Hejran Hejrat Co. Ltd v. US Army Corps of Engineers

930 F.3d 1354
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 17, 2019
Docket2018-2206
StatusPublished
Cited by18 cases

This text of 930 F.3d 1354 (Hejran Hejrat Co. Ltd v. US Army Corps of Engineers) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers, 930 F.3d 1354 (Fed. Cir. 2019).

Opinion

Dyk, Circuit Judge.

*1356 Hejran Hejrat Co. Ltd. ("HHL") appeals from a decision by the Armed Services Board of Contract Appeals ("Board") dismissing HHL's case for lack of jurisdiction. Because we conclude that there was a request for a final decision by a contracting officer and a final decision entered by the contracting officer, we reverse and remand for further proceedings.

BACKGROUND

This appeal arises from HHL's 2011 contract with the United States Army Corps of Engineers ("USACE") to provide transportation services in Afghanistan. After the contract expired, HHL requested additional compensation from the USACE based on alleged violations of the contract: suspension of work, changes to the contract requirements, and termination of the original contract. After various preliminary submissions, on March 5, 2015, HHL submitted a document entitled "Request for Equitable Adjustment (REA)" with a sworn statement by HHL's Deputy Managing Director having "full management [authority] to ... close out ... the contract." J.A. 70. In that submission, HHL requested that the submission be "treated as a[n] REA," J.A. 74, and requested $4,137,964 in compensation. The contracting officer denied HHL's request on March 26, 2017, in what the contracting officer characterized as the "Government's final determination in this matter." J.A. 116. HHL appealed the decision, but the Board concluded that it did not have jurisdiction because "[a]t no point, in six years of communication with the [USACE], has HHL requested a contracting officer's final decision." J.A. 4.

HHL appealed to our court. We have jurisdiction pursuant to 28 U.S.C. § 1295 (a)(10). We review the Board's determination of its jurisdiction de novo. Reflectone, Inc. v. Dalton , 60 F.3d 1572 , 1575 (Fed. Cir. 1995) (en banc).

DISCUSSION

In order for the Board to have jurisdiction, there must be a final decision by a contracting officer on a claim. Parsons Glob. Servs. v. McHugh , 677 F.3d 1166 , 1170 (Fed. Cir. 2012) (citing 41 U.S.C. § 7103 ). The issue on appeal is whether HHL requested a contracting officer's final decision on a claim, such that the officer's denial constituted a final decision that supported the Board's jurisdiction.

The statute provides that "[e]ach claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision." 41 U.S.C. § 7103 (a)(1). Thus, in order to constitute a claim a contractor must request a final decision by a contracting officer. M. Maropakis Carpentry, Inc. v. United States , 609 F.3d 1323 , 1327 (Fed. Cir. 2010) (citing James M. Ellett Const. Co. v. United States , 93 F.3d 1537 , 1543 (Fed. Cir. 1996) ) ("The CDA ... requires that a claim indicate to the contracting officer that the contractor is requesting a final decision.").

*1357 "[W]e evaluate whether a particular request for payment amounts to a claim based on the [Federal Acquisition Regulations (FARs),] ... the language of the contract in dispute, and the facts of each case." Parsons , 677 F.3d at 1170 . Under the relevant FAR, a claim is defined as "a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in sum certain." FAR 52.233-1(c) (2002).

HHL contends that its March 5, 2015, submission constituted a claim within the meaning of the CDA. There is no dispute that HHL's March 5 submission was under the FAR a "written demand ... seeking, as a matter of right, the payment of money in sum certain." Id. Indeed, the Board found that in its submissions "HHL adequately described five grounds why it is owed more money, and the sum certain being requested for each." J.A. 4.

On appeal the government makes three arguments as to why HHL's submission did not constitute a request for a final decision. First, the government's "[f]oremost" argument is that "HHL's March 5, 2015, submission is styled as a[n] REA, not as a claim . HHL also expressly requested that the document be 'treated as an REA.' " Gov't Br. at 12 (internal citations omitted) (emphasis added). The government's argument that an REA cannot constitute a claim is directly contrary to this court's en banc decision in Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995) (en banc), and subsequent cases. Just as in the current appeal, in Reflectone "[the contractor's] REA satisfie[d] all the requirements listed for a [Contract Disputes Act (CDA) ] 'claim' according to the first sentence of FAR [52.233-1(c) ]," and thus we "conclude[d] that the Board ha[d] jurisdiction to review the [contracting officer]'s denial of [the contractor's] REA." Id. at 1578 . 1

Second, the government argues that "the [March 5] document fails to include any language requesting a final decision." Gov't Br. at 12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
Cobeal Consulting Group
Armed Services Board of Contract Appeals, 2025
In Re SECRETARY OF THE ARMY
Federal Circuit, 2024
Mindseeker, Inc.
Armed Services Board of Contract Appeals, 2024
BB Government Services Srl
Armed Services Board of Contract Appeals, 2023
Zafer Construction Company v. United States
40 F.4th 1365 (Federal Circuit, 2022)
BCC-UIProjects-ZAAZTC Team JV
Armed Services Board of Contract Appeals, 2022
Penna Group, LLC
Armed Services Board of Contract Appeals, 2021
JAAAT Technical Services, LLC
Armed Services Board of Contract Appeals, 2021
Najmaa Alshimal Company
Armed Services Board of Contract Appeals, 2021
BAE Systems Ordance Systems, Inc.
Armed Services Board of Contract Appeals, 2021
SkyQuest Aviation, LLC
Armed Services Board of Contract Appeals, 2021
Constellation NewEnergy, Inc.
Armed Services Board of Contract Appeals, 2020
Archer Western Aviation Partners
Armed Services Board of Contract Appeals, 2020
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
ECC International, LLC
Armed Services Board of Contract Appeals, 2020

Cite This Page — Counsel Stack

Bluebook (online)
930 F.3d 1354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hejran-hejrat-co-ltd-v-us-army-corps-of-engineers-cafc-2019.