United States v. Cotton, 535 U.S. 625, 630 (2002).

3 This amount is equal to $121,214.66 at Fiscal Year 2022’s budget rate (R4, tab 40 at 1). 3 Counts I, II, and III Stem from the Same Set of Operative Facts as BBGS’s September 15, 2021, Claim

The Board’s jurisdiction under the Contract Disputes Act (CDA) is dependent upon the contractor’s submission of its claim to the CO and a final decision on, or the deemed denial of, the claim. CCIE & Co., ASBCA Nos. 58355, 59008, 14-1 BCA ¶ 35,700 at 174,816. Because the CDA does not define the term “claim,” we look to the Federal Acquisition Regulations (FAR) for a definition. Reflectone, 60 F.3d at 1575; H.L. Smith, Inc. v. Dalton, 49 F.3d 1563, 1564-65 (Fed. Cir. 1995).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Cotton
535 U.S. 625 (Supreme Court, 2002)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Tecom, Inc. v. The United States
732 F.2d 935 (Federal Circuit, 1984)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers
930 F.3d 1354 (Federal Circuit, 2019)
A & D Auto Sales, Inc. v. United States
748 F.3d 1142 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
BB Government Services Srl, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bb-government-services-srl-asbca-2023.