Emily Malone D/B/A Precision Cabinet Company v. The United States

849 F.2d 1441
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 26, 1988
DocketAppeal 88-1021
StatusPublished
Cited by172 cases

This text of 849 F.2d 1441 (Emily Malone D/B/A Precision Cabinet Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emily Malone D/B/A Precision Cabinet Company v. The United States, 849 F.2d 1441 (Fed. Cir. 1988).

Opinion

BISSELL, Circuit Judge.

Emily Malone d/b/a Precision Cabinet Company (Malone) appeals the decision of the Armed Services Board of Contract Appeals (ASBCA) upholding the government’s decision to terminate Malone’s contract for default. Emily Malone d/b/a Precision Cabinet Co., ASBCA Nos. 30383, 30384, 87-2 BCA ¶ 19,758 [available on WEST-LAW, 1987 WL 41055], aff'd on reconsideration, 87-3 BCA ¶ 19,962. We reverse [available on WESTLAW, 1987 WL 40779].

BACKGROUND

The Air Force awarded Malone a contract to paint and refurbish 265 houses at Robins Air Force Base in Warner Robins, Georgia. Malone received a notice to proceed on October 18, 1983.

The contract required Malone to complete and the government to accept Malone’s work on an initial house (exemplar) as a means of establishing workmanship standards before Malone commenced work on other houses. Malone prepared and painted the exemplar, and the contracting officer (CO) inspected it on December 6, 1983. The CO had certain difficulties with Malone’s performance on the exemplar, including the paint color and the coats of paint used. However, the CO merely stated that he wanted time to consider possible changes. Malone, on the other hand, was eager to get to work. The parties, therefore, reached a compromise under which Malone would immediately go to work preparing carport support columns at 65 houses while the CO considered the changes.

The CO testified that he did not accept the exemplar. Malone, however, believed that the CO had accepted it. Therefore, immediately after completing work on the carport columns in late December 1983, Malone began to work on the houses themselves. The CO contributed to Malone’s perception that he had accepted the exemplar in two ways: (1) by failing to object to Malone’s continued performance even though the CO knew what Malone was doing, and (2) by continuing until June 1984 to pay invoices for work performed by Malone.

The contract required surface preparation for painting to include sanding of “bare spots” to eliminate abrupt changes in paint thickness. Malone interpreted “bare spots” to mean places where bare wood or metal showed through surrounding paint. This interpretation, which Malone employed in working on the exemplar, led Malone to sand about 15% of the surface areas painted. Nevertheless, the CO found this sanding work unacceptable, and so communicated with Malone by several letters and in person between February and June 1984. In response, Malone stated that it understood the exemplar set the standard of workmanship for the contract and expressly requested whether that standard had changed. Malone also asked for the government’s interpretation of “bare spots.” The CO refused to respond to either question.

Finally, by letter dated June 15,1984, the CO stated that he had never accepted the exemplar. He also explained the government’s interpretation of “bare spots” to be the existence of any peeled paint even if the peeling did not disclose the original surface. The CO informed Malone that no further payments would be made until Malone took acceptable corrective action. By June 1984, however, Malone had completed about 70% of the work under the contract using the exemplar as its workmanship standard.

Malone refused to re-perform its previous work, but it did try to find a surface preparation acceptable to the government. It succeeded in doing this in early August 1984. This method involved sanding nearly 100% of the surface area. On approving this method, the CO directed Malone to re-perform its earlier work in this way. This would have involved removing the paint already applied, and sanding virtually 100% of the surface area instead of the 15% Malone sanded when relying on the exemplar as its workmanship standard. Malone insisted that it had done the work already performed consistent with the terms of the *1443 contract by complying with the workmanship standard of the exemplar, and refused to re-perform. The government, therefore, terminated the contract for default on November 9, 1984. Malone appealed this action to the ASBCA.

The ASBCA held that Malone had a duty to perform in the face of a dispute absent a material breach of contract by the government, and that no such breach occurred here. Therefore, it denied Malone’s appeal. Malone subsequently appealed to this court.

ISSUES

1. Whether the ASBCA had jurisdiction to entertain Malone’s appeal when Malone had not submitted a claim for money relating to the default termination.

2. Whether the ASBCA erred in holding that the government properly terminated its contract with Malone for default.

OPINION

I

The government contends that the ASBCA had no jurisdiction to hear Malone’s appeal because Malone did not first submit a claim for money to the CO, but merely asked the ASBCA to determine the propriety of the termination for default. According to the government, Malone’s appeal is in the nature of a request for declaratory relief, which the ASBCA has no power to grant.

In support of the government’s assertion, the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 605(a), 607(d) (1982), provides that all contractor claims must be submitted in writing to the CO in order for a board of contract appeals (BCA) to have jurisdiction. It is undisputed that Malone never submitted a written monetary claim to the CO relating to the default termination.

This case, however, concerns a government claim against a contractor. Caselaw supports the proposition that a government decision to terminate a contractor for default is a government claim. Lisbon Contractors, Inc. v. United States, 828 F.2d 759, 764-65 (Fed.Cir.1987) (discussing BCA practice of treating termination for default as government claim, and relying in part on this premise to hold that government bears burden to prove validity of default termination); Z.A.N. Co. v. United States, 6 Cl.Ct. 298, 305-06 (1984) (holding that default termination is government claim); James Reedom, d/b/a J & M Electronic, ASBCA No. 30226, 85-1 BCA ¶ 17,879, at 89,566 [available on WESTLAW, 1985 WL 16514] (explaining that CO decision to terminate contract for default was government claim within meaning of CDA). 1

This position follows directly from the language of the CDA. The only guidance Congress provided concerning the definition of a government claim exists in the language of section 605(a), which states that “[a]ll claims by the government against a contractor relating to a contract shall be the subject of a decision by the contracting officer.” A default termination falls precisely within the contours of this language. The government issues it by CO decision, and it is both adverse to the contractor and relates to the contract because it involves a determination that the contractor has failed to fulfill its contractual duties.

The CDA states that a contractor may appeal a government claim to the appropriate BCA without having to submit a monetary claim of its own to the CO. 41 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trident Engineering & Procurement, P.C.
Armed Services Board of Contract Appeals, 2023
State of Ohio v. United States
Federal Claims, 2022
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2021
John Shaw LLC d/b/a Shaw Building Maintenance
Armed Services Board of Contract Appeals, 2021
KF&S Corp.
Armed Services Board of Contract Appeals, 2020
Matcon Diamond, Inc.
Armed Services Board of Contract Appeals, 2020
State Corps v. United States
Federal Claims, 2019
Emiabata v. United States
Federal Claims, 2018
Paresky v. United States
Federal Claims, 2018
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Zebel LLC v. United States
Federal Claims, 2017
Mw Builders, Inc. v. United States
134 Fed. Cl. 469 (Federal Claims, 2017)
Confidential Informant 59-05071 v. United States
134 Fed. Cl. 698 (Federal Claims, 2017)
Rebish v. United States
134 Fed. Cl. 308 (Federal Claims, 2017)
Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
849 F.2d 1441, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emily-malone-dba-precision-cabinet-company-v-the-united-states-cafc-1988.