Empire Energy Management Systems, Inc. v. James G. Roche, Secretary of the Air Force

362 F.3d 1343, 2004 U.S. App. LEXIS 5512, 2004 WL 574712
CourtCourt of Appeals for the Federal Circuit
DecidedMarch 24, 2004
Docket03-1277
StatusPublished
Cited by34 cases

This text of 362 F.3d 1343 (Empire Energy Management Systems, Inc. v. James G. Roche, Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Energy Management Systems, Inc. v. James G. Roche, Secretary of the Air Force, 362 F.3d 1343, 2004 U.S. App. LEXIS 5512, 2004 WL 574712 (Fed. Cir. 2004).

Opinions

[1345]*1345Opinion for the court filed by Circuit Judge DYK. Dissenting opinion filed by Chief Judge MAYER.

DYK, Circuit Judge.

The Department of the Air Force (“Air Force”) terminated a contract between Empire Energy Management Systems, Inc. (“Empire”) and the Air Force for default. The Armed Services Board of Contract Appeals (“Board”) sustained the Air Force’s default termination. Empire Energy Mgmt. Sys., Inc., ASBCA No. 46741, 03-1 BCA P 32,079, 2002 WL 31501910 (2002). We affirm.

BACKGROUND

On June 10, 1988, Empire and the Air Force entered into a contract under which Empire was to provide cogeneration1 (“co-gen”) of electricity, chilled water, hot water, and steam to MacDill Air Force Base (“MacDill”) for a lengthy period of time concluding on October 6, 2019. The Air Force did not agree to pay for the construction of the plant; Empire was required to furnish “all plant, labor, equipment, [and] engineering and perform all operations necessary to furnish, install, own, operate and maintain a cogeneration plant” at its own expense. Id. at 158,531. Instead, the Air Force contracted only to pay for the utility services provided by the cogen plant, at a discount from the market price. The contract specified a commercial operation date (“COD”) by which Empire was required to have completed commercial operations acceptance tests successfully and to have substantially completed construction of the cogen plant. The contract also required Empire “to comply with all Federal, State and local environmental and archeological laws and regulations.” Id. The contract contained several standard contract clauses from the Federal Acquisition Regulations (“FAR”), including the standard FAR default clause, FAR 52.249-8.2

On June 11, 1990, the Air Force and Empire entered into Modification 6 of the contract, which obligated Empire to construct two cogen plants at MacDill, rather than the original single plant. In Modification 6, the Air Force agreed to lease the site to be used for the purpose of constructing and operating the second cogen plant (the “cogen site”) to Empire for only nominal consideration. The Air Force and Empire subsequently agreed to build only the second cogen plant and to postpone the construction of the first cogen plant. The dispute in this case relates only to the construction of the second cogen plant.3

[1346]*1346The Air Force had previously used land adjacent to the cogen site for washing fuel bladders. To prevent the release of fuel to the surrounding land and storm drains, it had installed an oil-water separator, a device that uses gravity to separate oil and other petroleum products from water, based on their respective densities. Nonetheless, because some petroleum products are water-soluble, the oil-water separator could not completely eliminate potential pollutants from the water, which was discharged to a storm sewer. The oil-water separator and its discharge were subject to regulation by the United States Environmental Protection Agency (“EPA”). After the cogen site was selected, Empire requested information from the Air Force about the environmental conditions at both the cogen site and the site of the oil-water separator, which the Air Force provided.

Shortly after groundbreaking at the co-gen site on February 7, 1991, Empire stopped work on the project because of a dispute with the company through which Empire had arranged financing for the project. This work stoppage continued until May 4, 1992, when the parties executed Modification 7 (“Mod 7”) and a novation agreement. Among other provisions, Mod 7 contained a release of all claims that arose from facts and circumstances that existed prior to Mod 7, with an exception not pertinent here. Mod 7 also provided a new completion schedule for the cogen site and a facility charge to be paid monthly by the Air Force after COD. May 4, 1992, the date Mod 7 was executed, was “the starting date for performance” of the completion schedule, and the COD was set at 300 days from that start date. Empire Energy, 03-1 B.C.A. (CCH) at 158,539. Although the COD was set at 300 days from the starting date, or February 28, 1993, the Air Force agreed not to terminate the contract for default within 480 days of the starting date, or 180 days after the COD.4 Thus, Mod 7 set August 27, 1993, as the first date on which the Air Force could terminate the contract for default (“the termination date”). Mod 7 further provided that the Air Force was required to provide a cure notice allowing Empire at least ten days to cure any default other than the failure to achieve the COD.

Pursuant to the Resource Conservation and Recovery Act of 1976 (“RCRA”), Pub. L. No. 94-580, 90 Stat. 2795 (codified as amended at 42 U.S.C. §§ 6901-87 (2000)), the EPA regulates owners and operators of facilities that generate, transport, treat, store, or dispose of hazardous materials. The EPA’s primary regulation of treatment, storage, and disposal facilities is through the RCRA permitting system. Owners and operators of such facilities must have a RCRA permit for the facility; treatment, storage, or disposal of hazardous waste is prohibited without a permit. 40 C.F.R. § 270.1(b)-(c) (2003); see also 42 U.S.C. § 6925(a). A RCRA permit allows the operation of a facility for treatment, storage, or disposal and outlines the precautions and corrective actions that the [1347]*1347operator must take to protect the environment.

During the work stoppage, the EPA notified the Air Force on August 15, 1991, that it had issued the corrective action portion of a permit for MacDill pursuant to RCRA.5 The permit required the Air Force to conduct a RCRA Facility Investigation (“RFI”) with respect to several solid waste management units (“SWMU”) located throughout MacDill, including the oil-water separator near the cogen site. Although the boundaries of the oil-water separator SWMU are disputed, the Board found that “for purposes of the RFI the [oil-water separator] and an area three to five feet around it was the SWMU.” Empire Energy, 03-1 B.C.A. (CCH) at 158,-549. Thus, the SWMU encompassed only a small portion of the cogen site.6 The permit also provided that the Air Force “shall give notice to the Regional Administrator as soon as possible of any planned physical alterations or additions to the permitted facility.” United States Environmental Protection Agency, Permit No. FLD 570 024 582, HSWA7 Portion of the RCRA Permit (“EPA Permit”), at 8 (1991).

On May 15, 1992, shortly after it had started working again in response to Mod 7, Empire investigated the storm sewer near the oil-water separator, where it allegedly discovered oil-based contaminants. Empire stopped working and requested a stop work order from the Air Force on May 19, 1992, stating that “Empire has just become aware that it is being prevented from proceeding with performance by the presence of an unknown quantity of an environmentally hazardous substance on the project site,” allegedly left by the oil-water separator. (App. at 1063.) The contracting officer, Ms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.S. Aeroteam, Inc.
Armed Services Board of Contract Appeals, 2025
Pinewood Inc. fka PNI Incorporation
Armed Services Board of Contract Appeals, 2025
Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)
Consorzio Stabile GMG S.c.ar.1.
Armed Services Board of Contract Appeals, 2023
Goodloe Marine, Inc.
Armed Services Board of Contract Appeals, 2022
GSC Construction, Inc.
Armed Services Board of Contract Appeals, 2020
cooper/ports America, LLC v. Secretary of Defense
959 F.3d 1373 (Federal Circuit, 2020)
Moonschein Industries LLC
Armed Services Board of Contract Appeals, 2019
Watts Constructors, LLC
Armed Services Board of Contract Appeals, 2019
State Corps v. United States
Federal Claims, 2019
ECC CENTCOM Constructors, LLC
Armed Services Board of Contract Appeals, 2018
Coastal Environmental Group, Inc.
Armed Services Board of Contract Appeals, 2018
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
MOQA-AQYOL JV, LTD.
Armed Services Board of Contract Appeals, 2017
Rda Construction Corp. v. United States
132 Fed. Cl. 732 (Federal Claims, 2017)
Delfasco LLC
Armed Services Board of Contract Appeals, 2017
Quality Trust Inc.
Armed Services Board of Contract Appeals, 2016

Cite This Page — Counsel Stack

Bluebook (online)
362 F.3d 1343, 2004 U.S. App. LEXIS 5512, 2004 WL 574712, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-energy-management-systems-inc-v-james-g-roche-secretary-of-the-cafc-2004.