Cobeal Consulting Group

CourtArmed Services Board of Contract Appeals
DecidedJanuary 28, 2025
Docket63815
StatusPublished

This text of Cobeal Consulting Group (Cobeal Consulting Group) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cobeal Consulting Group, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Cobeal Consulting Group ) ASBCA No. 63815 ) Under Contract No. W912DQ-21-C-4014 )

APPEARANCE FOR THE APPELLANT: Ms. Sophy Laughing Chief Executive Officer

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Virginia Murray, Esq. Kristine Hauser, Esq. Engineer Trial Attorney U.S. Army Engineer District, Kansas City

OPINION BY ADMINISTRATIVE JUDGE WILSON ON THE GOVERNMENT’S PARTIAL MOTION TO DISMISS FOR LACK OF JURISDICTION

This appeal involves a contract between Cobeal Consulting Group (Cobeal) and the United States Army Corps of Engineers (USACE or government) for the construction of classrooms, simulator spaces, and administrative spaces at the Mexico National Civil Protection School in Mexico City, Mexico. On October 30, 2023, USACE terminated the contract for default. Cobeal alleges that the termination for default was unjustified and seeks to have it converted into a termination for convenience. Additionally, Cobeal raises claims in its complaint for increased costs, return of withheld liquidated damages, and various time extensions of the contract’s duration. USACE moves to dismiss these additional claims on the grounds that they were never presented to a contracting officer (CO) and are therefore outside of the Board’s jurisdiction. Because the Board lacks jurisdiction over appellant’s additional monetary claims, we grant USACE’s motion.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On September 15, 2021, USACE awarded Cobeal Contract No. W912DQ21C4014, a firm fixed-price contract for the construction of the Mexico National Civil Protection School (MNCPS) in Mexico City, Mexico, at a total price of $7,373,976.58 (R4, tabs 7, 8). The contract contained the following clauses: 52.233-1 Disputes (MAY 2014); 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEP 2000); and 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014), which reads in pertinent part:

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. . .

2. By letter dated July 26, 2023, USACE informed Cobeal the following: Your latest schedule submitted for review in July 2023. . . reflects a late completion for End Project on August 21, 2024. Pursuant to clause 52.211-12, “Liquidated Damages”, an amount of $1,540.00 for each calendar day of delay will be held for liquidated damages to the Government by Cobeal Consulting Group beginning on June 25, 2023.

(R4, tab 24)

3. On July 31, 2023, Cobeal submitted a request for equitable adjustment (REA 1) to USACE for an 18% increase in the contract’s total price plus legal fees due to “exchange rate volatility and its unpredictable impact associated with the [] contract” and elimination of the liquidated damages clause and associated fees and the elimination and return of retainage (R4, tab 25 at COE000002-5). The REA did not quantify the amount requested, however Cobeal included the following certification: “This Request for Equitable Adjustment (REA) does not include any costs that already have been reimbursed or that have been separately claimed. COBEAL certifies that the request is made in good faith and that the supporting data are accurate and complete to the best of our company’s knowledge.” (Id. at COE000012. Additionally, the submittal included a request for a “clear and detailed decision” which addresses each specific element and explains the rationale for accepting or rejecting any part of the REA; and an explanation of appeal rights for “appealing the decision to the appropriate forum, such as the U.S. Court of Federal claims or a board of contract appeals.” (Id. at COR 000010)

4. USACE’s CO denied Cobeal’s REA 1 in its entirety via letter dated August 28, 2023, stating that liquidated damages will continue to be withheld and retainage will be handled in accordance with the terms of the contract. The CO added further, “[t]he contract price will not be increased. If you disagree with my position in

2 response to your REA, Cobeal has the right to submit a Certified Claim requesting a Contracting Officer’s Final Decision (COFD) in accordance with FAR 52.233-1 Disputes.” (R4, tab 31) The record does not contain a subsequent request by Cobeal for a COFD relating to the issues contained in REA 1.

5. Based upon Cobeal’s lack of progress due to numerous contractor delays to the project, USACE’s CO issued a Show Cause letter to Cobeal on September 13, 2023 (R4, tab 33).

6. On October 25, 2023, Cobeal submitted a second REA (REA 2) to USACE’s CO seeking $220,172.64, which included costs related to a time extension of 58.45 days for delays to the project caused by “unusually severe weather” ($118,210.97) and a return of liquidated damages ($90,860), plus interest ($11,101.67). This REA did not include a certification. (R4, tab 41)

7. The next week, by letter dated October 30, 2023, the CO terminated the contract for default due to Cobeal’s failure to “prosecute the work on the [MNCPS] contract with the diligence that will ensure its completion within a timely manner” (R4, tab 42 at COE000002). The termination notice did not address any issues relating to REA 2.

8. By letter dated January 22, 2024, Cobeal timely appealed the termination of its contract for default to the Board. Cobeal further mentioned that, in addition to the termination decision, it estimated damages for the project in excess of $4,000,000, and that “[t]he total direct and consequential damages are under review and will be detailed in our official complaint.” The notice did not mention any of the issues contained in REA 1 (e.g. 18% increase in contract price due to exchange rate volatility, elimination of liquidated damages, and elimination and return of retainage) or the August 28, 2023, CO denial of REA 1.

9. On January 24, 2024, the Board docketed Cobeal’s appeal as ASBCA No. 63815.

10. On May 9, 2024, Cobeal filed an extensive (335-page) complaint. In its complaint, Cobeal alleges that the termination for default was unjustified and should thus be converted into a termination for convenience (compl. at 102-22). Cobeal’s complaint also contains monetary claims for numerous alleged cost increases, time extensions, and the return of liquidated damages assessed by USACE. These additional claims include, but are not limited to:

• Claims that defective specifications and design errors increased Cobeal’s costs and delayed its progress, including claims relating to rebar (claims for $96,221.58 3 and $86,796.30), general design errors ($32,436.16), showers ($10,805.47), and HVAC design ($2,071.92) (id. at 29-30, 32)

• A request for the Board to readjust or reimburse $209,070.97 in liquidated damages (id. at 18-19, 84-85)

• A request for $220,172.64 and a 58.45-day extension for weather delays (id. at 18-19)

• Claims for damages resulting from USACE’s alleged material misrepresentations and bad faith relating to the electrical system ($230,988.47) and vox and data-related costs ($106,249.56) (id. at 30-31)

• Claims for increased costs beyond a negotiated modification for asbestos removal and USACE’s alleged failure to disclose the asbestos prior to contract award (claims for $314,075.07, $143,153.26, and $314,004.72; time extensions of 546 and 243 days) (id. at 27, 39)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Cobeal Consulting Group, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cobeal-consulting-group-asbca-2025.