K-Con Building Systems, Inc. v. United States

778 F.3d 1000, 2015 U.S. App. LEXIS 2205, 2015 WL 570935
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 12, 2015
Docket2014-5062
StatusPublished
Cited by145 cases

This text of 778 F.3d 1000 (K-Con Building Systems, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K-Con Building Systems, Inc. v. United States, 778 F.3d 1000, 2015 U.S. App. LEXIS 2205, 2015 WL 570935 (Fed. Cir. 2015).

Opinion

TARANTO, Circuit Judge.

K-Con Building Systems, Inc., entered into a contract with the federal government to construct a building for the Coast Guard. Once K-Con finished, the government imposed liquidated damages for delay in completion. . K-Con sued in the Court of Federal Claims, seeking two forms of relief. First, it requested remission of the liquidated damages on two grounds — that the contract’s liquidated-damages clause was unenforceable and that K-Con was entitled to an extension of the completion date. Second, it requested additional compensation based on work performed in response to government requests that K-Con alleges amounted to contract changes. The Court of Federal Claims held that the contract’s liquidated-damáges clause is enforceable and that K-Con did not comply with the written-notice precondition for invoking the contract clause governing changes. It also held that K-Con’s claim for an extension on the completion date must be dismissed for lack of jurisdiction. We affirm.

Background

On January 20, 2004, K-Con entered into a contract with the Coast Guard, under which K-Con would construct a “cutter support team building” in Port Huron, Michigan, for $582,641. The project was to be completed by November 20, 2004, with K-Con agreeing to pay $589 in liquidated damages for each day of delay. On May 23, 2005, the Coast Guard accepted the building as substantially complete. It withheld payment of $109,554 as liquidated damages for what it calculated to be tardiness of 186 days. No party challenges the calculation.

On July 28, 2005, K-Con sent a letter to the government 'contracting officer requesting remission of the liquidated damages. “wrongfully withheld from the con *1004 tract.” J.A. 259, Letter from K-Con to Contracting Officer (July 8, 2005) (first letter). As grounds for remission, K-Con asserted that the “liquidated damages [constituted] an impermissible penalty” and that the Coast Guard “failed to issue extensions to the completion date as a result of changes to the contract.” Id. It provided no details regarding its request for a time extension based on contract changes. After the contracting officer denied K-Con’s request for remission, K-Con sued in the Court of Federal Claims under the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613 (2006). 1 K-Con sought remission of $109,554 plus interest in liquidated damages on the two grounds asserted in its July 28, 2005 letter. Original Complaint, K-Con Bldg. Sys., Inc. v. United States, No. 05-01054C (Fed.Cl. Sept. 30, 2005).

On December 15, 2006, while litigation in the Court of Federal Claims was underway, K-Con submitted a second letter to the contracting officer. J.A. 263-64, Letter from K-Con to Contracting Officer (Dec. 15, 2006) (second letter). The second letter extensively details the contract changes allegedly made by the Coast Guard during the contract term and asks for a new remedy — $196,126.38 for additional work necessitated by the changes— as well as an extension of the completion date of the contract. The contracting officer denied K-Con’s requests. K-Con then amended its complaint in the Court of Federal Claims to add allegations about the matter covered in its second letter and to seek, beyond the liquidated-damages relief, a judgment of $196,126.38 and a 186-day extension. Amended Complaint, K-Con Bldg. Sys., No. 05-01054C (Fed.Cl. Mar. 18, 2007).

The Court of Federal Claims first ruled, in deciding an initial government motion for summary judgment, that the contract’s liquidated-damages clause is enforceable. The court later issued two rulings in deciding a second government motion for summary judgment. It held that K-Con did not provide valid written notice regarding contract changes and therefore had not satisfied a precondition to claiming additional compensation under the contract’s changes clause. And it dismissed, for lack of jurisdiction, K-Con’s time-extension claim for remission of liquidated damages.

K-Con appeals all three rulings. We have jurisdiction under 28 U.S.C. § 1295(a)(3).

Discussion

Whether the Court of Federal Claims had jurisdiction under the CDA is a question of law we decide de novo. Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed.Cir.1995) (en banc). A plaintiff “bears the burden of establishing subject matter jurisdiction by a preponderance of the evidence.” Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir.1988). “[W]e review a grant of summary judgment by the Court of Federal Claims de novo, drawing justifiable factual inferences in favor of the party opposing the judgment.” Long Island Sav. Bank, FSB v. United States, 503 F.3d 1234, 1244 (Fed.Cir.2007). “Once the moving party has satisfied its initial burden, the opposing party must establish a genuine issue of material fact and cannot rest on mere allegations, but must present actual evidence.” Id.

A

Before turning to the merits, we must determine which issues the Court of *1005 Federal Claims had jurisdiction to decide under the CDA. “The CDA grants [the Court of Federal Claims] jurisdiction over actions brought on claims within twelve months of a contracting officer’s final decision.” James M. Ellett Constr. Co. v. United States, 93 F.3d 1537,1541 (Fed.Cir.1996) (citing 41 U.S.C. § 609(a)). Jurisdiction requires both that a claim meeting certain requirements have been submitted to the relevant contracting officer and that the contracting officer have issued a final decision on that claim. Id. at 1541-42.

A claim is “‘a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.’ ” Refiectone, 60 F.3d at 1575 (quoting regulation then codified at 48 C.F.R. § 33.201; current version at 48 C.F.R. § 52.2331). A claim need not “be submitted in any particular form or use any particular wording ... [, but it must provide] a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maint., Inc. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Youmans v. United States
Federal Claims, 2025
Shoreline Foundation, Inc.
Armed Services Board of Contract Appeals, 2024
MTS General Trading & Construction
Armed Services Board of Contract Appeals, 2024
SBA Contracting, LLC
Armed Services Board of Contract Appeals, 2023
Chugach Federal Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
J&J Maintenance, Inc., d/b/a J&J Worldwide Services
Armed Services Board of Contract Appeals, 2023
Fidelity & Deposit Company of Maryland
Armed Services Board of Contract Appeals, 2023
OSC Solutions, Inc.
Armed Services Board of Contract Appeals, 2023
M. Nicolas Enterprises, Llc.
Federal Claims, 2021
McLarnon v. United States
Federal Claims, 2021
Blanchard's Contracting, LLC
Armed Services Board of Contract Appeals, 2021
Yates v. United States
Federal Claims, 2020
Kiewit Infrastructure West Co. v. United States
972 F.3d 1322 (Federal Circuit, 2020)
Alfajer, Ltd.
Armed Services Board of Contract Appeals, 2020
Css, LLC v. United States
Federal Claims, 2020

Cite This Page — Counsel Stack

Bluebook (online)
778 F.3d 1000, 2015 U.S. App. LEXIS 2205, 2015 WL 570935, Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-con-building-systems-inc-v-united-states-cafc-2015.