Dj Manufacturing Corporation v. United States

86 F.3d 1130, 1996 WL 316426
CourtCourt of Appeals for the Federal Circuit
DecidedAugust 19, 1996
Docket95-5128
StatusPublished
Cited by25 cases

This text of 86 F.3d 1130 (Dj Manufacturing Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dj Manufacturing Corporation v. United States, 86 F.3d 1130, 1996 WL 316426 (Fed. Cir. 1996).

Opinion

BRYSON, Circuit Judge.

DJ Manufacturing Corporation (DJ) appeals from a decision of the United States Court of Federal Claims granting summary judgment to the government. DJ argued that the liquidated damages clause in the contract between the parties was unenforceable as a penalty. The trial court rejected that argument, DJ Mfg. Corp. v. United States, 33 Fed. Cl. 357 (Fed.C1.1995), as do we.

I

In January 1991, the government solicited an offer from DJ for 283,695 combat field packs to support troops who were then participating in Operation Desert Storm. The solicitation documents set forth a delivery schedule, sought accelerated delivery if possible, and provided for liquidated damages for late delivery. The parties negotiated a contract, which became effective on February 14, 1991. Like the underlying solicitation documents, the contract provided that, for each article delivered after the date fixed in the contract, liquidated damages would be assessed at % of one percent of the contract price for each day of delay.

DJ missed several deliveiy deadlines. In accordance with the liquidated damages clause, the government withheld payment in the amount of $663,266.92, a reduction of about 8 percent of the total contract price of $8,493,828.

DJ filed suit in the Court of Federal Claims to recover the withheld amount, contending that the liquidated damages clause constituted an unenforceable penalty. The government moved for summary judgment. In support of its motion, the government submitted a declaration by an Army logistics management specialist, who stated that possession of the field packs was essential to the troops’ combat readiness. In addition, the government submitted a declaration from the contracting officer, who stated that all contracts for items to be used in Operation Desert Shield/Desert Storm contained liquidated damages clauses for late delivery because of the need to get war items to the soldiers quickly.

*1133 In response to the government’s motion, DJ produced an affidavit of its president, who stated that the rate set forth in the liquidated damages clause “does not seem related to any specific need with respect to the item in question or the time-frame, but, rather, seems to be a fairly standard rate used in many solicitations for many different items.” The affidavit listed several other government contracts and solicitations that allegedly contained clauses setting liquidated damages at the same rate. DJ argued that there was therefore a disputed issue of material fact as to whether the contracting officer had “used a standard rate, historically employed by [the agency]” and had made “no attempt to forecast just compensation.”

The Court of Federal Claims granted the government’s motion. At the outset, the court held that DJ bore the burden of establishing that the liquidated damages clause was unenforceable, and that in order to avoid summary judgment DJ had to point to evidence raising a triable question of fact with respect to that issue. The court then recited the rule that a liquidated damages clause is enforceable if the harm that would be caused by a breach is difficult to estimate and the amount or rate fixed as liquidated damages is a reasonable forecast of the loss that may be caused by the breach.

As to the first element, the court characterized this ease as presenting “a paradigmatic example of a situation where accurate estimation of the damages resulting from delays in delivery is difficult, if not impossible.” As to the second element, the court rejected DJ’s argument that in order to determine the reasonableness of the liquidated damages, it was necessary to inquire into the process that the contracting officer followed in reaching the amount that was inserted into the contract. The inquiry, the court explained, is an objective one. “The proper inquiry focuses on whether the amount itself is a reasonable forecast, not whether, as [DJ] seems to suggest, the individual responsible for proposing the rate engaged in a reasonable attempt to forecast damages.” Because DJ failed to offer any evidence that the liquidated damages rate agreed upon in the contract was “greater than that which the government could reasonably suffer as a result of the delayed delivery of the field packs,” the court granted the government’s motion and ordered DJ’s complaint to be dismissed.

II

By fixing in advance the amount to be paid in the event of a breach, liquidated damages clauses save the time and expense of litigating the issue of damages. Such clauses “serve a particularly useful function when damages are uncertain in nature or amount or are unmeasurable,” Priebe & Sons v. United States, 332 U.S. 407, 411, 68 S.Ct. 123, 126, 92 L.Ed. 32 (1947), which is often the case when there is a delay in the completion of a contract for the government. Id.; United States v. Bethlehem Steel Co., 205 U.S. 105, 120, 27 S.Ct. 450, 455-56, 51 L.Ed. 731 (1907); Jennie-O Foods, Inc. v. United States, 580 F.2d 400, 413, 217 Ct.Cl. 314 (1978) (“Costs to the public convenience and the temporary thwarting of the public goals ... are hard to measure with precision.”).

When damages are uncertain or difficult to measure, a liquidated damages clause will be enforced as long as “the amount stipulated for is not so extravagant, or disproportionate to the amount of property loss, as to show that compensation was not the object aimed at or as to imply fraud, mistake, circumvention or oppression.” Wise v. United States, 249 U.S. 361, 365, 39 S.Ct. 303, 304, 63 L.Ed. 647 (1919); see United States v. Bethlehem Steel Co., 205 U.S. at 121, 27 S.Ct. at 456 (“The amount is not so extraordinarily disproportionate to the damage which might result from the [breach], as to show that the parties must have intended a penalty and could not have meant liquidated damages.”). With that narrow exception, “[t]here is no sound reason why persons competent and free to contract may not agree upon this subject as fully as upon any other, or why their agreement, when fairly and understandingly entered into with a view to just compensation for the anticipated loss, should not be enforced.” Wise v. United States, 249 U.S. at 365, 39 S.Ct. at 304; see also Sun Printing & Publishing Ass’n v. Moore, 183 U.S. 642, 674, 22 S.Ct. 240, 253, *1134 46 L.Ed. 366 (1902) (except where “the sum fixed is greatly disproportionate to the presumed actual damages,” a court “has no right to erroneously construe the intention of the parties, when clearly expressed, in the endeavor to make better contracts for them than they have made for themselves”).

A party challenging a liquidated damages clause bears the burden of proving the clause unenforceable. See Jennie-0 Foods, Inc. v. United States, 580 F.2d at 414; Farmers Export Co. v. M/V Georgis Prois, Etc..

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
BCI Construction USA, Inc.
Armed Services Board of Contract Appeals, 2024
Metro Machine dba General Dynamics NASSCO-Norfolk
Armed Services Board of Contract Appeals, 2022
Sauer Incorporated
Armed Services Board of Contract Appeals, 2022
Goodloe Marine, Inc.
Armed Services Board of Contract Appeals, 2022
Maruf Sharif Construction Company
Armed Services Board of Contract Appeals, 2019
Cky Inc. v. United States
Federal Claims, 2018
Dobson Bay Club II DD, LLC v. La Sonrisa De Siena, LLC
393 P.3d 449 (Arizona Supreme Court, 2017)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
ASFA International Construction Industry and Trade, Inc.
Armed Services Board of Contract Appeals, 2014
Dyno Group, Inc.
Armed Services Board of Contract Appeals, 2014
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
BINL, Inc. v. United States
106 Fed. Cl. 26 (Federal Claims, 2012)
Doral Bank PR v. Federal Home Loan Mortgage Corp.
477 F. App'x 31 (Fourth Circuit, 2012)
R.P. Wallace, Inc. v. United States
63 Fed. Cl. 402 (Federal Claims, 2004)
Safeco Credit & Fraley Associates, Inc. v. United States
44 Fed. Cl. 406 (Federal Claims, 1999)
Seaboard Lumber Co. v. United States
42 Cont. Cas. Fed. 77,340 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
86 F.3d 1130, 1996 WL 316426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dj-manufacturing-corporation-v-united-states-cafc-1996.