Alfajer, Ltd.

CourtArmed Services Board of Contract Appeals
DecidedJuly 23, 2020
DocketASBCA No. 62125
StatusPublished

This text of Alfajer, Ltd. (Alfajer, Ltd.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alfajer, Ltd., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Alfajer, Ltd. ) ASBCA No. 62125 ) Under Contract No. W91B4N-18-A-5006 )

APPEARANCE FOR THE APPELLANT: Walt Pennington, Esq. Pennington Law Firm San Diego, CA

APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney MAJ Nicholas Lucchetti, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT ON THE GOVERNMENT’S MOTION TO DISMISS

This dispute concerns the loss of equipment connected to the performance of call number W91B4N19F5034 (the call or the contract) under blanket purchase agreement (BPA) No. W91B4N-18-A-5006 (the BPA) for the United States Army (Army or the government) to lease equipment from Alfajer, Ltd. (Alfajer or appellant). Appellant’s complaint contains four counts concerning the government’s failure to ensure Alfajer could safely transport required equipment or refusal to pay for damaged equipment: I) breach of contract; II) breach of good faith and fair dealing; III) superior knowledge; and IV) quantum valebant. The government filed a motion to dismiss for lack of jurisdiction and a motion to strike. The government requests we dismiss Counts I through III as lacking jurisdiction because the claims have not yet been before the contracting officer (CO) and to strike Count IV as either an equitable remedy under an implied-in-law theory that we do not have jurisdiction to hear or, in the alternative that it was not submitted to the CO. Appellant responded that the government did not cite a particular rule from the Federal Rules of Civil Procedure for its motion to dismiss Counts I through III and that the facts were asserted in the claim to the CO, just not the legal theories. Further, appellant states that we are not permitted to strike Count IV and requests additional time to respond if we converted the motion to strike, to a motion for summary judgment. The government replied, disputing appellant’s arguments for Counts I through III and also standing by its theory that we strike Count IV. We deny the government’s motion, in part, and grant it, in part. STATEMENT OF FACTS (SOF) FOR THE PURPOSES OF THE GOVERNMENT’S MOTIONS

1. On August 8, 2018, the government issued a BPA with a BPA dollar limit of $93,000,000 and order limit of $1,500,000. The period of performance was August 8, 2018 through August 7, 2023. (R4, tab 2)

2. Among other clauses, the BPA included Defense Federal Acquisition Regulation Supplement (DFARS) 252.225-7995, CONTRACTOR PERSONNEL PERFORMING IN THE UNITED STATES CENTRAL COMMAND AREA OF RESPONSIBILITY (Deviation 2017-O0004) (SEP 2017) (R4, tab 2 at 000124-31). The clause generally placed the risk of working in dangerous conditions on appellant in paragraph (b)(2): “Contract performance in USCENTCOM AOR may require work in dangerous or austere conditions. Except as otherwise provided in the contract, the Contractor accepts the risks associated with required contract performance in such operations” (R4, tab 2 at 000125). Paragraph (b)(3) allowed contractor personnel to carry weapons for self-defense: “When authorized in accordance with paragraph (j) of this clause to carry arms for personal protection, contractor personnel are only authorized to use force for individual self-defense” (R4, tab 2 at 000125). Paragraph (j) explained procedures to allow contractors to carry weapons for self-defense (R4, tab 2 at 000130).

3. On December 3, 2018, the parties entered into the call in question in this dispute under the BPA. The call required six-month leases for ten different categories of equipment and a Defense Base Act insurance contract line item number (CLIN). The call did not include purchasing any equipment. (R4, tab 4 at 000160-65)

4. The call included a performance work statement (PWS) that included security requirements for getting equipment to and from the military installation. Specifically, Section 1.6.8. Security Requirements added: “The Contractor is required to provide his own security to escort all the MHE upon the initial delivery to MSS Thompson, and the final retrieval of the MHE from MSS Thompson upon contract completion/expiration[.]” (R4, tab 4A at 000171)

5. On February 12, 2019, appellant filed a certified claim with the CO. Appellant claimed $355,000. Appellant stated that the costs arose from alleged hijacked equipment. First, on the way to providing the equipment, appellant alleged that one of its forklifts was hijacked. Then, the contract was supposed to be for six months but was cut short to less than two months in duration. While demobilizing, more equipment was allegedly hijacked. Further, although appellant asked for 20-25 days to demobilize, the government required demobilization promptly. (R4, tab 13 at 000222)

2 6. The CO issued a final decision, dated April 8, 2019 denying the claim, stating that the risk was on the contractor in a firm-fixed price contract. Appellant acknowledged receipt on May 30, 2019. (R4, tab 19)

7. On July 5, 2019, appellant timely appealed, which was docketed as ASBCA No. 62125.

8. Appellant filed its complaint with its appeal. In its complaint, appellant focused on its assertions that the government failed to provide safe transport or protect Alfajer’s equipment and the government’s prior knowledge of such attacks (compl. ¶¶ 7, 10-12, 26). Appellant listed four counts in its complaint. Count I was a breach of contract for the Army’s refusal to pay for seized equipment and other amounts allegedly due (id. ¶ 25). Count II was a breach of implied covenant of good faith and fair dealing because the government received a benefit of the equipment without providing sufficient security for the equipment (id. ¶¶ 39-42). Count III was for breach of contract based upon the government’s superior knowledge of the enemy controlled area and failure to provide safe passage plus the requirement for immediate removal of the equipment (id. ¶¶ 44-45). Count IV was for quantum valebant, specifically, that the government received a benefit in the form of equipment that was hijacked and seized so the government is responsible for the cost of the equipment regardless of the fact that no contract for purchasing the equipment existed (id. ¶ 48).

DECISION

“To determine whether a claim is new we examine whether it derives from the same set of common or related operative facts as the claim presented to the contracting officer and seeks the same or similar relief.” Parwan Group Co., ASBCA No. 60657, 18-1 BCA ¶ 37,082 at 180,495 (citing Scott Timber Co. v. United States, 333 F.3d 1358, 1365 (Fed. Cir. 2003); The Public Warehousing Co., ASBCA No. 56022, 11-2 BCA ¶ 34,788 at 171,227). If the set of common or operative facts are essentially the same as the ones presented in the claim, then they are considered to be within the scope of the appeal. Parwan Group Co., 18-1 BCA ¶ 37,082 at 180,495 (citing MACH II, ASBCA No. 56630, 10-1 BCA ¶ 34,357 at 169,673). A new legal theory that is based on the same operative facts does not constitute a new claim, nor do additional facts that do not alter the nature of the original claim. Parwan Group Co., 18-1 BCA ¶ 37,082 at 180,495 (citing Trepte Constr. Co., ASBCA No. 38555, 90-1 BCA ¶ 22,595 at 113,385-86). Put simply, the claim must give the CO adequate notice of appellant’s claim, clearly and unequivocally. Parwan Group Co., 18-1 BCA ¶ 37,082 at 180,495 (citing K-Con Bldg. Sys., Inc. v. United States, 778 F.3d 1000, 1005 (Fed. Cir. 2015)); see also Scott Timber Co., 333 F.3d at 1365 (quoting Contract Cleaning Maint., Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barrett Refining Corporation v. United States
242 F.3d 1055 (Federal Circuit, 2001)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Alfajer, Ltd., Counsel Stack Legal Research, https://law.counselstack.com/opinion/alfajer-ltd-asbca-2020.