State Corps v. United States

CourtUnited States Court of Federal Claims
DecidedFebruary 15, 2019
Docket14-1121
StatusPublished

This text of State Corps v. United States (State Corps v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Corps v. United States, (uscfc 2019).

Opinion

In the United States Court of Federal Claims No. 14-1121C

(E-Filed: February 15, 2019)

) STATE CORPS, ) ) Plaintiff, ) ) Contract Disputes Act, 41 v. ) U.S.C. § 7104(b)(4) (2012); ) Termination for Default; THE UNITED STATES, ) Motion for Summary ) Judgment, RCFC 56(a); Waiver Defendant. ) of Default Not Found. )

R. Dale Holmes, Philadelphia, PA, for plaintiff.

Amanda L. Tantum, Senior Trial Attorney, with whom appeared Chad A. Readler, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, and Allison Kidd- Miller, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, for defendant. Pietro Mistretta, Assistant District Counsel, United States Army Corps of Engineers, of counsel.

OPINION AND ORDER

CAMPBELL-SMITH, Judge. Plaintiff State Corps (also referred to as SC) is an Afghani corporation that was awarded a construction contract for a logistics center in Jariyan al Batnah, Qatar by the United States Army Corps of Engineers (USACE). See ECF No. 1 at 1-3 (plaintiff’s complaint). Defendant terminated the contract for default, and plaintiff now challenges that decision and seeks additional compensation allegedly due to plaintiff under the terms of the contract. See id.

Presently before the court are the parties’ motions for summary judgment. In evaluating the motions, the court considered the following: (1) plaintiff’s revised motion for summary judgment, ECF No. 58; (2) plaintiff’s proposed findings of uncontroverted facts, ECF No. 59; (3) defendant’s response to plaintiff’s proposed findings of uncontroverted facts, ECF No. 63; (4) defendant’s proposed findings of uncontroverted facts, ECF No. 64; (5) defendant’s response to plaintiff’s motion and its cross-motion for summary judgment, ECF No. 67; (6) plaintiff’s response to defendant’s cross-motion and reply in support of its motion, ECF No. 70; (7) plaintiff’s response to defendant’s proposed findings of uncontroverted facts, ECF No. 71; (8) defendant’s reply in support of its cross-motion, ECF No. 75; and (9) defendant’s notice clarifying its proposed findings of uncontroverted facts, ECF No. 77. The court deemed oral argument unnecessary.

For the following reasons, plaintiff’s motion for summary judgment is DENIED, and defendant’s cross-motion for summary judgment is GRANTED.

I. Background

A. Contract Requirements and Performance before July 24, 2013

On August 20, 2012, the USACE awarded plaintiff contract number W912ER-12- C-0046 (the contract), to construct the United States Army Central Logistics Extension Center (ARCENT Center) in Jariyan al Batnah, Qatar, and notified plaintiff of the award on August 21, 2012. See ECF No. 64-1 at 1-3. The contract provided that:

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the dates the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 300 calendar days.

Id. at 20. The USACE issued its notice to proceed on September 27, 2012, see id. at 90, which resulted in a required completion date of July 24, 2013, see id. at 293-94.

Under the terms of the contract, plaintiff was required to submit for approval a variety of items related to its performance, such as: (1) “Shop Drawings” (“Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work”); (2) [“]Product Data” showing the “size, physical appearance and other characteristics of materials or equipment for some portion of the work”; (3) “Physical examples of materials, equipment or workmanship”; and (4) “[O]perating and maintenance [O&M] data” for equipment to allow “the safe and efficient operation, maintenance and repair of the item.” Id. at 50-52. When making such submittals, unless otherwise specified for a particular item, plaintiff was required to allow a minimum of seven calendar days exclusive of mailing time for the USACE’s review and approval process. Id. at 54.

The default clause in the contract states:

If the Contractor refuses or fails to prosecute the work for any separable part, with the diligence that will insure its completion within the time specified in this contract including any extension, or fails to complete the work within

2 this time, the Government may, by written notice to the Contractor, terminate the right to proceed with the work . . . that has been delayed.

ECF No. 64-1 at 37. It further provides that, in the event of a delay in completing the work:

[t]he Contractor’s right to proceed shall not be terminated nor the Contractor charged with damages under this clause, if—

(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor . . .

and

(2) The Contractor, within 10 days from the beginning of any delay (unless extended by the Contracting Officer), notifies the Contracting Officer in writing of the causes of the delay.

Id.

Throughout late 2012 and until the expected completion date of July 24, 2013, numerous issues arose with the contract performance, about which the parties frequently corresponded. See ECF No. 64 at 15-19 (defendant summarizing the course of correspondence); ECF No. 71 at 7 (plaintiff objecting in several instances to the paraphrasing or characterization of specific correspondence, but not objecting to the fact of the correspondence). This course of correspondence included a letter from plaintiff to the contracting officer, dated June 13, 2013, which reads as follows:

This is a formal response to the cure notice that was given to State Corps on the 3rd of June 2013.

First of all, I would like to apologize on behalf of State Corps that it came down to us being issued a cure notice. This is our first Governmental contract in Qatar and we have always tried for successful completion of this project. This is no excuse for being behind on the schedule but unfortunately we had experienced some challenges at the start of the project which included getting the company registered in Qatar and developing our team there.

One of the major challenges we had at the start of the project included the base’s security requirements and getting badges for our staff which delayed our early start and some issues with our previous QCMs and the first Project Manager which put the project 110 days behind the schedule in which [] State Corps received an unsatisfactory notice of no work performed.

3 Now we have the right technical team, Hardworking subcontractor and are done with Badge’s issues and feel that we are able to complete the project according to the contract requirements and time frame.

Despite the fact that we have had good construction performance onsite during last one month, but faced some issues with our QCM program in Qatar which caused some delay in submittal process of the project, Three weeks ago we brought a change to the QCM position of the project and assigned another QC Manager. With his knowledge, expertise and leadership, now we feel that submittal process is becoming a smooth process.

Since the Cure Notice, we have received “A” and “B” codes on 10 out of 18 submittals, 5 Have been submitted to COR which are under review and 3 are being worked and will be submitted to the COR in the next couple of days, during the last 10 days our team have been able to submit the majority of the items which needed to be submitted, It can show the adequacy of our team and efforts of State Corps for successful and soon completion of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
In Re Gabapentin Patent Litigation
503 F.3d 1254 (Federal Circuit, 2007)
Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)
Dairyland Power Cooperative v. United States
16 F.3d 1197 (Federal Circuit, 1994)
Airport Industrial Park, Inc. v. United States
59 Fed. Cl. 332 (Federal Claims, 2004)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Indemnity Insurance Co. of North America v. United States
34 Cont. Cas. Fed. 75,436 (Court of Claims, 1988)
Kennedy v. United States
164 Ct. Cl. 507 (Court of Claims, 1964)
Olson Plumbing & Heating Co. v. United States
602 F.2d 950 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
State Corps v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-corps-v-united-states-uscfc-2019.