Watts Constructors, LLC

CourtArmed Services Board of Contract Appeals
DecidedJune 24, 2019
DocketASBCA No. 61518, 61961
StatusPublished

This text of Watts Constructors, LLC (Watts Constructors, LLC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watts Constructors, LLC, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Watts Constructors, LLC ) ASBCA Nos. 61518, 61961 ) Under Contract No. W9128F-14-C-0024 )

APPEARANCES FOR THE APPELLANT: Sara Beiro Farabow, Esq. David A. Blake, Esq. Michael E. Wagner, Jr., Esq. Seyfarth Shaw LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Erin K. Murphy, Esq. Stanley E. Tracey, Esq. Engineer Trial Attorneys U.S. Army Engineers District, Omaha

OPINION BY ADMINISTRATIVE JUDGE MELNICK ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT 1

In ASBCA No. 61518, Watts Constructors, LLC (Watts), has appealed from the government's termination for default of a construction contract at Fort Carson, Colorado. First, it says it was excusably delayed beyond the contract completion date. Second, it contends the government waived its right to terminate. Third and fourth, it argues that the contracting officer abused her discretion by relying upon materially erroneous information and permitting herself to be influenced by a government inspector who made derogatory comments. Fifth, it maintains that, prior to terminating Watts, the government breached the implied duty of good faith and fair dealing by overly inspecting its work.

The government has moved for summary judgment, arguing that the Board may not exercise jurisdiction over the portions of the amended complaint asserting excusable delay or breach of contract. It also suggests that the undisputed facts fail to support either waiver, abuse of discretion, or breach of the duty of good faith and fair dealing. The government's jurisdictional objections are rejected. Summary judgment is entered in

1 The motion also sought a stay while this request for summary judgment remained pending. That was addressed in response to other filings by the parties. We also note as discussed more below that the motion for summary judgment also included portions that were a motion to dismiss. favor of the government upon Watts' waiver and abuse of discretion counts. Summary judgment is denied regarding Watts' allegation of breach of the duty of good faith and fair dealing arising from over inspection.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

The following facts are not the subject of genuine dispute.

1. On July 17, 2014, the United States Army Corps of Engineers (government) awarded the contract identified above to Watts for the design and construction of buildings on Fort Carson (am. compl. 11 18-20; gov't mot. at 2; R4, tabs 3-4). Among the incorporated clauses were Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (JUN 2007); FAR 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996); and FAR 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) (R4, tab 3 at 155-56). After extensions, and except for tangential issues not relevant, the parties established November 22, 2016, as the deadline for contract completion (am. compl. 1140-45; gov't mot. at 3-4).

2. Watts failed to complete performance by November 22, 2016, but continued working (am. compl. and answer 11102-03). 2 On June 19, 2017, the government assessed and withheld from payment to Watts, liquidated damages for the period December 22, 2016 through April 30, 2017 (am. compl. and answer 1103). On July 13, 2017, the parties bilaterally modified the contract, establishing December 21, 201 7 as the new contract completion date (am. compl. and answer 11102, 105; R4, tab 176). The terms of the modification provided that it "allow[ed] continued performance without waiving the Government's rights, including the right to assess liquidated damages until contract completion" (R4, tab 176). Eventually, the government released some previously withheld liquidated damages but continued to assess them going forward, leading to a net assessment ofliquidated damages from January 3 until November 30, 2017 (am. compl. and answer 1108; gov't prop. findings 16; app. stmt. gen. issues 16).

3. In a September 6, 2017 letter to the contracting officer, Watts described a meeting in which the government requested the designer to consider a new wall cavity for a building under construction. Watts noted that if the government elected to proceed it would submit a request for the costs and time related to the extra work (R4, tab 220).

4. On September 20, 2017, the contracting officer sent Watts a cure notice based upon its lack of progress and failure to maintain schedule milestones. According to the notice, Watts 'jeopardized the successful completion of the contract by the contract completion date of December 21, 2017." The contracting officer gave Watts ten days to

2 The answer cited is the one filed November 19, 2018, in ASBCA No. 61518, which responds to the amended complaint of October 19.

2 cure the condition, requiring that Watts provide a recovery plan to complete the work, including an updated project schedule and description of mitigation efforts. She warned that failure to comply could result in notification to Watts' surety of performance issues. She also explained that Watts could be liable for reprocurement costs should the contract be terminated for default. (Am. compl. and answer ,r 113; R4, tab 228) Watts' September 30 response stated it would not complete the project until May 25,.2018, because of labor shortages, government direction to refrain from energizing electrical panels, and the government's suspension of work due to the wall cavity issue (am. compl. and answer ,r 114; R4, tab 234). On December 20, 2017, the contracting officer notified Watts' surety that a termination for default appeared imminent and inquired into whether the surety would arrange to complete the work (gov't prop. findings ,r 7; app. stmt. gen. issues ,r 7; R4, tab 268).

5. Watts did not complete the project by the final extended completion date of December 21, 2017 (am. compl. 115(a), 49; gov't prop. findings ,r 8; app. stmt. gen. issues 1 8). On that date, the contracting officer informed Watts by letter that the government deemed the schedule and completion date to remain in effect. She emphasized that it was not waiving any of its contract rights, expressly reserving the right to terminate for default and to continue assessing liquidated damages (gov't prop. findings ,r 9; app. stmt. gen. issues ,r 9; R4, tab 270).

6. During a January 8, 2018 meeting with Watts, the government agreed to review a resource loaded schedule, to be provided by Watts by January 24, describing how Watts would complete performance by May of 2018. The government doubted Watts could complete the project by that time, but stated it was looking for a realistic proposal. (Am. compl. and answer 11 116-18) A January 16 follow up letter from the contracting officer found that Watts' response to the government's cure notice was not compelling or its delay excusable. It did confirm the agreement to review a resource loaded schedule. The contracting officer emphasized that the December 21, 201 7 completion date remained in effect, that the government did not waive any of its contract rights, and it reserved the right to terminate the contract for default. (Gov't prop. findings ,r 11; app. stmt: gen. issues 1 11; R4, tab 281) On January 24, Watts submitted its proposed schedule for completion by May 24 (am. compl. and answer ,r 120; R4, tab 294 at 8129).

7. On January 30, 2018, the contracting officer terminated the contract for default (gov't prop. findings 1 13; app. stmt. gen. issues 1 13; R4, tab 294). Repeating her finding that Watts had failed to provide compelling reasons not to terminate, she concluded that the delay in completion did not arise from unforeseeable causes beyond the control and without the fault of both Watts and its subcontractors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Securiforce International America, LLC v. United States
879 F.3d 1354 (Federal Circuit, 2018)
Labatte v. United States
899 F.3d 1373 (Federal Circuit, 2018)
Dobyns v. United States
915 F.3d 733 (Federal Circuit, 2019)
Durable Metal Products, Inc. v. United States
36 Cont. Cas. Fed. 75,897 (Court of Claims, 1990)
Hoel-Steffen Construction Co. v. United States
456 F.2d 760 (Court of Claims, 1972)
Daydanyon Corp. v. United States Defense Logistics Agency
673 F. App'x 997 (Federal Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Watts Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watts-constructors-llc-asbca-2019.